ICC Arbitration Case No. 7585 of 1992 (Foamed board machinery) [English text]
[Cite as: http://cisgw3.law.pace.edu/cases/927585i1.html]
Primary source(s) for case presentation: Text of case
DATE OF DECISION:
JURISDICTION:
TRIBUNAL:
JUDGE(S):
CASE NUMBER/DOCKET NUMBER: 7585 of 1992
CASE NAME:
CASE HISTORY: Unavailable
SELLER'S COUNTRY: Italy (claimant)
BUYER'S COUNTRY: Finland (defendant)
GOODS INVOLVED: Machinery for a production line of foamed boards
Case abstract ARBITRATION: ICC International Court of Arbitration case no. 7585 of 1992 Case law on UNCITRAL texts (CLOUT) abstract no. 301 Reproduced with permission from UNCITRAL An Italian seller of machinery for a production line of foamed boards, plaintiff, sued the Finnish buyer,
defendant, for damages and interest as the buyer had failed to make the third down payment to it and to
notify the relevant letters of credit on the required date. The contract contained a clause providing that the CISG was applicable to it. The arbitral tribunal held
that according to articles 1(1) CISG and 100 CISG, the CISG was applicable in its entirety (Finland had
made a reservation upon ratification, declaring that it would not be bound by Part II of the CISG) with
a statutory nature, because the conflict of laws rules expressed in the 1955 Hague Convention on the
Law Applicable to Contracts for the International Sale of Goods (Italy and Finland ratified this
Convention) led to the application of Italian law, which, after ratification of the CISG, incorporated the
provisions thereof. Therefore, the express choice of the CISG in the contract had not deprived the
CISG of its statutory character. The arbitral tribunal approved the seller's declaration of avoidance of the contract in accordance with
article 64(1)(b). It held that the buyer, by failing to notify the letters of credit on the date required, had
not complied with the requirements of articles 53 CISG and 54 CISG regarding the buyer's obligation
to pay the price. Reading article 25 CISG, which defines a fundamental breach, in connection with
articles 53 CISG and 54 CISG, the arbitral tribunal stated that the mere fact that a buyer had some
delay in payment was not always in itself a fundamental breach. In this case, the seller waited several
months before declaring the contractual relations terminated, in spite of the fact that it was clear that the
buyer did not have the financial resources. The arbitral tribunal regarded the period between the buyer's
default and the declaration of avoidance by the seller as an "additional period" fixed by the seller under
articles 63(1) CISG and 64(1)(b) CISG. On the basis of articles 78 CISG and 84 CISG, the arbitral tribunal determined that the seller was
entitled to claim interest on any sum that was in arrears. Stating that the CISG had not solved the
question of the rate of interest, the arbitral tribunal further determined that as the financial aspects of the
sale were linked with the German Mark, the applicable rate of interest was the German one. The arbitral tribunal found that the damages claimed by the seller, namely, on the one hand damages for
preservation of the undelivered machinery and costs and expenses (legal costs, arbitration), and on the
other hand, damages for loss of profit, should be considered as foreseeable according to article 74
CISG, as such damages were usual in situations of avoidance of a contract for breach of one party.
Citing article 77 CISG, the arbitral tribunal awarded the total amount claimed by the seller for the first
category of damages. The damages for loss of profit were held to be covered by article 74 CISG. The
arbitral tribunal held that, according to article 75 CISG, the seller, who had resold the machinery, was
entitled to recover the difference between the contract price and the price of the substitute transaction. Referring to the first clause of article 7(2), the arbitral tribunal granted the seller, in addition to
damages, the "compensation fee" contained in the contract's penalty clause.
APPLICATION OF CISG: Yes [Article 1(1)(b)]
APPLICABLE CISG PROVISIONS AND ISSUES
Key CISG provisions at issue: Articles
Classification of issues using UNCITRAL classification code
numbers:
6B [Agreements to apply Convention];
7C22 [Gap-filling: recourse to general principles on which
Convention is based];
25B [Definition of fundamental breach: substantial deprivation
of expectation, etc.];
53A [Obligations of the buyer: obligation to pay price of
goods];
54A1 [Obligation to pay price: enabling steps (common examples:
arranging for letter of credit];
63A [Notice fixing additional final period for performance:
additional final period for buyer's performance];
64A11 ; 64A211 [Seller's right to avoid contract, grounds for
avoidance: fundamental breach of contract, buyer's obligations;
Buyer does not pay or take delivery within an additional period
of time set by the seller];
74A ; 74B [Damages (general rules for measuring): Loss suffered as
consequence of breach; Outer limits of damages (foreseeability of
loss)];
77A [Obligation to take reasonable measures to mitigate
damages];
78A ; 78B [Interest on delay in receiving price or any other sum
in arrears; Rate of interest];
100B1 [Applicability based on date of contract]
EDITOR: Albert H. Kritzer
CISG issues ruled upon:
Applicability, contract vs. statutory basis for applying the CISG. The
contract provided that the CISG applies (contractual election of the
parties). The tribunal deemed it appropriate to determine whether
there
was also a statutory basis for applying the CISG.
"a) When the Convention is only applicable because it has been chosen
by the parties, it has the same nature as an agreement. As with all
contractual agreements, some of its provisions can then be avoided by
the law declared applicable by the conflict of laws rules in the
absence
of choice. A different result would ensue had the parties chosen a
national law incorporating the Vienna Sales Convention.
"b) When the Convention is applicable because it has been ratified, it
has the same nature as a Statute or an Act of Parliament."
In this case, based on Articles 1(1) and 100, the tribunal concluded
that there was also a statutory basis for applying the CISG.
Payment, buyer's obligation to pay the price (enabling steps:
obligation to obtain letter of credit). Article 53 sets forth buyer's
obligation to pay the price. Article 54 states that this obligation
"includes taking such steps . . . as may be required under the
contract". Buyer did not obtain a letter of credit on the date
required. Failure to do so was termed a breach of contract.
Avoidance/Fundamental breach/Notice fixing an additional final period
for performance ("Nachfrist" notice). Reading Article 25 in connection
with Articles 53 and 54, the tribunal stated that delay in payment
(failure to obtain the required letter of credit) "is not always in
itself a fundamental breach. According to circumstances, delay on
payment for the buyer of delay of delivery for the seller cannot be the
cause of immediate avoidance of the contract."
Seller waited over three months before declaring the contract avoided,
"[i]n spite of the fact that it was absolutely clear that [buyer] did
not have financial resources." The tribunal regarded the period
between
default and the declaration of avoidance as an "'additional period'
fixed by seller" in accordance with Article 63(1) and held that seller
was entitled to avoid the contract as provided in Article 64(1)(b).
In implementing Article 63(1), there is a conflict among commentators as
to whether the fixing of an additional time period by the seller must be
done in such a way as to make it clear to the buyer that the additional
period sets a fixed and final limit on the date for performance or
whether no such unequivocal warning is necessary.* This arbitral
opinion appears to support the latter view, as the tribunal simply
states: "The time period between November 28th, 1991 (date of equipment
inspection) and March 19th, 1992 (date of termination) has to be
analyzed as the 'additional period' fixed by Seller as set out in
Articles 63(1) and 64(1)(b) of the Convention."
* Will and Honnold support the former view; Knapp and Enderlein & Maskow
support the latter view. Will and Knapp, Bianca-Bonell Commentary
(1987) 315 and 461; Honnold, "Uniform Law for International Sales Under the 1980
United Nations
Convention, 2d ed. (1991) 370; Enderlein & Maskow, "International Sales
Law" (1992) 238.
Without reference to Articles 63(1) and 64(1)(b), another provision of
the CISG that could have been relevant to the results reached is Article
64(1)(a) on the theory that delay of over three months in providing the
required letter of credit is a "fundamental breach" of contract.
Interest (right to, accrual of, rate of). The tribunal stated:
"Article 78 . . . provides that the creditor is entitled to interest
'without prejudice to any claim for damages.' The purpose of this
provision is to make a distinction between interest and damages and to
give compensation for the financial loss due to the mere fact that delay
in payment has a financial cost. The same general idea is at the origin
of Article 84 which obliges the seller who is bound to refund the price,
to pay interest on it from the date on which he received money. The
practical consequence for the present case is that Seller is entitled
to claim interest on any sum that was in arrears."
The tribunal allowed interest from the date payment was due.
This was a contract between a seller from Italy and a buyer from Finland
with payment to be made in the currency of a third country. In ruling
on the rate of interest, the tribunal stated:
"The question of the rate of interest is not solved in the Convention. .
. . Several solutions are conceivable: the rate in force in the state
whose law is applicable; the rate in force in the place of business of
the creditor; the rate in force in the place of procedure.
"The arbitrator shares another view. In his opinion, the rate of
interest is linked to a precise currency. It would be rather illogical
to base interest for the delayed payment of a price agreed in strong
currency on the legal rate in force at a place of business located in a
country which has a high inflation figure and, consequently, a high rate
of interest. The same reasoning would lead to the exclusion of the law
applicable to the contract, the lex fori, or that of the place of
payment. . . .
"Clearly, the financial aspects of the sale are linked with the German
Mark. The applicable rate of interest is therefore the German one."
Damages/Mitigation of damages. Two categories of damages were claimed:
"on the one hand, damages for storage, care and maintenance of the
non-delivered machinery and costs and expenses (legal costs, arbitration);
on the other hand, damages for loss of profit."
Commenting on the fact that Article 74 "limits the amount of damages to
the foreseeable loss", the tribunal stated: "The claims under the
present case are usual in situations of avoidance of a contract for
breach of one party. They should therefore be considered as
foreseeable" and elaborated as follows:
"The first part of the claim (charges for storage . . ., costs and
expenses) belongs to the category of the well known Roman law damnum
emergens. . . . Article 77 states that the 'party who relies on a
breach of contract' has a duty 'to mitigate the loss, including loss of
profit, resulting from the breach.' In the present case, the size of
the machinery and its specification obliged Buyer to expenses of
carriage and storage in a warehouse, to care and maintenance. [Also
allowed was the cost of] modification of electrical equipment for the
needs of the new buyer."
"The other part of the claims consist of loss of profit. These claims
belong to the category of lucrum cessans of Roman Law. . . . [T]his
sort of claim is expressly stated in Article 74 . . . A specific
provision in Article 75 gives the seller who resells the goods the right
to 'recover the difference between the contract price and the price in
the substitute transaction.'" Loss of profit was calculated on this
basis.
Penalty clauses/Gap-filling. There are two parts to Article 7(2): a
part that calls for settlement of questions concerning matters governed
by the CISG which are not expressly settled in it in conformity with the
general principles on which the CISG is based; and a part that calls for
settlement of such matters in conformity with the law applicable by
virtue of the rules of private international law. The second part of
Article 7(2) applies where the CISG does not contain applicable general
principles on the matter.
In resolving a penalty clause issue, the tribunal referred to the first
part of Article 7(2), but not the second part.
The facts are: the contract specified different rights in the event it
is "terminated by fault".
At issue was seller's right to the compensation fee plus damages.
Seller's position was, the compensation fee is "a price, a consideration
other than in addition to damages suffered." Advising that the contract
clause at issue has to be interpreted in accordance with the CISG and
"in conformity with the general principles on which it is based" as
provided in Article 7, the tribunal reasoned that:
The section on buyer's rights is not a compensation for damages
suffered. The fact that it rules out a right to interest expressly
given to the buyer under Article 84(1) is significant. And there is
evidence that the compensation fee also "has a nature different from
damages in compensation of a loss". The fact that the reference to
"force majeure" rules out Article 79 damages claims by buyer is
significant in this respect. Seller is entitled to the compensation fee
in addition to damages pursuant to Article 74.
CITATIONS TO OTHER ABSTRACTS OF DECISION
English: Unilex database <http://www.unilex.info/case.cfm?pid=1&do=case&id=134&step=Abstract>
French: Bulletin de la Cour Internationale d'Arbitrage de la Chambre de Commerce Internationale (November 1995) 59; Journal du Droit International (1995), No.4, 1015 et seq. [cited as a 1994 award]
Italian: Diritto del Commercio Internazionale (1996) 622-623 No. 93
CITATIONS TO TEXT OF DECISION
Original language (English): ICC International Court of Arbitration Bulletin (November 1995) 60-64; Unilex database <http://www.unilex.info/case.cfm?pid=1&do=case&id=134&step=FullText>
Translation (French): Journal du Droit International (1995) 1015-1020 [cited as 1994]; Bulletin de la Cour Internationale d'Arbitrage de la Chambre de Commerce Internationale (November 1995) 59-66
CITATIONS TO COMMENTS ON DECISION
English: Lookofsky, Understanding the CISG in Scandinavia (1996) 67 n.122, 124 n.51; Mullis, Avoidance for Breach under the Vienna Convention: Critical Analysis of Some of the Early Cases (1998) n.114; Koch, Pace Review of Convention on Contracts for International Sale of Goods (1998) 251 n.246 [fundamental breach: uncertainty as to seller's future performance]; for analysis of the remedy of avoidance citing this and other cases, go to Kazimierska, Pace Review of the Convention on Contracts for the International Sale of Goods (1999-2000) n.249; Koneru, 6 Minnesota Journal of Global Trade (1997) 123-138 [comments on liquidated damages/penalty clauses and on interest rulings in this case and other cases]; Ferrari, International Legal Forum (4/1998) 138-255 [247 n.1027 n.1029, 251 n.1060 (interest issues)]; Thiele, 2 Vindobono Journal (1998) 3-35, citing this case [n.75, n.76, n.150, n.153-154] and 42 other interest rulings; Petrochilos, Arbitration Conflict of Laws Rules and the CISG (1999) nn.12, 18, 52, 69; Kimbel, 18 Journal of Law and Commerce (1999) 301-331 (analysis of the remedy of Nachfrist citing this and other cases: 311 n.36); Graffi, Case Law on the Concept of "Fundamental Breach" in the Vienna Sales Convention, Revue de droit des affaires internationales / International Business Law Journal, No. 3 (2003) 338-349 at nn.45, 59; Liu Chengwei, Recovery of interest (November 2003) nn.36, 101, 223; Larry A. DiMatteo et al., 34 Northwestern Journal of International Law & Business (Winter 2004) 299-440 at n.507; [2005] Schlechtriem & Schwenzer ed., Commentary on UN Convention on International Sale of Goods, 2d (English) ed., Oxford University Press, Art. 74 paras. 18, 49; Pilar Perales, Case cited at n. 38 in Presentation on Nachfrist at September 2005 seminar in Singapore; CISG-AC advisory opinion on Calculation of Damages under CISG Article 74 [Spring 2006] n.82 (related cases cited in addendum to opinion); Spaic, Analysis of Fundamental Breach under the CISG (December 2006) n.330 Finnish: Huber/Sundström, Defensor Legis (1997) 758 n.53
French: Y.D. [Derains], Journal du Droit International (1995) 1020-1022; Muir Watt, Revue de Droit des Affaires Internationales (1996) 401-406
German: Will, UN-Kaufrecht und internationale Schiedsgerichtsbarkeit (1999) nn.29, 32
Italian: Giardina, Rivista dell' arbitrato (1998) 191 [206 n.42]
Spanish: Perales, 3 Cuadernos Jurídicos (1996) No. 43, 5 [8-9 n. 33, n. 48, n. 49] = ICC Coll III 611-613 [commentary on Article 78: determination of rate of interest under the CISG (review of case law)]; Castellanos, Autonomia de la voluntad y derecho uniforme en la compraventa internacional, thesis, Carlos III de Madrid (1998) 166
Classification of issues present
Editorial remarks
Citations to other abstracts, case texts and commentaries
Pace Law School Institute of International
Commercial Law - Last updated March 20, 2007
Comments/Contributions
Go to Database Directory || Go to CISG Table of Contents || Go to Case Search Form || Go to Bibliography