Reproduced with permission from 15 Journal of Law and Commerce (1995)
175-199
excerpt from review of
Les premières applications jurisprudentielles du droit uniforme
de la vente internationale
by Claude Witz (L.G.D.J. Paris 1995)
Reviewed by Vivian Grosswald Curran
(. . .)
The Buyer's Notice of Lack of Conformity Ironically, the CISG's provisions as to the buyer's duty of giving notice
of the lack of conformity of the goods have been the subject of far more case law than the
seller's failure to provide conforming goods (p. 88). Witz notes in
particular the severity of German judges in applying Article 39 section 1 against the buyer (p.
89).[52] In a case heard by a Stuttgart court, a German buyer of Italian shoes
claimed that it had examined several samples, but that the defects could not have been discovered
before the
buyer's clients brought them to the buyer's attention. The shoes were
delivered on May 25, 1988 and the buyer gave notice of lack of conformity of June 10, 1988. The
court held that the
buyer was in contravention of the "reasonable time" requirement of
Article 39(1), reasoning that the buyer had had a duty to examine the goods minutely and
scrupulously. The court noted in this context that the buyer previously had identified flaws in a
prior shipment, and that it therefore had been on notice of problems
[LG Stuttgart 31 August 1989].
[53] The court thus held notice to be tardy when it was
given sixteen days after delivery. In another case, a German buyer gave notice of defects in cucumbers sold
by a Turkish seller only seven days after inspecting them
[OLG Düsseldorf 8 January
1993]. [54] The parties' contract provided that the buyer's
examination was to take place in Turkey rather than at the place of delivery. The judges found that
the parties had derogated from Article 38 section 2, which provides that, "[i]f the
contract involves carriage of the goods, examination may be deferred until after the goods have
arrived at their destination." The court held that seven days constituted an unreasonably
long time period (pp. 89-90). In yet another case before a German court, notice of lack of conformity
was deemed unreasonable where it was given two months after the delivery of the goods
(mussels), and where the court found that the claimed defect in packaging could have been discovered
immediately (p. 90)
[OLG Frankfurt 20 April 1994].
[55] In other cases before German courts, notice of lack of
conformity was held not to have been given within a reasonable time period when it was given
more than two months after the delivery of shirts of the wrong size
[OLG Düsseldorf 10 February
1994]; [56] and when it was given some three and a half months after
the delivery of shoes with easily identifiable flaws
[LG Berlin 16 September 1992].
[57] Witz suggests that the German courts have been influence in their CISG
decisions by (1) prior judicial solutions reached pursuant to the 1964 Hague Conventions, which
required the buyer
to give notice without delay[58] and (2) precedents decided under German national law (p.
91). The problem of reasonable time periods has been further compounded by a
German
court's failure to differentiate between Article 39 section 1's reference to
a reasonable time
period in the context of giving notice of lack of conformity in goods, and
Article
49's references to reasonable time periods for a buyer's giving notice of
avoiding a contract
(p. 100).[59] Witz's criticism of the severity of German judges is magnified by his
suspicion that a predictable reluctance on the part of judges in other Contracting States to be
equally harsh may lead to disparities in the evolving case law of the various CISG signatory
states. He particularly regrets that guidelines cannot be offered as to uniform time periods
that would satisfy the
CISG's requirements, a problem he attributes to the need for a case by case
approach (pp. 90-91). One might suggest, however, that
Witz's concern should be alleviated precisely because holdings disparate
with respect to definite time periods, and analyzed on a case-by-case basis, implicate
interpretive uniformity to a
far lesser degree than disparities in matters less dependent on the
particular circumstances
of each case.
(. . .)
Go to entire text of Curran review
52. Article 39 § 1 provides that "[t]he buyer
loses the right to rely on a lack of conformity of the goods if he does not give
notice to the seller specifying the nature of the lack of conformity within a
reasonable time after he has discovered it or ought to have discovered
it." 53. LG Stuttgart, 31-08-1989, IPRax 1990, 317 et
seq.
54. OLG Düsseldorf, 08-01-1993, NJW-RR 1993, 999
et
seq. 55. OLG Frankfurt, 20-04-1994, RIW 1994, 593 et
seq. 56. OLG Düsseldorf, 10-02-1994, DB 1994, 2942 et
seq
. 57. LG Berlin, 16-09-1992 (unpublished case) (p. 90 n.46). 58. For the severity of German decisions pursuant to
LUVI
[the 1964 Hague Conventions], Witz refers the reader to Schlechtriem &
Magnus, Internationales Rechtsprechung zu EKG
[ULIS] und EAG [ULF] (1987) (p. 18 n.14). 59. Article 49 § 2 provides that, (. . .)
THE INTERPRETIVE CHALLENGE TO UNIFORMITY
FOOTNOTES
declare the contract avoided unless he does so:
(a) In respect of any late delivery, within a reasonable time after he has
become
aware that delivery has been made;
(b) In respect of any breach other than late delivery, within a reasonable
time:
(i) After he knew or ought to have known of the breach;
(ii) After the expiration of any additional period of time fixed by the
buyer in
accordance with paragraph (1) of article 47, or after the seller has
declared that
he will not perform his obligations within such an additional period; or
(iii) After the expiration of any additional period of time indicated by
the
seller in accordance with paragraph (2) of article 48, or after the buyer
has
declared that he will not accept performance.
Go to Database Directory || Go to CISG Table of Contents || Go to Case Search Form || Go to Bibliography