Reproduced with permission from 16 Journal of International Business
Law 615-668 (1995)
Eric C. Schneider [*]
1. Introduction
Two courts have applied consequential damage provisions found in international
conventions. A court in the United States recently applied provisions of the
United Nations Convention on Contracts for the International Sale of Goods
("CISG" or "Convention").[1] In 1980, the German Supreme Court applied
a substantively similar consequential damage provision of the earlier Hague
Convention on the International Sale of Goods ("ULIS")[2] in a decision that has predictive value for
future applications of the CISG.[3] This
Article will analyze whether these two courts approached consequential damages
in a manner that is more consistent with prior national law than with the
development of a unified international approach to international sales
disputes.[4]
Section 2 of this Article explores a U.S. district court's approach to damages
under the CISG in the case of Delchi Carrier, SpA v. Rotorex Corp.[5] After analyzing the rationale behind
the damage award in Delchi, Section 3 discusses a German Supreme Court
decision applying a provision analogous to the CISG. Finally, Section 4
concludes that the U.S. court applied the international CISG provisions in a
manner consistent with its national law, while the German Court elevated
international principles over national law. Because of the U.S. court's
inability to set aside its own national thinking, this case represents an
unfortunate first decision on the subject of consequential damages under the
CISG.
2. The U.S. Case: Delchi Carrier
In Delchi, the U.S. District Court for the Northern District of New
York applied the consequential damages provisions of the CISG as the
controlling law of the dispute. The Delchi plaintiff
("Buyer") was an Italian manufacturer and seller of air conditioners
and the defendant ("Seller") was a New York corporation. In January
1988, Seller contracted to sell Buyer 10,800 Rotorex model compressors, which
were to be delivered in three installments by May 15, 1988.[6] Buyer, apparently at the time of the
contract, informed Seller that it was going to use the compressors to
manufacture its "Ariele" line of air conditioners, a product which
Buyer expected to sell in the summer of 1988.[7]
On March 26, 1988, Seller sent 2,438 compressors to Buyer and received a
$188,923.46 payment by letters of credit.[8] Seller sent the second installment of
compressors on or around May 9, 1988 and received $129,985.60, also in the form
of letters of credit.[9] When the second
installment was in transit, Buyer, while attempting to install the first
shipment of compressors, discovered that the Rotorex compressors were
nonconforming.[10] Buyer attempted to
correct the nonconformity in various ways in order to avoid damages,[11] but ultimately Buyer rejected the
compressors and cancelled the contract.[12]
After deciding that the CISG[13] governed
this contract, the U.S. district court found that Seller breached the contract
by failing to supply 10,800 conforming compressors.[14] The court then awarded Buyer
"consequential" damages[15] for
those costs incurred which were "a foreseeable result of [Seller's]
breach" and which were "both commercially reasonable and reasonably
foreseeable." [16] These foreseeable
and reasonable damages included: (1) the costs of labor, materials, and
shipping that Buyer incurred because of the unsuccessful attempt to remedy the
nonconforming Rotorex compressors; (2) the costs Buyer incurred to expedite the
delivery of previously ordered Sanyo compressors as replacements in its Ariele
units; (3) the cost of handling and storage of the rejected Rotorex
compressors; (4) the lost profit from lower sales volume of Arieles ordered in
the summer of 1988; and (5) pre-judgment interest.[17] The court rejected Buyer's damage
request for anticipated profits which Buyer claimed on orders which it could
have filled if able to produce more Arieles.[18]
2.1. Background
2.1.1. The Delchi Court's Overview of the CISG
Before ruling on plaintiff's damage claims, the court made a few general
statements about remedies available under the CISG. The district court noted
that the CISG allows lost profit resulting from a diminished volume of sales.[19] Additionally, under CISG Article 74,
Buyer was "entitled to collect monetary damages for [Seller's] breach in
`a sum equal to the loss, including loss of profit,' although not in excess of
the amount reasonably envisioned by the parties."[20]
Contrary to the district court statement, however, CISG Article 74 does not in
fact limit damages to an amount "reasonably envisioned" by both
parties, but rather limits damages in terms of what the breaching party did
actually foresee or could reasonably foresee.[21] Article 74 states:
Instead of referring to the foreseeability language of the CISG, the U.S.
district court stated the test in the narrower terms of New York law.[23] New York law or Italian law might have
been the controlling law in a case involving diversity jurisdiction such as
Delchi had the district court not already decided that the CISG was the
controlling law of the case. New York law differs from the CISG by allowing
consequential damages only when there is evidence that the defendant tacitly
agreed to assume responsibility for such damages.[24] The Delchi court's use of the
"in contemplation of parties" limitation reflects a distinct
development in U.S. law, not the language of CISG Article 74.
The CISG is meant to be interpreted and applied in a manner which promotes
uniformity of application. Matters not expressly governed by the Convention
are to be settled "in conformity with the general principles on which it
is based." [25] The Delchi
court correctly stated that CISG Article 74 is based on a general principle:
that damages should provide the injured party with the benefit of the bargain,
including expectation and reliance damages.[26] This Section examines whether the U.S.
district court's decision in Delchi upheld this general CISG
principle.
Although the district court cites CISG articles as the controlling law on each
item of recovery, analysis of the decision reveals that the court was
influenced more by a national legal tradition, as developed by state law, than
by a policy favoring the unification of international sales law. In applying
the traditional U.S. limitations on damages, the Delchi court used a
more restrictive approach than most state courts and courts of other nations
utilize when applying the CISG.
2.1.2. Limitations on Damages in the United States
It is understandable that a U.S. district court, with its common law and
statutory heritage, might apply the CISG differently than a court in a civil
law jurisdiction. In the U.S. judicial system, unlike in civil law systems,
only the parties are responsible for presenting evidence and must do so under
more restrictive rules of evidence and according to varying levels and shifting
burdens of proof.[27] In determining
consequential damages, the trial judge or jury initially will take evidence and
make findings of fact. As in most other countries, this evidentiary and fact
finding process at early common law was entirely a determination of fact.[28] Judges did not try to control or limit
the jury's award of damages.[29] In the
late eighteenth century, however, when the perception developed that jury
awards were disproportionate, judges developed a number of devices to limit the
fact finding function of juries and to limit awards of consequential damages.[30]
In the United States, trial judges control damage awards through procedural
mechanisms. For example, trial judges rule on the admissibility of evidence,
instruct juries on the law and on the amount of damages allowed, and, if the
damage award is excessive, set aside jury verdicts after trial and order a new
trial.[31] A trial judge's ruling on a
motion for a new trial is a matter of law and subject to appeal and further
analysis by appellate court judges.[32]
In addition to these procedural devices, U.S. courts also developed three
substantive legal doctrines that limit damage awards: avoidability,
foreseeability, and certainty.[33]
Although each of the three traditional limitations on damages seem to involve
factual determinations, U.S. judges routinely make findings "as a matter
of law" on foreseeability, certainty, and avoidability, as well as
causation in situations where reasonable persons could not differ.[34]
This process of ruling "as a matter of law" has led to two
distinguishable practices. Under the first practice, a judge, after allowing a
plaintiff's evidence on damages, may find the evidence inadequate to prove the
plaintiff's case as a matter of law.[35]
Under the second practice, a U.S. judge may bar the presentation of any
evidence of certain types of damage as a matter of law.[36] This second practice of barring the
presentation of evidence has led to stricter limitations on damages in U.S.
courts than in courts of other countries.
An intentional result of these devices and practices is to limit damages to
the amount of actual risk that a defendant undertakes at the time of
contracting.[37] The practice of limiting
damages to the risk undertaken was consistent with the historical trend of
limiting damages in an age of industrialization, an age of eschewing damages
which might be a disincentive to contracting.[38] Although the recent trend in most U.S.
jurisdictions has been to relax the restrictions on damages -- a trend more
favorable to the injured party[39] --
some states, such as New York, continue to restrict consequential damage
awards. The influence of this restrictive view of consequential damages is
evident in the Delchi court's application of the CISG articles.
2.2. Damages Awarded by the Delchi Court
2.2.1. Damages for the Costs of Attempting to Remedy
First, the Delchi court awarded damages to compensate Buyer for costs
of labor, materials, and shipping incurred as a result of its unsuccessful
attempts to remedy the nonconformity of Rotorex's compressors.[40] The court cited no article of the CISG
to support this award, although it did seem to conclude that, under the
criteria of CISG Article 74, the costs of labor, materials, and shipping
"were [expenses] that would not have been incurred without Rotorex's
breach," and that these expenses were "a foreseeable result of
Rotorex's breach."[41]
The Uniform Commercial Code ("U.C.C.")[42] and the
Restatement (Second) of Contracts ("Restatement of
Contracts") [43] would characterize these labor, materials, and shipping
expenses as "incidental" damages, not limited by the foreseeability
test. According to the U.C.C. and Restatement of Contracts, the buyer
must only show these damages are reasonable.[44] Under U.S. law, "incidental
damages" include additional costs incurred after a breach in a reasonable
attempt to avoid loss, even if the attempt is unsuccessful, while
"consequential damages" include such items as injury to person and
property, and lost profits caused by the breach.[45]
The CISG, however, does not provide for the awarding of incidental damages:
it mentions only the recovery of consequential damages,[46] which, under CISG Article 74, must be
"foreseeable" to be recoverable.[47] The lack of a foreseeability
requirement in U.S. law for incidental damages[48] may explain why the judge in
Delchi failed to state any facts that justified the finding that these
labor, material, and shipping expenses were foreseeable.
2.2.2. Damages for the Cost of Expediting Delivery
Second, the Delchi court awarded Buyer damages under CISG Article 77
for the cost of expediting the shipment of previously ordered replacement Sanyo
compressors as part of an unsuccessful attempt to replace the defective Rotorex
compressors.[49] The district court found
that such expedited action did not constitute "cover"[50] because Delchi had ordered the Sanyo
compressors before the formation of the contract with Rotorex.[51] CISG Article 77 provides:
Article 77 is phrased in terms similar to the "avoidability"
limitation on contract damages which developed in early common law.[53] The purpose of Article 77 is the same
as the provisions of the Restatement of Contracts[54] and the U.C.C.[55] which deny recovery of damages that
could have been reasonably avoided.[56]
Although the CISG, the Restatement, and the U.C.C. are phrased in terms
of reducing damage awards to the extent a plaintiff could have reasonably
avoided them, the judge in Delchi turned a shield into a sword and
interpreted CISG Article 77 as requiring mitigation and allowing consequential
damages for costs incurred in the mitigation process.[57] This application of Article 77 is
reminiscent of some U.S. cases criticized for inferring that the injured party
is under a duty to mitigate.[58]
Requiring mitigation can result in a misleading interpretation of the CISG
because Article 77 was not intended to place liability on the injured party for
failing to avoid damages. Rather, the injured party is simply precluded from
recovering damages which could have been reasonably avoided.[59]
It was unnecessary for the Delchi judge to base this recovery of
mitigation expenses on a requirement to mitigate. Additionally, it was
unnecessary to characterize the expedited delivery of Sanyo compressors as
something other than cover.[60] Since the
district court found, in summary fashion, that these mitigating expenses were
"both commercially reasonable and reasonably foreseeable,"[61] such damages were recoverable as
consequential damages under CISG Article 74.[62]
2.2.3. Damages for Handling and Storage Costs
Third, the Delchi court awarded damages for the cost of storage and
handling of the rejected Rotorex compressors.[63] Damages for storing and handling the
rejected product, to the extent that such damages were foreseeable, are clearly
recoverable under CISG Article 74 as consequential damages.[64] Although the district court did not
mention the foreseeability limitation, it did seem to limit the damages award
to those costs which were reasonably incurred.[65] This use of a "reasonable"
limitation, however, is how a U.S. court would treat "incidental"
damages under the U.C.C., which does not require a showing of foreseeability,[66] rather than how a court should treat
such damages under the CISG, which does require foreseeability.
2.2.4. Damages for Lost Profits
Fourth, Delchi claimed damages for lost profits.[67] This claim for lost profits actually
involved two different categories of loss: (1) lost profits on "actual
orders" placed with Delchi in the summer of 1988; and (2) lost profits on
"indicated orders," or, in other words, orders that Delchi claimed
would have been made had more Arieles been available.[68]
To determine whether the two categories of actual lost profits and indicated
lost profits were recoverable from Rotorex, the court examined the evidence and
made determinations regarding three aspects of Delchi's evidence: causation,
foreseeability, and proof of damages with reasonable certainty.[69] Again, the district court analyzed
causation, foreseeability, and reasonable certainty in a manner more consistent
with New York law than with the policy underlying the CISG.
2.2.4.1. Causation
With regard to lost profits from actual orders, the court allowed Delchi's
damages to the extent that these losses were a "foreseeable and direct
result of Rotorex's breach."[70]
Applying this standard, the district court did not allow damages for lost
profits resulting from actual unfilled orders due to factors beside the breach,
including the cancellation of an order for 300 units by one buyer whose
customers had cancelled, or the cancellation of a 50 unit order by Delchi
before it knew of the nonconformity of Rotorex's compressors.[71] Delchi was allowed, however, to recover
its lost profit on a 250 unit order by a British firm, even though the British
firm canceled its order in August 1988 "due to a general lack of
sales."[72] The court found
Delchi's loss on this order recoverable because "those units would
have been already shipped by Delchi in July but for the Rotorex breach .
. . . Thus the lost sales to the British affiliate were a direct
result of Rotorex's breach."[73]
The district court did not find the late cancellation or the weak market for
Arieles in Great Britain to be an intervening cause.[74]
The district court did not allow damages for lost profit on the
"indicated orders," orders which Delchi claimed it could have
received but for the breach, because Delchi failed to prove that the breach
caused these losses and that such losses, if they occurred, were not proved
with reasonable certainty.[75] With
regard to a number of "indicated orders," the district court not only
held that the evidence offered by Delchi was inadmissible because it was
speculative, but also held that Delchi failed to prove that its "inability
to fill such orders was directly attributable to Rotorex's breach."[76]
Article 74 of the CISG, which discusses causation, allows "[d]amages for
breach . . . [for] the loss, including loss of profits, suffered
. . . as a consequence of the breach."[77] The court applied the causation
principles of Article 74 in a manner consistent with U.S. law, namely that to
be recoverable, a loss must be caused in fact by the breach.[78]
2.2.4.2. Foreseeability
The district court found that Delchi's lost profits on actual orders were
a foreseeable result of Rotorex's breach under CISG Article 74.[79] Although the court cited the CISG, it
also stated, in general terms, a test of foreseeability more closely resembling
New York law than the wording of the CISG.
The foreseeability limitation on contract damages in U.S. law developed at
common law[80] from the English case of
Hadley v. Baxendale. [81] The foreseeability limitation is usually stated
as comprising two rules:[82] (1) the
injured party can recover for losses that "may fairly and reasonably be
considered [as] arising naturally, i.e. according to the usual course of
things, from such breach of contract itself;"[83] and (2) that there should be no
consequential damage recovery except "such as may reasonably be supposed
to have been in the contemplation of both parties, at the time they made the
contract, as the probable result of the breach of it."[84] This test has evolved into the
foreseeability limitation[85] now found in
the U.C.C. and the Restatement of Contracts. [86] A similar foreseeability
limitation on damages is found in many other legal systems, as well as in CISG
Article 74.[87]
U.S. jurisdictions have not uniformly applied the foreseeability limitation.
Many state courts interpreted Hadley as requiring evidence that, at the
time of contracting, the parties contemplated the consequential damages later
sought.[88] Some states, such as New
York[89] and Pennsylvania,[90] have held the obligor responsible for
damages only to the extent that he "tacitly agreed to assume
responsibility."[91] Although Pennsylvania later
rejected the tacit agreement test,[92] New
York courts continue to hold that, as a matter of law, a plaintiff cannot
recover consequential damages without evidence demonstrating a defendant's
tacit agreement at the time of contracting to accept responsibility for such
damages.
The "tacit agreement" test has been rejected by most states and the
U.C.C.,[93] but its underlying
justification -- that the obligor should not be responsible for damages
beyond the risk assumed at the time of contracting -- continues to affect
decisionmaking in the United States. This approach of limiting risk to that
assumed at the time of contracting seems to have received new life in 1981 when
the Restatement of Contracts included section 351(3), stating:
Commentary on this section of the Restatement indicates that this
approach is to be used in only exceptional cases, and courts thus have made
little use of it.[95] Nevertheless, many
courts still resist holding a seller liable for damages for prospective lost
profits, and the demise of the tacit agreement test is still uncertain in some
states such as New York.
Another possible source of nonuniform application of the CISG in the United
States is that the U.C.C. has not adopted the foreseeability limitation to
limit breach of warranty damages involving an injury to person or property.
Such breach of warranty damages are recoverable on a showing of proximate cause
alone, regardless of foreseeability.[96]
In this limited instance, contract damages, like tort damages,[97] are not limited by foreseeability. It
is noteworthy that the CISG does not apply to claims for personal injury or
death and does not adopt a different damage article for breach of warranty, but
rather applies Article 74 to all damages for breach of contract.[98]
An area of further concern is the textual difference between the U.C.C., the
Restatement of Contracts, and the CISG regarding the extent to which
consequential damages should be foreseen. The U.C.C. allows "any
loss resulting from general or particular requirements and needs of which the
seller . . . had reason to know."[99] The Restatement allows damages
for foreseeable probable damages,[100] while CISG Article 74 allows for
damages "which the party in breach foresaw or ought to have foreseen
. . . as a possible consequence of the breach." [101] Arguably, the CISG and the U.C.C. are
closer in their textual standards.[102]
In the United States, courts have not asked whether, at the time of contract
formation, the defendant foresaw or could reasonably have foreseen the manner
or particular way in which the loss would result. But, in contract law, unlike
in tort law, the extent of damages recoverable has been limited to the
type of loss that was reasonably foreseeable at the time of making the
contract.[103]
Another textual difference between the CISG and U.S. law concerns whether
foreseeability is based on an objective or a subjective test. In the United
States, foreseeability of consequential damages resulting from a breach of a
contract for the sale of goods is determined by an objective test. The U.C.C.
limits damages to those "of which seller . . . had reason
to know." [104] The Restatement of
Contracts also requires "reason to foresee." [105] Article 74 of the CISG, however, is
written in terms of both an objective and a subjective test of "loss which
the party in breach foresaw or ought to have foreseen." [106] In situations where the breaching
party knows of unusual losses which might occur in case of a later breach,
there is minimal difference between the objective and the subjective
standards.[107]
Few U.S. courts have barred proof of buyer's lost profits on the ground that
the lost profits could not be foreseeable. Judges in the United States apply
various presumptions in making their findings, some of which derive from case
law and some of which derive from comments to the U.C.C.[108] Courts begin with the assumption that
cover is normally possible whenever a breach occurs because one can usually buy
similar goods in a market economy.[109]
Thus, if a contract is breached, it is usually not foreseeable to a seller at
the time of contract formation that if he later breaches, the buyer will not be
able to cover, thus preventing the buyer from performing his resale
obligations. To recover lost profits, a buyer must show that the seller
actually knew or should have known at the time of contract formation that cover
would not be available upon breach.[110]
Additionally, in order to recover damages for lost profits a buyer must show
that the seller knew or should have known that the purchase was for resale and
that the resale would have earned the buyer a profit.[111] A buyer is assisted in his proof by
the U.C.C., which states that if the seller knows that the buyer is purchasing
for resale, then loss of profit within a normal range is foreseeable.[112] In these circumstances, a seller also
is generally liable for foreseeable claims by third parties against a buyer for
his failure to perform resale contracts involving the undelivered goods.[113]
2.2.4.3. Proof With Reasonable Certainty
The "reasonable certainty" limitation -- that damages are
recoverable only to the extent that they can be proved with reasonable
certainty -- is a creation of U.S. law[114] and does not exist in the CISG. The
Delchi court did not cite any CISG authority supporting the proposition
that damages for lost profit must be proved with reasonable certainty.
Instead, the Delchi court imposed the common law damage limitation while
still maintaining that the CISG was the controlling law of the contract. The
district court stated:
The sources cited by the district court make no mention of the CISG, and
Merlite involves a domestic sale. Some form of the reasonable certainty
limitation on damages, even if not called for in the CISG, will be applied by
courts everywhere.[117] If there is a gap
in the CISG on this point, the Delchi court indeed was correct to apply
the law of the forum in a purely procedural matter. As one commentator has
stated, "[p]roblems of proof and certainty of loss are procedural matters
which remain within the province of national law, and procedural conceptions
may still serve as covert limitations on CISG consequential awards."[118]
If U.S. courts apply the certainty limitation to international sales in the
same manner as domestic sales, however, then such courts may be exceeding
procedural determinations. There is a distinction between a court determining
that evidence is unreliable or uncertain and a court not allowing any evidence
of a type of loss because the law of the jurisdiction refuses to allow damages
for that type of loss as a matter of law. In the latter situation, barring
evidence of damage from loss of goodwill is not merely a procedural
determination. Such a restrictive approach could make lost profit from future
sales and goodwill more difficult to obtain in some U.S. jurisdictions than in
the courts of other nations applying the CISG. At the very least, disallowing
evidence of loss of goodwill damage as a matter of law undermines the
predictability and harmonization of litigation results under the CISG.[119]
Another problem with the certainty limitation is a lack of predictable
application by courts. Both the Restatement of Contracts and the U.C.C.
agree that a party can only recover damages for breach of contract that can be
shown with reasonable certainty.[120] It has
been noted, however, that in cases where lost
profit is sought on a collateral transaction, certainty, like foreseeability,
is "a convenient means for keeping within the bounds of reasonable
expectation the risk which litigation imposes upon commercial
enterprise[s]."[121] Furthermore,
"[i]f the test of foreseeability is met, but the court nevertheless
concludes that liability would impose on the party in breach a risk
disproportionate to the rewards that the party stood to gain by the contract,
`the test of certainty is the most usual surrogate.'"[122]
Numerous U.S. court decisions have determined whether evidence of damages for
lost profits were allowed, and whether such damages were proved with sufficient
certainty to be recoverable as consequential damages. Because these decisions
have reached very different conclusions on similar facts, scholars, in an
effort to make outcomes more predictable, have characterized these disparate
results in three categories.[123] These
categories, based on the nature of the buyer and the nature of the lost profit,
include: (1) a middleman-buyer suing for lost resale profit on the goods
seller promised to deliver ("middleman-buyer");[124] (2) a
manufacturer-buyer claiming lost profit due to seller's defective performance
of a promise to deliver goods necessary for production
("manufacturer-buyer");[125] and
(3) a buyer in either category claiming loss of future sales due to customer
dissatisfaction which resulted from seller's breach of a contract to sell goods
("loss of goodwill").[126]
Courts have been more hesitant to award lost profits to buyers in the second
and third categories because "the provision of opportunities for gain may
have a snowball effect: opportunities breed further opportunities."[127] In category two, the
manufacturer-buyer category, courts allowing damages for lost profit have no
difficulty in finding such losses foreseeable.[128] When damages for lost profits are not
allowed, it is usually because of the plaintiff's failure either to prove
damages with reasonable certainty or to prove causation.[129] The "reasonable certainty"
limitation has been less restrictive when applied to established businesses,
which are better able to demonstrate the extent of injury by introducing
records of past profits into evidence,[130] or even evidence of profit records from
similar businesses.[131] On the other
hand, new businesses have not fared as well. In some cases, courts have
precluded new businesses, as a matter of law, from presenting evidence of lost
profits, although now the trend has been to allow such evidence, but only upon
meeting a higher standard of proof.[132]
U.S. judges confronted with category three, loss of goodwill, cases often
disallow evidence of or deny damages for lost goodwill or profits.[133] Damages for
lost goodwill or lost profits based upon potential future sales are not awarded
either because the damages are unforeseeable, not proximately caused by the
breach, or without proof with reasonable certainty.[134] Most claims for loss of goodwill fail
because the court found the evidence insufficient to award damages. However,
U.S. courts also have found, as a matter of law, that loss of goodwill damages
was not subject to proof with reasonable certainty and that evidence of such
loss should be excluded.[135]
The district court in Delchi applied Article 74 to a manufacturer-buyer
situation and did not allow evidence on the amount of damages for future
"indicated orders" on the basis that such evidence would be
"speculative" and there was "no evidence that . . .
Delchi's inability to fill those orders was directly attributable to [or
caused by] Rotorex's breach."[136]
Thus, the court denied damages for loss of "indicated orders," as
have other U.S. courts, because the damages could not be established with
reasonable certainty.
Although most states will allow evidence of damages of loss of goodwill,[137] New York courts, still utilizing the
tacit agreement test, are more likely to rule that such evidence is
inadmissible.[138] Until recently,
Pennsylvania courts also excluded "loss of goodwill" evidence. In
1990, however, the Pennsylvania Supreme Court, having abandoned the "tacit
agreement" test in 1977,[139]
seemed to change Pennsylvania law regarding goodwill damages.[140] The new standard would allow
plaintiffs to pursue claims for goodwill damages under warranty theories,
provided that evidence can be introduced to: (1) establish a causal nexus
between the damages and the breach of warranty; and (2) provide the trier of
fact with a reasonable basis for the calculation of damages.[141]
Anticipated profits do have a current discounted value. Such profits may
involve some uncertainty of proof, but to disallow evidence of such damages as
a matter of law is an unjust denial of compensation which may occur in a U.S.
court applying the CISG.
2.2.5. Pre-Judgment Interest
The Delchi court awarded the plaintiff pre-judgment interest on its
reliance damages as well as on its consequential damages for lost profits under
CISG Article 78.[142] Because Article 78
does not specify the proper interest rate, the district court, in its
"discretion,"[143] ordered that
interest be paid at the U.S. treasury bill rate as set forth in 28 U.S.C.
§ 1961(a).[144]
The district court then ordered the
parties to submit the proper calculation of pre-judgment interest within
fifteen days.[145]
Based on cultural differences between the signatory nations, CISG Article 78,
more so than any other provision of the Convention, was the subject of
disagreement.[146] Religious mandate
prohibits interest in some countries and capitalist and communist societies
have different theories about interest rates.[147] Article 78, as finally adopted, states
that "[i]f a party fails to pay the price or any other sum that is in
arrears, the other party is entitled to interest on it, without prejudice to
any claim for damages recoverable under article 74."[148] Article 78 is silent on whether it
applies to unliquidated as well as liquidated damages. Additionally, Article
78 provides no guidance for calculating such interest and gives no indication
of the circumstances under which pre-judgment interest should be awarded.
There is, however, an indication in prior drafts of the CISG and in some of the
comments by its drafters that pre-judgment interest should not be allowed on
unliquidated damages.[149]
The CISG, as applied in Delchi, is federal law. "Whether or not
to award pre-judgment interest in cases arising under federal law has in the
absence of a statutory directive been placed in the sound discretion of the
district courts"[150] if: (1) the
cause of action arises under the laws and treaties of the United States; (2)
the Convention is silent on the question of pre-judgment interest; and (3) the
policy of the Convention is consistent with such an award.[151]
It is questionable whether the last two criteria for allowing a court
discretion in this matter were met in Delchi. Furthermore, CISG Article
7(2) directs a court as follows:
Arguably, because of the general language of Article 78 as enacted and the
prior rejections of specific language by its drafters, it is appropriate for a
U.S. district court to order pre-judgment interest on unliquidated damages.
CISG Article 78 does allow the award of pre-judgment interest. If one reads
the language of Article 78 -- "if a party fails to pay . . .
any other sum in arrears" -- to include consequential damages, Article
78 also would allow interest on unliquidated damages. The drafting history and
the Article itself, however, seem to indicate that an award of such interest
was not intended by the drafters, or perhaps that the drafters intentionally
left the CISG silent on this issue.
Whether to give pre-judgment interest on unliquidated damages was arguably an
issue that the drafters believed should be properly resolved by resort to the
local conflict of law rules.[153] The
district court in Delchi had diversity jurisdiction over a case
involving a contract between U.S. and Italian corporations. In diversity cases
like Delchi, a federal district court will follow the conflict of laws
rules which prevail in its forum state.[154] Since Delchi did not involve
the foreign relations of the United States, federal common law should not have
been applied.[155] If the district court
in Delchi found the CISG silent on the issue of awarding pre-judgment
interest on unliquidated damages, the district court should have looked to New
York conflict of laws rules in order to determine whether New York or Italian
law controlled the issue. The Delchi court might have determined that
under New York conflicts rules, New York had a "greater interest"[156] in this matter than Italy.
Alternatively, the district court might have determined that the matter of
pre-judgment interest is procedural rather than substantive,[157] and based its recovery on the New York
Code, which allows pre-judgment interest on unliquidated damages for breach of
contract.[158]
The district court, however, engaged in no discussion about these issues, but
instead disregarded CISG Article 7 and the legislative history of CISG Article
78. Although the Delchi court might have come to the same conclusion if
it had analyzed the award under the CISG, a probing analysis of these issues
would have more positively influenced the future application of the CISG.
3. The German Case
The German case concerning consequential damage provisions similar to CISG
Article 74 involved a buyer who attempted to recover damages for future lost
profits due to his customer's dissatisfaction with the delivered goods. The
decision, handed down by the Federal Supreme Court of Germany in 1980,[159] addressed consequential damages for
breach of a contract for the international sale of cheese.
3.1. Factual Background and Lower Court Decisions
Plaintiff ("Seller") was a Dutch exporter of cheese and Defendant
("Buyer") was a German importer of cheese who resold the cheese to
customers, including wholesalers.[160] In
December 1976, after lengthy negotiations, the parties finalized a contract for
the cheese to be delivered to Germany in January 1977.[161] Seller delivered the cheese, but when
Buyer did not pay the full contract price, Seller sued.[162] Buyer claimed that: (1) Seller had
agreed to discount the sales price;[163]
and (2) Seller had breached the contract because three percent of the cheese
delivered was defective.[164]
As a result of this defective delivery, Buyer alleged the following damages:
(1) four of Buyer's customers, who were bulk buyers, discontinued business with
Buyer, costing Buyer 288,000 DM in lost profits over four years; (2) one of
Buyer's customers, Firm H, lost customers as a result of the defective cheese,
for which Buyer had to pay Firm H 80,000 DM; and (3) as a result of losing
business relations with one customer, Firm I, Buyer lost a group delivery
arrangement, which would increase Buyer's transportation costs by 62,400 DM
over four years.[165] At trial, Seller
argued that Buyer's customers left for other reasons.[166]
The trial court[167] found for Seller and
denied Buyer's claims for consequential damages, but reduced the contract price
by three percent for the defective cheese.[168] Buyer then appealed to the
intermediate court of appeals[169] and
renewed its claim for consequential damages.[170] After finding that three percent of
the cheese delivered was defective, the court of appeals affirmed the trial
court's judgment in favor of Seller.[171]
The court of appeals held that Buyer's claims for consequential damages were to
be determined under Article 82 of the Unified Law of the International Sale of
Movable Things [ULIS], the controlling law of the contract.[172]
The [ULIS], however, was superseded in 1990 in Germany by the CISG.[173] Since CISG Article 74 is substantively
identical to [ULIS] Article 82, decisions under [ULIS] Article 82 are informative as
to how German courts will treat consequential damages under the CISG.[174]
In denying Buyer's claims for consequential damages,[175] the court of appeals reasoned that a
buyer can only recover lost profits under [ULIS] Article 82(2) if the Seller can
foresee at the time of the contract that Buyer's customers would discontinue
relations as a consequence of a mere three percent rate of defective
delivery.[176] Based on a survey of trade
associations,[177] the court of appeals
concluded that Seller could not reasonably have foreseen loss from discontinued
relations.[178]
3.2. The German Supreme Court Decision
On further appeal, the German Supreme Court[179] pointed out that the court of appeals
erred in its finding that the contracting parties affirmatively chose [ULIS]
as the controlling law of this contract.[180] Nevertheless, the German Supreme Court
agreed that [ULIS] applied to this contract because "there is nothing
express or implied to rule it out."[181] Additionally, the German Supreme Court
determined that Seller did not contest the fact that three percent of the
cheese delivered under the contract was defective.[182] Finally, the German Supreme Court
noted that the lost profits claimed by Buyer and Firm H might not have been
caused by Seller's breach, but rather by Buyer's delivery of defective cheese
that was in stock prior to the contract with Seller.[183] Seller, however, did not raise this
issue. After reviewing the facts and legal analysis of the appeals court, the
German Supreme Court held that the court of appeals erred in regard to the
issue of foreseeability because it improperly used a survey of trade
organizations to determine trade custom.[184]
The German Supreme Court agreed with the court of appeals that under
[ULIS]
Article 82(1) a seller is liable for lost profit damages resulting from a
delivery of defective goods.[185] Damages
for lost profits, however, are available only to the extent that the seller
should have foreseen the lost profit at the time of contract formation, under
the conditions that the seller knew or should have known would possibly result
from a breach.[186] The test formulated
by the German Supreme Court is what a "reasonable, ideally typical obligor
would expect to happen under the circumstances."[187] Because Seller knew that Buyer was a
middleman, the German Supreme Court determined that it was foreseeable that
Buyer would intend to resell the cheese for a profit.[188] An industry survey could determine
whether profits beyond those lost on the resale of the specific defective
cheese were foreseeable to the Buyer.[189]
In fact, the German Supreme Court cited a prior 1965 German Supreme Court
decision approving the use of survey evidence of trade custom and knowledge.[190]
The German Supreme Court suggested that the proper survey question was:
whether a seller who knows at the time of contract formation that a buyer will
resell the goods should be liable for either a buyer's lost profits due to lost
customers or for a buyer's damages resulting from the buyer's customer losing
sales because of its lost customers, when three percent of a product delivered
on the original contract was defective.[191] Furthermore, a proper survey question
would indicate that, at the time of contract formation, both the seller and the
buyer knew that Dutch imports saturated the German cheese market.[192] With such market saturation, a threat
existed that the customers of middlemen-buyers might readily change suppliers,
even for trivial reasons aside from the substantial defects complained of by
Buyer.[193]
After reviewing the survey and the legal findings of the court below, the
German Supreme Court found that the court of appeals addressed the correct
legal issue.[194] According to the German
Supreme Court, [ULIS] Article 82 requires a subjective and an objective test that
can conclusively be met by a survey demonstrating a trade custom of
foreseeability.[195] The German Supreme
Court, however, found that the court of appeal's survey was procedurally flawed
because the survey did not allow Seller to know the contents of the basic
survey questions, the people surveyed, or the competence of survey
respondents.[196] The appeals court's
decision was remanded for a re-examination of the foreseeability issue.[197]
Because German civil procedure allows a trial de novo in an appeal to
the intermediate court,[198] a court of
appeals can make its own determination of the facts and utilize a survey in
order to determine foreseeability. The German Supreme Court hears appeals on
errors of law only, and, in the instant case, found the flawed survey process
to be an error of law.[199]
The German Supreme Court, although it did articulate a rule of foreseeability,
did not rule as a matter of law whether the damages Buyer suffered due to lost
customers were foreseeable.
3.3. The Background of German Law on Consequential Damages
It is difficult to make generalizations about contract remedies in German
law.[200] It is fair to conclude,
however, that although German law, unlike the U.C.C., favors specific relief in
theory, it shares a common principle with the U.C.C. and the CISG: a remedy is
intended "to put the obligee in the same position, economically speaking,
as he would have enjoyed had the breach not occurred."[201] This underlying philosophy has led
German courts to develop concepts of breach and remedies beyond what the BGB
[Introductory Law to the German Civil Code]
literally allows, particularly in the area of damages for a delivery of
defective goods.[202]
Under the BGB, a buyer can obtain damages for delivery of defective goods for
breach of warranty[203] in only two
situations: (1) when the defect destroys or significantly diminishes the value
or fitness of the goods for ordinary use or for the purpose provided for in the
contract; or (2) when the goods lack the quality which seller expressly
guaranteed.[204] Under BGB section 463,
if the seller has guaranteed that the goods sold have a specific attribute, or
if the seller fails to disclose a known defect, then a buyer may be able either
to rescind the contract or seek a reduction in price and claim damages.[205] Implied guarantees or warranties are
not easily established,[206] however, and
without such a guarantee or without evidence of fraudulent conduct by the
seller, the buyer's remedies under the BGB are limited to either rescission
("Wandelung") or a reduction of the sales price
("Minderung").[207] If the
goods are fungible, then the buyer can demand substitute goods.[208] These remedies are exclusive, and the
BGB does not otherwise allow consequential damages.[209]
Since 1902, German courts have developed an alternative means to make a buyer
whole for a partial breach resulting from a seller's delivery of defective
goods. Buyers can now make a claim on the basis of a "positive
breach," but in order to prevail there must be proof that the seller was
at fault.[210] Section 287 of the Code of
Civil Procedure sets the standard of proof as "mere probability,"
which is arguably a lower standard than reasonable certainty under U.S. law.[211]
The German Supreme Court in applying [ULIS] to the cheese case did not impose
any of these BGB or court developed restrictions on Buyer's right to claim
consequential damages. Instead, the German Supreme Court referred to [ULIS]
Article 82(1) which allows consequential damages without evidence of warranty,
fraud, or fault.[212]
It is questionable whether the German Supreme Court used the principles of
[ULIS], or was influenced equally by national legal doctrines when stating the
standards for determining the recoverable amount of consequential damages. BGB
section 252 sets forth the German Code standard for calculating consequential
damages. Section 252 provides that "damages to be recovered include lost
profits . . . [p]rofit is deemed to be lost which could have been
expected with probability according to the ordinary course of events or in view
of particular circumstances, especially the preparations and provisions
made."[213] Under the BGB, this
probability determination is made at the time of breach.[214] Plaintiff must prove only that the
circumstances referred to in the second sentence of BGB section 252,
"ordinary course of events or particular circumstances," existed.
After proving that these circumstances existed, it is presumed that the profits
would have been earned but for the occurrence of the breach.[215] Defendant, to avoid liability for lost
profit, must then show that "his default [did not] appreciably increase
the objective possibility of loss of a kind that in fact occurred."[216]
The BGB does not distinguish contractual liability from tort liability, and
sections 241 through 304 apply to obligations arising from both.[217] The limitations on consequential
damages set forth in these sections of the BGB include general principles of
avoidability[218] and comparative fault.[219] Furthermore, the BGB does not limit
the recovery of consequential damages to those which are foreseeable.[220]
Early commentary on the BGB suggested an interpretation of BGB section 252
that would limit lost profits to those foreseeable under the circumstances as a
probable consequence of breach.[221]
Until the late 1970s, this interpretation was rejected in favor of an approach
which viewed section 252 as simplifying proof of causation rather than acting
as limiting damages to those that were foreseeable. Section 252 was
interpreted as permitting the use of objective market evidence, such as what
damage reasonable sellers would expect a breach to cause under market
conditions, rather than having to present evidence of the particular subjective
intention the BGB. The traditional test for recovery of consequential damages
was whether the obligor's breach, "as judged by ordinary human standards
at the time of its occurrence, renders more likely damages of the kind actually
suffered."[222]
In the late 1970s, as legal scholars again debated the necessity of adopting a
foreseeability limitation on contract damages,[223] German courts began to apply the
foreseeability limitation to certain types of contract damages.[224] The German cheese case has been cited
as an early example of the development by German courts of the foreseeability
limitation to cases where a defendant, after selling goods to a middleman, is
sued for goodwill damages resulting in lost profits and lost customers because
of the delivery of defective goods.[225]
3.4. The German Supreme Court's Interpretation of [ULIS]
In the cheese case, the German Supreme Court applied [ULIS] doctrine of
foreseeability as a limit on damages for lost profit, using the time of
contract formation, rather than the time of breach, as the vantage point from
which to determine foreseeability.[226]
Given the contemporaneous development by German courts of a foreseeability
limitation, it is difficult to determine if the German Supreme Court's decision
in the cheese case was a faithful application of [ULIS], or merely an
application of a developing doctrine of German national law.
As stated earlier, the German law for damages arising out of the domestic sale
of goods initially "reject[ed] foreseeability as a method of limiting
liability for default in the performance of a contract."[227] Instead, until several years before
the cheese case, courts used a theory of "adequate causation" as the
primary test to determine contract damages.[228] Under the "adequate
causation" test, which German courts still apply,[229] a breaching party "is liable for a
loss if his default appreciably increased the objective possibility of loss of
a kind that in fact occurred."[230]
A breaching party is not liable if the default was, in the ordinary course of
events, a matter of indifference with regard to what actually occurred and only
became a "condition of the occurrence of the loss as a result of unusual
or intervening events."[231] Whether
a breach is an adequate cause is determined by a court applying the objective
standard of an:
Thus, under the "adequate causation" test there is both an objective
and a subjective test of causation, which does not limit, but rather, expands
damage.
In applying [ULIS], the German Supreme Court referred to the subjective and
objective limitations of the foreseeability test.[233] The German Supreme Court held that the
seller is liable for damages that a "reasonable, ideally typical obligor
would know to be a serious consequence of a breach in light of the
circumstances."[234] In reaching its
formulation of foreseeability, the German Supreme Court cited commentaries
comparing the doctrines of foreseeability in numerous other legal systems.[235] Of primary influence were commentaries
on [ULIS] Articles 13 and 82 concerning the meaning of "what a party knew or
should have known."[236] Based on
these commentaries, the German Supreme Court determined that a judge should ask
not "what the obligor in the situation knew or should have known, but what
the `ideal obligor' should have known,"[237] a test that seems to combine
foreseeability with the Court's prior standard of adequate causation.
Whether there is really a significant difference between how German courts
have applied the "adequate causation test" and the way in which most
U.S. courts apply the foreseeability test is a question raised by legal
scholars.[238] Both tests refer to the
recovery of losses that occur "in the ordinary course of things," or
according to the "common experience of mankind."[239] These formulations are similar to the
first rule of Hadley -- that the loss must flow naturally from the
breach.[240] Both the German and the U.S.
tests also seem to employ the second Hadley prong:[241] the German courts use an objective
test to ask what an optimal obligor would expect to happen in the ordinary
course of things, while U.S. courts ask what a reasonable person would expect
to happen.[242] Both German and U.S.
courts first attribute the knowledge of surrounding circumstances to the
reasonable person, knowledge that an ordinary person could normally be expected
to have, and then add the knowledge which the defendant actually had.[243] Despite the similarities, the German
approach of adequate causation, in borderline cases, is thought to be more
favorable to plaintiffs than the foreseeability limitation.[244]
At the time of the cheese case, the German Supreme Court also was aware that
U.S. jurisdictions did not uniformly apply the test of foreseeability.[245] One author cited by the German Supreme
Court concluded, after a description of the development of the
"contemplation of the parties" test in the United States, that
foreseeability "is not simply determined by empirical standards but
involves a question of policy . . . [it is] essentially a question of
allocating risks and losses."[246]
Clearly, the German Supreme Court did not use a "tacit
agreement-contemplation of the parties" test of foreseeability under [ULIS]. The German Supreme Court's application of foreseeability more closely
resembled that of the U.S. courts that do not use the tacit agreement test.
Now that German courts take into account both the adequate causation test and
the foreseeability test, one would expect that damages would be granted on a
more limited basis in German judgments. Cases cited as evidence of the German
development of the foreseeability limitation tend to be generous in determining
what risks the ideal obligor has undertaken,[247] perhaps because of a lingering
hesitancy to stray too far from a tradition based on adequate causation. It
also is not surprising that a German court would apply the newly adopted
foreseeability test of the ULIS or the CISG in a manner consistent with its
prior national law, which is generally more favorable to the obligee than the
obligor.
The German Supreme Court's decision in the cheese case does, however, clearly
reflect German legal tradition in the manner in which foreseeability was
proved. The proof used by both the court of appeals and German Supreme Court
was a survey of trade associations.[248]
The German Supreme Court justified this evidentiary device on the basis of a
1966 decision under German law.[249] This
approach is compatible with German procedure, under which the intermediate
court of appeals effectively conducts a trial de novo. [250]
An appellate court in the United States would not utilize a survey of persons
in the cheese industry, as did the German Court of Appeals. In the United
States, even at the trial court level, such evidence would be considered
hearsay and likely would be excluded on either of two grounds: (1) it deprives
the parties of the right to cross-examination and (2) it lacks probative
value.[251]
In the United States, an expert may testify based upon a poll, but a
party wishing to use a poll should have available "a complete record of
the methods by which the universe and sample were selected, and of the
techniques for selecting and instructing the interviewers."[252] Additionally, interviewers should be
available for cross-examination.[253] The
German Supreme Court is generally more willing to use opinion polls, in
accordance with a German legal tradition that predates the adoption of
[ULIS].
In the cheese case, however, the German Supreme Court indicated in its opinion
that it had a healthy skepticism of the reliability of opinion polls, insisting
that the party seeking to use the survey divulge the fundamental structure of
the survey to the other party.[254]
4. Conclusion
In both of the cases discussed, courts denied a buyer's damage claims for both
lost profit damages on prospective contracts and loss of goodwill because of
lack of sufficient proof. That the courts arrived at similar conclusions was
not, however, due to the identical application of the principles of similar
international sales convention articles. The U.S. district court in
Delchi referred briefly to scholarly comments[255] on the
CISG before applying the CISG in a manner totally consistent with the law of
New York, which was the seller's place of business. The district court did not
use a more detailed analysis, which was readily available in the literature,[256] nor make any other attempt to "set
aside national thinking."[257]
The German Supreme Court, in applying the ULIS . . . in the cheese
case, made a greater effort to consult the available literature on the
principles underlying the ULIS Convention. The German Supreme Court, in many
particulars, followed international principles rather than its own national
law. In accordance with the ULIS, the German Supreme Court was willing to
allow damages for a delivery of defective goods amounting to only three percent
of the total contract amount, without requiring proof of fault or an express
guarantee of quality. The German Supreme Court cited numerous authorities on
the ULIS and discussed the principle of foreseeability as a limitation on
contract damages for lost profit. The German Supreme Court applied the
foreseeability limitation at the time of contract formation rather than, as
under national law, at the time of breach.
The German Supreme Court also discussed the subjective and objective nature of
the foreseeability limitation under the ULIS, although it finally used an
objective test that resembled both its national tradition of determining
adequate causation and the emerging court-developed doctrine of foreseeability.
The German Supreme Court's decision ultimately rested on a national approach to
adequate causation, foreseeability, and manner of proof. Thus, because of
Germany's less formal rules of evidence and its less limiting application of
foreseeability, plaintiffs such as Delchi would more likely obtain damages for
lost profit or goodwill under the CISG in a German court than in a U.S. court.
Of course, this situation will lead to forum shopping, an outcome the CISG
drafters sought to avoid.
CISG Article 7(1) stresses the "need to promote uniformity in its
application."[258] The Secretariat
Commentary to Article 7 states that "[n]ational rules on sales of goods
are subject to sharp divergences in approach and concept. Thus, it is
especially important to avoid differing constructions of the provisions of this
Convention by national courts, each dependent upon the concepts used in the
legal system of the country of the forum."[259]
Some argue that "[p]roblems of proof and certainty of loss are procedural
matters which remain within the province of national law."[260] Article 7(2) states that any gaps in
the CISG are to be "settled in conformity with the general principles on
which it is based or, in the absence of such principles, in conformity with the
law applicable by virtue of the rules of private international law."[261] Certainly, matters that are clearly
procedural will not be subject to the CISG or any other rules besides those of
the forum. In those U.S. jurisdictions where prospective lost profits and lost
goodwill damages are not recoverable as a matter of law, however, such matters
should be subject to the choice of law determinations in CISG Article 7(2).[262] Perhaps the Delchi court should
have applied CISG Article 7(2) to determine whether under New York conflict
rules the law of Italy was the controlling law of the contract and, if so, how
Italian law applies the foreseeability test to prospective lost profits under
the Italian Code.[263]
That a German court fared better than a U.S. court in referring to and
following the guidelines of legal scholars is, in part, due to the fact that
Germany is a civil law jurisdiction, where courts traditionally give such
literature more weight.[264] The U.S.
court, accustomed to referring more often to code annotations or prior
decisions, was able to rely on neither. By giving terse mention to the CISG
articles at issue, by ignoring the extensive literature on the CISG, and by
interpreting the CISG articles according to New York law without analysis of
the Convention, the U.S. district court created an unfortunate first decision
on the subject of consequential damages under the CISG.
The Delchi decision fulfills a "gloomy prospect,"[265] of which one scholar cited by the
Delchi court warned. There is a "danger . . . that these
tribunals will apply the Convention within the limited context of their own
legal traditions," he cautioned, "exposing in the process the lack of
consensus and resulting ambiguity of certain provisions."[266]
*Associate Dean & Professor of Law,
University of Baltimore School of Law; B.A., University of Connecticut; LL.B.,
University of California, Hastings; LL.M., New York University. The author
thanks Professors Peter Schlechtriem and Albert H. Kritzer for their
suggestions and criticisms of prior drafts. The final draft of this Article is
the author's sole responsibility.
1. See United Nations Convention on Contracts for the
International Sale of Goods, U.N. Doc. A/CONF.97/18 (1980), S. TREATY DOC.
NO. 9, 98th Cong., 1st Sess. 22 (1983), 19 I.L.M. 671 (1980)
[hereinafter CISG].
2. See Convention Relating to a Uniform Law on the
International Sale of Goods, July 1, 1964, 834 U.N.T.S. 107.
3. ULIS Article 82 is the source of and is substantively
similar to CISG Article
74. SeeALBERT H. KRITZER,
GUIDE TO PRACTICAL APPLICATIONS OF THE UNITED NATIONS CONVENTION ON
CONTRACTS FOR THE INTERNATIONAL SALE OF GOODS 477 (1989).
Germany and the United States are now signatories to the CISG. For commentary
on the U.S. adoption of the CISG, see infra note 13.
For commentary on the German adoption of the ULIS and later the CISG, see
infra sections 3 and 4.
4. The problem of differing interpretive approaches to international sales
disputes has been predicted. SeePatrick Thieffry,
Sale of Goods Between French and U.S. Merchants: Choice of Law
Considerations Under the U.N. Convention on Contracts for the International
Sale of Goods, 22 INT'L LAW. 1017,
1021 (1988). For a discussion of damage terminology in civil and common law
jurisdictions, see Ugo Draetta, The Notion of Consequential Damages in
the International Trade Practice: A Merger of Common Law and Civil Law
Concepts 4 INT'L BUS. L.J. 487
(1991).
5. See Delchi Carrier, SpA v. Rotorex Corp., No. 88-CV-1078,
1994 WL 495787 (N.D.N.Y. Sept. 9, 1994). The decision was appealed and
cross-appealed. The court of appeals
affirmed with little comment on the issues raised in this Article, but
remanded on
other grounds. See Delchi Carrier, SpA v. Rotorex Corp., Nos.
95-7182, 95-7186 (2d Cir. Dec. 6, 1995).
6. See id. at *1.
7See id.
8. See id.
9. See id.
10. See id.
11. In an attempt to cure the defect, Delchi shipped substitute
Rotorex grommets to its manufacturing plant, spent 790.5 hours to insert the
special grommets, paid for a shipment of additional Rotorex connectors, and
finally inspected and tested the compressors above what was normally expected.
See id. at *2.
12. See id. at *1.
13. CISG is codified at 15 U.S.C.A. app. (West Supp. 1995). The CISG was
ratified by the U.S. Senate on October 9, 1986, and took effect on January 1,
1988. "Disputes arising out of international sales contracts formed after
January 1, 1988, between merchants from signatory nations may be governed by
the [CISG] rather than the Uniform Commercial Code or foreign sales law, unless
the parties specifically state otherwise." See Eric C. Schneider, The Seller's Right to Cure Under the
Uniform Commercial Code and the United Nations Convention on Contracts for the
International Sale of Goods, 7 ARIZ. J. INT'L &
COMP. L. 69, 69-70 (1989) (footnotes omitted).
14. See Delchi, 1994 WL 495787, at *4-5.
15. Consequential damage generally is defined as "[t]hose losses or injuries
which are a result of an act but are not direct and immediate."
BLACK'S LAW DICTIONARY 390 (6th ed. 1990).
16. Delchi, 1994 WL 495787, at *5.
17. Id. at *5-7.
18. See id. at *6 (holding that "Delchi [cannot]
recover on its claim for additional lost profits in Italy because the amount of
damages, if any, can not be established with reasonable certainty.").
19. See id. (citing JOHN HONNOLD, UNIFORM LAW
FOR INTERNATIONAL SALES § 415 (2d ed. 1991) and
Jeffrey S. Sutton, Comment, Measuring Damages Under the United Nations
Convention on the International Sale of Goods, 50 OHIO
ST. L.J. 737, 747-48 (1989)).
20. Delchi, 1994 WL 495787, at *5.
21. See CISG art. 74,
supra note 1, S. TREATY DOC. NO.
9 at 37, 19 I.L.M. at 688.
22. Id. (emphasis added).
23. "[I]t may fairly be said that the New York courts have generally
purported to follow the `contemplation' test and that the application of this
test has narrowed recovery of damages . . . more than the `had reason
to know' test of the Code." 1 STATE OF NEW YORK LAW REVISION
COMMISSION REPORT, Hearings on the Uniform Commercial
Code, 702 (1980). But see
Arthur G. Murphey, Jr., Consequential Damages in Contracts for the
International Sale of Goods and the Legacy of Hadley, 23
GEO. WASH. J. INT'L L. & ECON. 415, 435 n.103 (1989).
Murphey believes the difference in the tests is only apparent since "[n]o
case has been found in which recovery was denied because the injured party did
not foresee the loss." Id. at 435.
24. See Kenford Co. v. County of Erie, 493 N.E.2d 234
(N.Y. 1986) (Kenford I). In Kenford II, the New
York position was further clarified: "In determining the reasonable
contemplation of the parties, the nature, purpose, and particular
circumstances of the contract known by the parties should be considered, as
well as `what liability the defendant fairly may be supposed to have assumed
consciously, or to have warranted the plaintiff reasonably to suppose that it
assumed, when the contract was made.'" Kenford Co. v. County of Erie, 537
N.E.2d 176, 179 (N.Y. 1989) (citations omitted). For a further discussion of
the foreseeability limitation in U.S. courts, see infra
note 42 and accompanying text.
25. See CISG art. 7, supra note 1, S. TREATY DOC. NO. 9 at
23-24, 19 I.L.M. at 673.
26. The provision of expectation and reliance damages is
consistent with the philosophy of the drafters of the CISG. SeeCommentary on the Draft Convention on Contracts for the
International Sale of Goods, Prepared by the
Secretariat, U.N. Doc. A/CONF.97/5 (1979),
reprinted in UNITED NATIONS CONFERENCE ON
CONTRACTS FOR THE INTERNATIONAL SALE OF GOODS, OFFICIAL RECORDS
at 14, U.N. Doc. A/CONF.97/19, U.N. Sales No. E.81.IV.3 (1981) [hereinafter
Commentary]. A similar principle is found in the
U.C.C. and also underlies U.S. law generally. See
U.C.C. § 1-106(1) (1991) ("The remedies provided by this
Act shall be liberally administered to the end that the aggrieved party may be
put in as good a position as if the other party had fully performed but neither
consequential or special nor penal damages may be had except as specifically
provided in this Act or by other rule of law.").
27. In Germany, a civil law jurisdiction, the evidentiary hearing is dominated by
the court, not by the parties. A plaintiff does, however, usually have the
burden of proving facts establishing a claim beyond a reasonable doubt, but
relies on a general presumption that events generally occur in a normal way
unless there is proof to the contrary. See
GERHARD DANNEMANN, AN INTRODUCTION TO GERMAN CIVIL AND COMMERCIAL LAW 101-03 (1993); JOHN H. MERRYMAN, THE CIVIL LAW TRADITION: AN
INTRODUCTION TO THE LEGAL SYSTEMS OF WESTERN EUROPE AND LATIN AMERICA 111-23 (2d ed. 1985); William B. Fisch, Recent
Developments in West German Civil Procedure, 6
HASTINGS INT'L & COMP. L. REV. 221, 279-82 (1983).
28. See George T. Washington, Damages in
Contract at Common Law II, 48 LAW Q. REV.
90, 108 (1932) "(In the early law the problem of
compensation was treated as one of fact for the jury, subject to certain
mechanisms for checking the abuse of discretion . . . .")
[hereinafter Washington, Damages II].
29. See George T. Washington, Damages in
Contract at Common Law, 47 LAW Q. REV.
345, 351-52 (1931); Washington, Damages II,
supra note 28, at 90.
30. See Washington, Damages II, supra note 28, at 90.
31. E. ALLAN FARNSWORTH, CONTRACTS 873 (2d ed. 1990). 32. Id.
33. Id. at 873-74.
34. See id. at 527 (stating that courts have the
"general power to treat a question of fact as one of `law' if the jury
could reasonably find only one way"); Murphey, supra
note 23, at 466 ("[C]ourts now have a practice of limiting
recovery in the `harsh' case solely by saying that damages [are]
. . . `unforeseeable' not as a matter of fact, but as a matter of
fact and law"). As one observed stated:
Comment, Lost Profits as Contract Damages: Problems of Proof and
Limitations on Recovery, 65 YALE L.J. 992, 1026-27 n.181 (1956)
[hereinafter Lost Profits].
35. See FARNSWORTH,
supra note 31, at 537-38.
36. See id. at 538-39.
37. See Lost Profits,
supra note 34, at 1020.
38. The limitations on damages of causation, foreseeability, and certainty have
been used by U.S. judges to limit "disproportionate damages [that] may
induce defendant and other businessmen in similar occupations to shun bilateral
contracts entirely or to insure against future losses by insisting on
liquidated damages that fall short of full compensation, even when the loss
would not be disproportionate". Lost Profits,
supra note 34, at 996.
39. The trend of awarding consequential damages now favors the injured party.
See Murphey, supra note
23, at 422.
40. See Delchi, 1994 WL
495787, at *5.
41. See id.
42. "Incidental damages resulting from the seller's breach
include expenses reasonably incurred in inspection,
receipt, transportation[,] and care and custody of goods rightfully
rejected,
any commercially reasonable charges, expenses or commissions in connection
with
effecting cover and any other reasonable expense incident to the delay or
other
breach." U.C.C. § 2-715(1) (1991).
43. "Subject to the limitations stated in
§§ 350-53, the injured party has a right to damages
based on his expectation interest as measured by (b) any other
loss, including incidental or consequential loss, caused by the breach . .
." RESTATEMENT (SECOND) OF CONTRACTS § 347 (1981).
44. See JAMES J. WHITE &
ROBERT S. SUMMERS, UNIFORM COMMERCIAL CODE 266 (3d ed. 1988);
see also, Ohline Corp. v. Granite Mill, 849 P.2d
602, 605 (Utah App. 1993) (stating that in order to recover incidental damages,
"a buyer must show that the damages resulting from the breach were
reasonable"); Sprague v. Sumitomo Forestry Co., 709 P.2d 1200, 1205-06
(Wash. 1985) (contrasting the difference between consequential damages and
incidental damages). But see also, Mohler v. Jeke,
595 A.2d 1247, 1250 (Pa. Super. Ct. 1991) (stating that in order "to
recover incidental damages under a breach of contract theory, the damages
suffered must be direct and foreseeable").
45. See FARNSWORTH,
supra note 31, at 880-81; see also
U.C.C. § 2-715(2)(a) (1991)
("Consequential damages resulting from the seller's breach include (a) any
loss resulting from general or particular requirements and needs of which the
seller at the time of contracting had reason to know and which could not
reasonably be prevented by cover or otherwise.").
46. See CISG art. 74,
supra note 1, S. TREATY DOC. NO.
9 at 37, 19 I.L.M. at 688. Nothing in the CISG suggests an
intention to abolish incidental damages. See KRITZER,
supra note 3, at 19;
Murphey, supra note 23, at 459; see
also WHITE & SUMMERS,
supra note 44, at 266 (distinguishing between
"incidental" and "consequential" damages).
47. See CISG art. 74,
supra note 1, S. TREATY DOC. NO.
9 at 37, 19 I.L.M. at 688.
48. See U.C.C.
§ 2-715(1) (1991).
49. See Delchi, 1994 WL
495787, at *5 ("Nonetheless, Delchi's action in expediting shipment of
Sanyo compressors was both commercially reasonable and reasonably foreseeable,
and therefore Delchi is entitled to recover 504,305,665 lire as the net cost of
early delivery of Sanyo compressors . . . .").
50. Cover is the right of the party claiming damages to recover "[i]f the
contract is avoided and if, in a reasonable manner and within a reasonable time
after avoidance, the buyer has bought goods in replacement or the seller has
resold the goods." CISG art. 75,
supra note 1, S. TREATY DOC. NO.
9 at 37, 19 I.L.M. at 689.
51. See Delchi, 1994 WL 495787, at *5 ("The
shipment of previously ordered Sanyo compressors did not constitute cover under
CISG [A]rticle 75, because the Sanyo units were previously ordered, and hence
can not be said to have replaced the nonconforming Rotorex
compressors.").
52. CISG art. 77, supra note
1, S. TREATY DOC. NO. 9 at 37, 19 I.L.M. at 689.
53. See Vertue and Bird, 84 Eng. Rep. 1000, 1000
(1677) (holding that plaintiff in an assumpsit suit cannot collect damages
because he did not attempt to avoid damage to goods).
54. The [Restatement of Contracts] states:
(2) The injured party is not precluded from recovery by the rule stated in
Subsection (1) to the extent that he has made reasonable but unsuccessful
efforts to avoid loss.
RESTATEMENT (SECOND) OF CONTRACTS § 350 (1981).
55. The U.C.C. states that "[c]onsequential damages
resulting from the seller's breach include (a) any loss resulting
from general or particular requirements and needs of which the
seller at the time of contracting had reason to know and which could not
reasonably be prevented by cover or otherwise . . . ."
U.C.C. § 2-715(2) (1991).
56. See E. Allan Farnsworth, Damages and
Specific Relief, 27 AM. J. COMP. L.
247, 251 (1979).
57. See Delchi, 1994 WL
495787, at *5 (allowing plaintiff to collect the cost of mitigating losses).
58. See FARNSWORTH,
supra note 31, at 897 ("It is sometimes said
that in such cases the injured party is under a duty to
mitigate damages. This is misleading . . . .").
59. Under U.S. law, the burden of proof for showing that the injured party has
not taken steps to avoid damages is on the party in breach. See
FARNSWORTH, supra
note 31, at 897.
60. The Court states in a somewhat circular way that the "Sanyo compressors
did not constitute cover under CISG [A]rticle 75, because the Sanyo units
were previously ordered, and hence can not be said to have replaced the
nonconforming Rotorex compressors." Delchi,
1994 WL 495787, at *5. CISG Article 75 defines "cover" goods as
those "bought" within a reasonable time after avoidance. See
supra note 50 for a definition of cover. Although
the Sanyo compressors were "ordered" previously, it is not clear
whether they were "bought," thus confusing their status as
"covered" goods. See Delchi, 1994 WL
495787, at *5.
61. Delchi, 1994 WL 495787, at *5.
62. See CISG art. 74,
supra note 1, S. TREATY DOC. NO.
9 at 37, 19 I.L.M. at 688 ("Damages for breach of
contract by one party consist of a sum equal to the loss . . .
suffered . . . as a consequence of the breach. Such damages may
not
exceed the loss which the party in breach foresaw or ought to have foreseen
. . . ."). Under the U.C.C., plaintiff can recover
commercially
reasonable expenditures for unsuccessful cover or avoidance as
"incidental
damages." U.C.C. § 2-715 (1991). Incidental damages
include "additional costs incurred after the breach in a reasonable
attempt to avoid loss, even if the attempt is unsuccessful."
FARNSWORTH,
supra note 31, at 880-81 (citing Coast Trading Co. v. Cudahy Co., 592
F.2d
1074 (9th Cir. 1979) (stating that a seller whose resale was not
commercially
reasonable cannot recover incidental damages of costs of resale)).
63. See Delchi, 1994 WL 495787, at *5 ("Delchi
is entitled to recover 13,200,083 lire for the expenses incurred for handling
and storage of Rotorex's nonconforming compressors.").
64. See CISG art. 74,
supra note 1, S. TREATY DOC. NO.
9 at 37, 19 I.L.M. at 688; see also supra
note 59.
65. See Delchi, 1994 WL 495787, at *5 ("[T]he
court holds that Delchi is entitled to 2,103,683 lire as a
reasonable expense.") (emphasis added).
66. See supra note 55.
67. See Delchi, 1994 WL 495787, at *5-7.
68. Delchi, 1994 WL 495787, at *6.
69. See id.
70. Id.
71. See id. at *3.
72. Id.
73. Id.
74. See FARNSWORTH
, supra note 31, at 841. When a
contract is breached or a tort committed, resulting losses or damage may not be
caused by the actual breach or the tort itself, but rather by multiple or
intervening causes, such as the cancellation of an order by Delchi's British
customer or the lack of demand for Arieles in Britain after Rotorex's
breach. Such multiple or intervening causes are less likely to relieve a
defendant from contractual liability than from tort liability. See
id. at 841 n.7 ("Although the same problems of
multiple cause and of intervening cause that enliven the law of torts also
arise in connection with contract damages, they are relatively less important
than in the law of torts.").
75. Delchi, 1994 WL 495787, at *6.
76. "Delchi's claim of 4,000 additional lost sales in Italy is supported
only by the speculative testimony of Italian sales agents . . . .
The number of additional units they might have ordered . . . is not
in evidence, as the court sustained Rotorex's timely objections to the
speculative nature of such testimony." Id.
77. See CISG
art. 74, supra note 1, S. TREATY DOC. NO.
9 at 37, 19 I.L.M. at 688.
78. The factual causation requirement in U.S. contract law is similar to
the causation requirement in a tort claim, except that damages in tort are
intended to put the plaintiff in a pre-tort position, while contract
expectation damages put the plaintiff in the same position as he would have
been had there been full performance. See
FARNSWORTH, supra note 31, at
871 ("The basic principle for the measurement of [contract] damages is
that of compensation based on the injured party's expectation."). For
expectation damages, which include consequential damages, the plaintiff must
also demonstrate what his position would have been with contract performance.
See id. at 841.
79. See Delchi, 1994 WL
495787, at *6.
80. The English court in Hadley v. Baxendale
referred to the French Civil Code's articles 1149-51, and one of the judges
referred to the French requirement of foreseeability. See
Guenter H. Treitel, Remedies for Breach of Contract
(Courses of Action Open to a Party Aggrieved),
in 2 INTERNATIONAL ENCYCLOPEDIA OF
COMPARATIVE LAW 58 (Arthur von Mehren ed., 1976).
81. Hadley v. Baxendale, 156 Eng. Rep. 145 (1854).
82. See Murphey,
supra note 23, at 432 ("The [foreseeability]
rule is often discussed as being two rules or one rule in two parts.").
83. Hadley v. Baxendale, 156 Eng. Rep. at 151.
84. Id.
85. "Whatever the connotation in Hadley's
day, in time, most authorities in the United States -- and
some in England -- equated `foreseeability' with `in the contemplation of
the parties' and concluded that Hadley established
a rule of foreseeability." Murphey, supra
note 23, at 438.
86. See supra notes 54-55.
87. "The principle of excluding damages for unforeseeable
losses is found in the majority of legal systems."
Commentary, supra
note 26, at 59. Although numerous scholars claim that the rule of
foreseeability in CISG Article 74 is derived from English common law, it has
been forcefully argued that it is instead derived from French law.
See Franco Ferrari, Comparative
Ruminations on the Foreseeability of Damages in Contract Law
, 53 LA. L. REV. 1257, 1263-69 (1993);
Detlef König, Voraussehbarkeit des Schadens als Grenze
vertraglicher Haftung, in
DAS HAAGER EINHEITLICHE KAUFGESETZ UND DAS DEUTSCHE SCHULDRECHT, KOLLOQUIM
ZUM 65, GEBURTSTAG VON ERNST VON CAEMMERER 74, 86-130 (Hans G.
Leser & W. Frhr Marschall von Bieberstein eds., 1973).
88. 1 ROBERT L. DUNN, RECOVERY OF DAMAGES FOR LOST
PROFITS 23 (4th ed. 1992).
89. See Kenford Co. v. County of Erie, 537 N.E.2d
176, 179 (N.Y. 1989) ("In determining the reasonable contemplation of the
parties, the nature, purpose and particular circumstances of the contract
should be considered . . . as well as `what liability the defendant
fairly may be supposed to have assumed consciously . . . .'")
(citation omitted).
90. See Keystone Diesel Engine Co. v. Irwin, 191
A.2d 376, 377 (Pa. 1963) (holding that contemplation exists where "buyer
has communicated to seller . . . sufficient facts to make it apparent
that damages . . . were within reasonable contemplation of the
parties").
91. Morrow v. First Nat'l Bank of Hot Springs, 550 S.W.2d 429, 430
(Ark. 1977);
see also Western Indus., Inc. v. Newcor Canada Ltd., 739 F.2d 1198
(7th Cir. 1984) (stating in dicta that consequential damages are not
recoverable unless specifically negotiated).
92. R.I. Lampus Co. v. Neville Cement Prods. Corp., 378 A.2d 288, 288 (Pa. 1977)
("[B]uyer was not required to establish . . . that seller
contemplated or tacitly agreed. . . .").
93. See FARNSWORTH,
supra note 31, at 914-15; U.C.C.
§ 2-715 cmt. 2 (1991) ("The `tacit
agreement' test for the recovery of consequential damages is rejected.");
RESTATEMENT (SECOND) CONTRACTS § 351 cmt.
a (1981) ("[T]he party in breach need not have made a `tacit agreement' to
be liable for the loss.").
94. RESTATEMENT (SECOND) OF CONTRACTS
§ 351(3) (1981).
95. See id.§ 351 cmt. f (1981)
("There are unusual instances in which it appears . . . [that]
it would be unjust to put the risk on that party."); see
alsoJOSEPH M. LOOKOFSKY, CONSEQUENTIAL DAMAGES IN
COMPARATIVE CONTEXT 189 (1989) (explaining a study which
revealed only three cases that cited § 351(3), the most relevant
being All Points Towing, Inc. v. City of Glendale, 735 P.2d 145 (Ariz. App.
1987)). Lookofsky expressed the fear of some that the discretionary justice
represented by § 351(3) goes too far, "posing a threat to
commercial certainty and even to classical contract law."
Id. at 291.
96. See U.C.C.
§ 2-715(2)(b) (1991) ("Consequential damages resulting from
a seller's breach include injury to person or property
proximately resulting from any breach of warranty.").
97. In the United States, foreseeability is not a limitation on liability
for tort damages. See RESTATEMENT (SECOND)
OF TORTS § 435(1) (1965) ("If the actor's
conduct is a substantial factor in bringing about harm to another, the fact
that the actor neither foresaw nor should have foreseen the extent of the harm
or the manner in which it occurred does not prevent him from being
liable.").
98. See CISG art. 75,
supra note 1, S. TREATY DOC. NO.
9 at 37, 19 I.L.M. at 689.
99. U.C.C. § 2-715(2)(a) (1991) (emphasis
added).
100. RESTATEMENT (SECOND) OF CONTRACTS
§ 351(1) (1981) ("Damages are not recoverable for loss that
the party in breach did not have reason to foresee as a probable result. . . .").
101. See CISG art. 74,
supra note 1, S. TREATY DOC. NO.
9 at 37, 19 I.L.M. at 688 (emphasis added).
102. See Farnsworth, supra
note 56, at 253. Although the Restatement of
Contracts and the CISG also apply to seller's
consequential damages, this Article only discusses a buyer's consequential
damages. This approach is taken both because the CISG cases are about buyer's
damages and because, in U.S. courts, seller's claims for loss of direct profits
from defaulting buyers have received very favorable treatment, raising no
important issues of foreseeability. In such cases, courts seem "to
presume foreseeability and certainty rules have been met." STEWART
MACAULAY ET AL., CONTRACTS: LAW IN ACTION 133 (1995).
Commentators argue that this result is appropriate because there is little
danger of damage awards disproportionate to the consideration defendant would
have gotten from performance since "[c]ontract price is the ceiling of
recovery, and the largest cost items to be deducted from that price are the
most susceptible to proof." Lost Profits,
supra note 34, at 1003 (citations omitted).
103. See FARNSWORTH,
supra note 31, at 916 ("One takes the risk
of those [consequences] that one ought reasonably to have
foreseen."). This is unlike the test in tort law, which rejects the
foreseeability limit on damages. Instead, if the defendant's conduct threatens
any interest of the plaintiff, defendant is liable
for any resultant injury to plaintiff unless that injury is extremely bizarre.
See RESTATEMENT (SECOND) OF TORTS
§ 435 (1965).
104. U.C.C. § 2-715(2)(a) (1991) (emphasis
added).
105. RESTATEMENT (SECOND) OF CONTRACTS
§ 351(1) (1981) (emphasis added).
106. See CISG art. 74, supra note 1, S. TREATY DOC. NO. 9 at
37, 19 I.L.M. at 688.
107. See WHITE & SUMMERS
, supra note 44, at 514-18; Sutton,
supra note 19, at 744 (stating that a party
"may want to make . . . dangers known to the other contracting
party in order to implicate the subjective prong . . . Such notice,
however, would also create objective foreseeability today under the [U.C.C.]
and the Restatement, thus minimizing the
differences between article 74 and American view of foreseeability.").
108. See DUNN, supra note 88, at 36-43.
109. See supra note 50.
110. See FARNSWORTH,
supra note 31, at 918 ("Problems of
foreseeability do not usually arise unless the injured party who is a buyer
cannot cover . . . .").
111. See id. at 919-20. Because most goods are
readily available in a competitive market, the inability to cover is not
foreseeable in the ordinary course of events. See id.
at 878-79. See also
RESTATEMENT (SECOND) OF CONTRACTS
§ 351(2)(a) (1981) ("Loss may be foreseeable as a probable
result of a breach because it follows from the breach . . . in the
ordinary course of events . . . .").
112. See U.C.C.
§ 2-715 cmt. 6 (1991) (noting that damages resulting from loss
of resale profits are included under consequential damages). Seller is not
liable for extraordinary lost profit or losses from unusual terms of
buyer's resale contracts or "other circumstances of which seller is
ignorant." FARNSWORTH, supra
note 31, at 919.
113. See FARNSWORTH,
supra note 31, at 920 n.33 (citing Verhagen v.
Platt, 61 A.2d 892 (N.J. Super. Ct. 1948)).
114. See id. at 921.
115. "Damages are not recoverable for loss beyond an amount that the
evidence permits to be established with reasonable certainty."
RESTATEMENT (SECOND) OF CONTRACTS § 352
(1981).
116. Delchi, 1994 WL 495787, at *6 (footnotes
added).
117. See LOOKOFSKY,
supra note 95, at 181-87.
118. Id. at 283 n.158.
119. Commentators have noted:
WHITE & SUMMERS, supra note 44, at 451.
120. See RESTATEMENT (SECOND) OF CONTRACTS
§ 352 (1981); U.C.C.
§ 1-106 cmt. 1 (1991) (stating that damages "have to be
proved with whatever definiteness and accuracy the facts permit, but no
more"); U.C.C. § 2-715 cmt. 4 (1991)
("The burden of proving . . . consequential damages is on the
buyer, but the section on liberal administration of remedies rejects any
doctrine of certainty which requires almost mathematical precision in the
proof of
loss. Loss may be determined in any manner which is reasonable under the
circumstances."); see also WHITE & SUMMERS, supra
note 44, at 269 ("The 'fact-amount' doctrine, however, relaxes the burden
of
proof on the amount of loss once the buyer has proven the fact of a loss .
. . .").
121. CHARLES T. MCCORMICK, LAW OF DAMAGES 105 (1935).
122. L.L. Fuller & William R. Purdue, Jr., The Reliance Interest in
Contract Damages, 46 YALE L.J. 373,
376 (1937). It has been forcefully argued that the foreseeability rule should
be abandoned because it permits only all-or-nothing recovery and does not
necessarily prevent disproportionate damages. See
Lost Profits, supra
note 34, at 1021-22. This is because what courts often determine to be
foreseeable was not in fact foreseen or foreseeable since the test is based on
a "fiction." Id. One commentator
argues:
Id.
123. See Roy Ryden Anderson, Incidental and
Consequential Damages, 7 J.L. & COM.
327, 399-423 (1987); see also
RESTATEMENT (SECOND) OF CONTRACTS § 352
cmt. b (1981) ("The difficulty of proving lost profits varies greatly with
the nature of the transaction.").
124. Courts have commonly awarded lost profits in this category, including lost
resale profits on goods purchased for inventory. Older U.S. cases required
that the defendant seller had to have had notice at the time of contract
formation
of buyer's particular resale transaction. Recent cases have allowed that
"knowledge that the buyer was a merchant or that the buyer was ordering
quantities too large for its own use" is sufficient for foreseeability
of
lost resale profits. MACAULAY ET AL., supra note 102, at 133-34;
see also Lost Profits, supra note 34, at 1009-10. CONSEQUENTIAL DAMAGES IN THE INTERNATIONAL SALE
OF GOODS: ANALYSIS OF TWO DECISIONS
Damages for breach of contract by one party consist of a sum equal to the loss,
including loss of profit, suffered by the other party as a consequence of the
breach. Such damages may not exceed the loss which the party in breach
foresaw or ought to have foreseen at the time of the conclusion of the
contract, in the light of the facts and matters of which he then knew or ought
to have known, as a possible consequence of the breach of contract.[22]
A party who relies on a breach of contract must take such measures as are
reasonable in the circumstances to mitigate the loss, including loss of profit,
resulting from the breach. If he fails to take such measures, the party in
breach may claim a reduction in the damages in the amount by which the loss
should have been mitigated.[52]
A court may limit damages for foreseeable loss by excluding recovery for loss
of profits, by allowing recovery only for loss incurred in reliance, or
otherwise if it concludes that in the circumstances justice so requires in
order to avoid disproportionate compensation.[94]
[i]n conformity with the common law, see RESTATEMENT (SECOND) OF
CONTRACTS § 331 (sic);[115]
5 ARTHUR CORBIN, CORBIN ON CONTRACTS § 1020 (1951), and with the
law of New York, see Merlite Indus., Inc. v. Valassis Inserts,
Inc., 12 F.3d 373, 376 (2d Cir. 1993), to recover a claim for lost profit
under UNCCISG, a party must provide the finder of fact with sufficient evidence
to estimate the amount of damages with reasonable certainty.[116]
Questions concerning matters governed by this Convention which are not
expressly settled in it are to be settled in conformity with the general
principles on which it is based or, in the absence of such principles, in
conformity with the law applicable by virtue of the rules of private
international law.[152]
experienced observer at the time of the default, or even according to one
formulation, that of the most experienced observer (optimaler Beobachter). To
such an observer the court attributes knowledge of all the circumstances of
which a person of that kind could have known, as well as any additional
circumstances of which the wrongdoer himself actually knew.[232]
FOOTNOTES
Nearly all cases cited . . . [in a study on the application of the foreseeability test] are decisions on
appeal
by defendant. Plaintiff often obtains satisfactory results at the trial,
but
loses all or part of his verdict when defendant appeals. Appellate courts
will
probably be inclined to sustain the trial court's judgment when the record
discloses its logical, as well as evidentiary, basis.
(1) Except as stated in Subsection (2),
damages are not recoverable for loss that the injured party could have
avoided
without undue risk, burden or humiliation.
Because the legal principle of certainty
[relating to damages for loss of goodwill] in the plaintiff's case is
indivisible from factual questions about the amount and probity of
plaintiff's
evidence, it is difficult to make sensible and useful generalizations about
that principle. Often cases cited under the certainty rubric could be as
easily explained by saying that the 'plaintiff merely failed to prove his
damages' or 'failed to prove his case.' So stated, the principle is reduced
to
a homily.
[L]oss of profits resulting from breach
is seldom foreseen by either plaintiff or defendant at contract time.
Moreover, when the parties actually do foresee the risk of loss, they
generally
allocate that risk . . . by a contractual provision for liquidated
damages . . . . But the foreseeability rule is not applied when
the
loss was in fact considered; the rule is invoked only when a court must
effect
an allocation for which the parties failed to provide . . . . As a
result, the foreseeability rule penalizes one party for omissions made by
both
at contract time.