AMERICAN ARBITRATION ASSOCIATION
Case No. Moot 6
Superb Paper, Plc
Claimant
v.
Essential Controls, S.A.
Respondent
NOTICE OF ARBITRATION
AND
STATEMENT OF CLAIM
I. The Facts of the Case
II. The Law Applicable to the Case
III. The Legal Rights of the Claimant
.
IV. Relief Sought
(Signed)______________
For Superb Paper, Plc.
Attorneys
6 July 1998_____
Date
CLAIMANT’S EXHIBIT NO. 1
CONTRACT
(The Exhibit sets forth the entire contract. Only the relevant excerpts are reproduced here.)
1. Essential Controls, S.A., 26 Export Pl., Southside City, Equatoriana, (hereafter Seller) agrees to sell and Superb Paper, Plc., 123 Industrial Avenue, Highlands, Mediterraneo (hereafter Buyer) agrees to buy a computerized control system for a total price of $500,000. The system is to be installed by Seller in the facilities of Buyer. The technical specifications are contained in Appendix I.
* * *
3. Payment of $400,000 is to be made upon delivery of the control system to the facilities of Buyer. A payment of $50,000, or ten percent (10%), is to be made within ten days of completion of final testing of the installed control system. The final payment of $50,000 is to be made within six months of completion of the final testing.
4. The control system is to be installed by the Reliable Installation Co., Baltic City, Hanseatica. Certification that the system is properly installed, that it has been tested in place and that it is fully operational will be made by Reliable on behalf of Seller on or before 16 September 1996.
* * *
22. This contract shall be governed by the United Nations Convention on Contracts for the International Sale of Goods.
23. Any controversy or claim arising out of or relating to this contract shall be determined by arbitration in accordance with the International Arbitration Rules of the American Arbitration Association. The number of arbitrators shall be three. The place of arbitration shall be the Danubia International Arbitral Centre, Vindobona, Danubia. The language of the arbitration shall be English.
24. If, in any arbitration arising out of or relating to this contract, Buyer shall make a claim which, if found to be justified, would give rise to a claim by Seller against one of its suppliers, Buyer agrees that the claim of Seller against the supplier may be settled in the arbitration between Buyer and Seller, provided that the supplier agrees to have the claim of Seller against it settled in the arbitration, that the supplier agrees to waive any right it may have to participate in the selection of the arbitral tribunal, and that the claims of Seller against the supplier raise no new questions of law or fact from those to be decided in the arbitration between Buyer and Seller.
June 10, 1996
|
(Signed)
|
(Signed)
|
CLAIMANT’S EXHIBIT NO. 2
Faxed letter from Respondent to Claimant dated 27 August 1996
Mr. William Spiegel
Superb Paper, Plc
123 Industrial Avenue
Highlands, Mediterraneo
Dear Mr. Spiegel:
I wish to confirm to you the contents of our telephone conversation of earlier today. The charter airplane carrying the team from Reliable Installation Co. that was on its way to Mediterraneo to install the control system crashed yesterday and all passengers were killed.
Needless to say, when Reliable called me this morning to tell me of the accident, they were extremely upset. Nevertheless, they assured me that they would be able to assign a new team to the job and that the installation should be completed by the contract date. I will keep you informed if there are any further developments.
Trusting that there will be no further difficulties, I remain
Sincerely,
(Signed)
Thomas Oletti
Essential Controls, S.A.
CLAIMANT’S EXHIBIT NO. 3
Letter from Claimant to Respondent dated 13 September 1996
Mr. Thomas Oletti
Essential Controls, S.A.
26 Export Pl.
Southside City
Equatoriana
Dear Mr. Oletti:
In your letter to me of 27 August 1996 confirming to me the news of the crash of the airplane carrying the team from Reliable Installation Co. to Mediterraneo, you stated that Reliable would be sending a new team to our plant and the installation would be completed on time.
Since that time I have telephoned you on 30 August, 4, 9 and 12 September inquiring when the installation team from Reliable could be expected. On each occasion you have assured me that Reliable was working on assembling the new installation team. However, we have never been given a firm date by which we could expect their arrival.
I wish to remind you that you contracted with us that the control system would be completely installed, tested and operational by this coming Monday. It does not seem necessary to remind you how important it is to our operations to have it working, and working promptly.
I trust that you will inform me immediately when the team from Reliable will arrive.
Sincerely,
(Signed)
William Spiegel
Superb Paper, Plc.
CLAIMANT’S EXHIBIT NO. 4
Letter from Claimant to Respondent dated 18 September 1996
Mr. Thomas Oletti
Essential Controls, S.A.
26 Export Pl.
Southside City
Equatoriana
Dear Mr. Oletti:
I refer to my letter to you of 13 September 1996 reminding you that the contract date for installation of the control system was last Monday. You have still not informed us when the team from Reliable will arrive to install the control system. It is, therefore, necessary for us to be more insistent.
We expect the system to be fully installed and operational by 9 October 1996 at the latest. If it is not operational by that date, we will have to look to our legal rights.
I should add that we are completely sympathetic to the loss that Reliable has suffered. We wonder, however, why you have not looked to some other firm to do the installation if Reliable is not able to meet its obligations.
Sincerely,
(Signed)
William Spiegel
Superb Paper, Plc.
CLAIMANT’S EXHIBIT NO. 5
Letter from Respondent to Claimant dated 19 September 1996
Mr. William Spiegel
Superb Paper, Plc
123 Industrial Avenue
Highlands, Mediterraneo
Dear Mr. Spiegel:
I acknowledge your letter of 18 September 1996. This is a difficult situation. The loss of some of their old employees in the plane crash has been difficult for Reliable, both in a human way and professionally.
I know that Reliable has been trying to put a team together to install the control system at your plant. They have had had some unexpected difficulties with an installation on which their key personnel are committed.
Nevertheless, it is clear that the control system must be installed at your plant promptly. Therefore, I have informed Reliable that they must be ready to begin within the next three weeks or we would have to terminate our contract with them.
If we have to turn to a different installation firm, it will take an additional several weeks to complete the job. Therefore, I would like to know whether you would be satisfied with an installation that would be completed by October 30, 1996. We would, of course, be ready to make a suitable adjustment on the purchase price to compensate you for your forbearance.
I await your reply.
Sincerely,
(Signed)
Thomas Oletti
Essential Controls, S.A.
CLAIMANT’S EXHIBIT NO. 6
Letter from Claimant to Respondent dated 9 October 1996
Mr. Thomas Oletti
Essential Controls, S.A.
26 Export Pl.
Southside City
Equatoriana
Dear Mr. Oletti:
I refer to my letter of 18 September 1996. In that letter I told you that we expected the control system to be installed and fully operational by 9 October 1996. I also said that if the system was not installed and fully operational by 9 October 1996, Superb Paper, Plc would have to look to its legal rights.
The deadline is today. The team from Reliance that is supposed to install the control system has still not arrived, and we have not been told when or if they will. Therefore, we are hereby canceling the contract.
We are holding the control system for your account and will return it to you upon your return of the $400,000 we have paid you, which we hereby demand.
Sincerely,
(Signed)
William Spiegel
Superb Paper, Plc.
CLAIMANT’S EXHIBIT NO. 7
Letter from Respondent to Claimant dated 10 October 1996
Mr. William Spiegel
Superb Paper, Plc
123 Industrial Avenue
Highlands, Mediterraneo
Dear Mr. Spiegel:
I refer to the fax of your letter of 9 October 1996 and to our telephone conversation of today.
We completely reject your claim that you had a right to cancel the contract. We acknowledge that the installation of the control system has been delayed, for the tragic reasons of which you are well aware. However, the delay has not been unusually long and it will soon be rectified.
Reliable has finally finished the installation to which I referred in my letter of 19 September 1996. The personnel qualified to do the installation are available to arrive at your facility on Monday, 14 October. We have insisted to Reliance that the installation had to be completed by 30 October at the latest, and they have assured me that, if there are no unusual problems, it will be finished by Friday, 25 October.
I wish to express my regrets for this unfortunate delay, but I am sure that you will be fully satisfied with the Essential Control System.
Sincerely,
(Signed)
Thomas Oletti
Essential Controls, S.A.
CLAIMANT’S EXHIBIT NO. 8
Letter from Claimant to Respondent dated 10 October 1996
Mr. Thomas Oletti
Essential Controls, S.A.
26 Export Pl.
Southside City
Equatoriana
Dear Mr. Oletti:
As I told you in our telephone conversation earlier today, we appreciate that Reliance would have installed the control system within the contract period if there had not been the airplane crash. However, we do not accept that neither Reliance nor you could have seen to the installation of the system before this time.
In any case, it is now too late. The contract was cancelled yesterday, and we have entered into a replacement contract with Bridget Controls GMBH.
To clarify our position stated in our fax of yesterday, we are holding your control system as security for the return of the $400,000 that we have paid to you.
Sincerely,
(Signed)
William Spiegel
Superb Paper, Plc.
CLAIMANT’S EXHIBIT NO. 9
Letter from Claimant to Respondent dated 13 March 1997
Mr. Thomas Oletti
Essential Controls, S.A.
26 Export Pl.
Southside City
Equatoriana
Dear Mr. Oletti:
It appears that we are not progressing in settling our dispute. You continue to hold our $400,000, and we continue to hold your control system as security. In order to break this deadlock, if Essential Controls does not reimburse us the $400,000 within the next ten days, i.e., by 24 March, we will sell the control system as best we can and reimburse ourselves from the proceeds. If we are not able to sell the control system for the full amount that you owe us, we will be forced to begin legal proceedings in the appropriate forum.
Sincerely,
(Signed)
William Spiegel
Superb Paper, Plc.