Reproduced with permission of the authors and MEALEY'S International Arbitration Report, Vol. 21, No. 6 (June 2006) 1-5
This article is another reply to the case note of Marcus S. Jacobs and Yanming Huang on a recent CIETAC award.[1] The CIETAC award concerned a contract for the international sale of commodities between a European seller and a Chinese buyer. The contract was governed by the CISG and included a "penalty" clause according to which the seller was to pay a fixed amount of damages in the event of failure to deliver. The seller so failed and the buyer claimed damages under Articles 75 "and/or" 76 CISG.
The authors of the initial case note did not display many facts but, under their view, the legal question was whether the parties, by including a penalty clause in their contract, impliedly opted out of the damages regime of the CISG by virtue of Article 6 of the Convention with the consequence that any increase of the agreed sum was to be determined according to Article 114 of the Chinese Contract Law [2] Law at the discretion of the arbitrators. This reply will again attempt to give an answer to this question.
1. EXPRESS PENALTY AND LIQUIDATED DAMAGES CLAUSE FORMS PART OF THE CONTRACT
The starting point for any analysis is the penalty and liquidated damages clause in the contract itself. There is nothing unusual in the fact that the parties to any sales contract are free to include an express provision for penalty and liquidated damages in the event of a breach of contract.[3] This is nothing more and no less than freedom of contract and party autonomy.
These principles are found in most legal systems and reinforced by the second -- substantive -- limb of Article 6 CISG which states that the parties may derogate from or vary the effect of any of the provisions of the Convention.
The question of whether the parties impliedly opted out of the Convention's damages regime to the effect that any domestic law applies is in itself misconceived. The reason for this is that the second -- substantive -- limb of Article 6 CISG only applies to the relationship [page 1] between (express and implied) contract terms and the default rules of the Convention but does not allow for any recourse to domestic law. The clause in the contract at hand can, admittedly, derogate from the damages regime of the CISG in full or vary specific damages provisions of the CISG. It cannot, however, render any domestic law applicable. In other words, the approach of Marcus S. Jacobs and Yanming Huang to this case unduly mixes the choice of law level (first limb) with the substantive law level (second limb) of Article 6 CISG by discussing the issue of an implicit opting-out.
In conclusion, by agreeing on a penalty and liquidated damages clause the parties modified the damages regime of the CISG. In exactly what way this modification comes into play is a question of contract interpretation and will be addressed below.
If the parties have included a penalty and liquidated damages clause in their contract the question of public policy arises whether such a clause is valid. That is the only question not addressed by the CISG but left to the applicable domestic law pursuant to Article 4(a) CISG which states that the Convention is not concerned with the validity of any of the provisions of the contract.[4]
Different jurisdictions hold polar views on the issue of the validity of penalty and liquidated damages clauses. In common law jurisdictions the distinction between penalty clauses, which are invalid, and liquidated damages clauses, which are valid, is of great practical importance.[5]
In civil law jurisdictions both liquidated damages clauses and penalty clauses are valid but the court or the arbitral tribunal may reduce the amount of money to be paid.[6] Despite technicalities in the details, the core rule according to which both the common law systems and the civil law systems distinguish between penalty clauses on the one hand and liquidated damages clauses on the other hand displays a common understanding: penalties are meant to deter a breach of contract whereas liquidated damages clauses pre-estimate future loss. Due to the fact that this distinction has proven difficult to be drawn in practice, modern systems, for example the Dutch law of obligations [7] or the UNIDROIT Principles of International Commercial Contracts,[8] treat penalty and liquidated damages clauses uniformly as being valid with the possibility of reduction.
In the present case, the penalty and liquidated damages clause was valid according to Article 114(1) of the Chinese Contract Law.[9]
In conclusion, penalty and liquidated damages clauses are enforceable under the Convention, unless, by virtue of Article 4(a) CISG, the applicable domestic law considers them invalid or provides for a reduction.[10]
Given a valid penalty and liquidated damages clause difficult questions arise concerning the modification of the standard damages regime of the CISG. Before addressing these questions, the precise scope and function of the particular contract clause needs to be determined. This is a question of contract interpretation to which Articles 8 and 9 CISG apply.[11] Due to the fact that we do not know many facts of the actual case we assume different fact patterns to illustrate the interaction between the contract term and the default rules of the CISG.
In the present case, the actual loss suffered by the aggrieved party seems to have exceeded the lump sum since the buyer claimed damages under Articles 75 "and/or" 76 CISG. Both provisions allow for specific methods of calculating damages. According to Article 75 CISG the aggrieved party may claim damages for their cover transaction. According to 76 CISG the aggrieved party may claim the difference between the contract price and the market price if they did not undertake a cover transaction. In general, both provisions require that the aggrieved party avoided the contract for fundamental breach of contract; facts which we cannot infer from the original case note.
However, it needs to be noted that Article 74 might form a basis for claiming such damages even without the necessity of contract avoidance.[12] Assumingly, the buyer in the present case would have recovered a higher sum under one of these provisions than under the penalty and liquidated damages clause which, in effect, constituted a limitation clause.[13] [page 2]
The question of whether or not the aggrieved party may claim for damages in addition to a contractual penalty and liquidated damages clause is to be answered by interpreting the clause. The crucial point is whether or not the clause was meant to be exclusive.[14] For example, if the parties agreed that a penalty clause applies "without prejudice to any other remedy available" it is apparent that the aggrieved party may cumulatively claim for damages. They can claim the penalty amount without having the need to prove the actual loss but can claim further loss if the burden of proof can be discharged. The situation is different if the party can claim the original penalty clause as a penalty clause. Full compensation for losses can still be claimed, as the penalty clause is only payment for the breach of the contract but not compensation for the actual loss.[15]
On the other side of the spectrum, if the parties agreed that the fixed sum be paid "in full and final settlement," they effectively derogated all other available remedies. Another factor to be considered is the event for which the penalty and liquidated damages clause applies.[16] If the clause only applies in the event of delay the aggrieved party might well have a damages claim for their performance interest, for example loss of profit.[17] Usually, the aggrieved party will have a claim for the recovery of any money paid to the party in breach on avoidance of the contract in addition to any penalty and liquidated damages.[18]
In conclusion, the questions concerning claims to the actual loss exceeding a contractual penalty and liquidated damages provision is not a question connected to the validity of such clauses and thus not outside the scope of the CISG. Rather, it is a question as to the extent of damages which is a matter governed by the Convention and it can be resolved by virtue of Article 7(2) CISG in applying the principles of the Convention, here the principle of full compensation as embodied in Article 74 first sentence CISG.[19] There is thus no need to look at Chinese law for any discretionary increase in the amount of damages by the court or the arbitral tribunal.
It is to be hoped that in this article the authors effectively rebutted the view of Marcus S. Jacobs and Yanming Huang that the parties to a CISG contract, by including a penalty clause in their contract, impliedly opted out of the damages regime of the CISG to the effect that domestic law applies giving discretionary power to the court or the arbitral tribunal to increase the agreed sum. By contrast, this is a question of damages which is governed by the CISG. The Convention has rules to be applied to the question whether the aggrieved party can claim damages in excess of a penalty and liquidated damages clause. Domestic law becomes decisive only with respect to the validity of such clauses. [page 3]
ENDNOTES
* [Editor's Note: Dr. Florian Mohs is a postdoctoral researcher
at the University of Basel and a visiting scholar
at the Law School of the University of Melbourne, Australia.
He worked as an associate to Professor Ingeborg
Schwenzer coordinating the publication of the 2nd edition
of the Commentary on the UN Convention on the
International Sale of Goods (Oxford University Press,
2005). Dr. Mohs holds law degrees from the University
of Basel, Switzerland (iur.) and the Victoria University
of Wellington, New Zealand (LL.M.).
1. The saga developed as follows: Marcus S. Jacobs
and Yanming Huang "An Arbitrator's Power And
Duties Under Art 114 Of Chinese Contract Law
In Awarding Damages In China In Respect Of A
Dispute Under A Contract Governed By CISG"
20(5) Mealey's Intl. Arb. Rep. 20 (2005); Bruno
Zeller "The CISG And The Opting Out Clause
Pursuant To Article 6 -- A Corrective Reply"
20(8) Mealey's Intl. Arb. Rep. 51 (2005); Marcus S. Jacobs and Yanming Huang "A Rebuttal Of Dr
Bruno Zeller's Commentary: The CISG And the
Opting Out Clause Pursuant To Article 6 A Corrective
Reply" 20(10) Mealey's Intl. Arb. Rep. 17
(2005).
3. E. Allan Farnsworth "Damages and Specific Relief "
27 Am. J. Comp. L. 247, 248 (1979) on the Draft
Convention; Peter Schlechtriem in Peter Schlechtriem
and Ingeborg Schwenzer (eds) Commentary on the UN Convention on the International Sale of Goods (CISG) (2nd ed, Oxford University Press, Oxford,
2005) Art 4 para 23, Art 6 para 12.
4. See Epsilon BVBA v Interneon Valkenswaard BV
(Rechtbank van Koophandel, Hasselt, 21 January
1997, English abstract at <http://www.unilex.info/case.cfm?pid=1&do=case&id=262&step=Abstract>)
holding that a penalty clause was invalid under the
applicable Belgian law.
5. England: Alfred McAlpine Capital Projects Ltd v Tilebox Ltd [2005] EWHC 281 (TCC); Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd
[1915] AC 79. USA: Sec. 2-718(1) UCC (note, however, that it has been suggested to delete
the second sentence of Sec. 2-718(1) UCC which,
currently, stipulates that "[a] term fixing unreasonably
large liquidated damages is void as a penalty"
because it is perceived as unnecessary and capable of
causing confusion. See Sec. 2-718 UCC and comment
1.b) of the 2002 Draft).
6. See the comparative notes to Article 9:509 of the
European Principles of Contract Law.
7. Article 6:91 Burgerlijk Wetboek (BW).
8. Article 7.4.13 of the UNIDROIT Principles addresses
both types of clauses under the heading
"agreed payment for non-performance" and states:
(2) However, notwithstanding
any agreement to the contrary the specified sum
may be reduced to a reasonable amount where it
is grossly excessive in relation to the harm resulting
from the non-performance and to the other
circumstances." This provision was relied on as
international practice in accordance with Article
9(2) CISG in the award of 5 June 1997 of the
Tribunal of International Commercial Arbitration
at the Russian Federation Chamber of Commerce
and Industry (at <http://cisgw3.law.pace.edu/cases/970605r1.html>).
9. Article 114(1) of the Chinese Contract Law, in
an English translation, provides:
Chinese law applied as the
proper law of the contract.
10. Case law and scholarly writing up to now suggest
that any possible reduction of penalty and liquidated
damages clauses to a reasonable extent is to be
determined by the applicable domestic law because
this question is attached to and interwoven with the
question of validity. See Diepeveen-Dirkson BV v Nieuwenhoven Vichandel GmbH (Gerechtshof Arnhem, 22 August 1995, English abstract at <http://www.unilex.info/case.cfm?pid=1&do=case&id=156&step=Abstract>); CIETAC award of 6 February
1997 (at <http://cisgw3.law.pace.edu/cases/970206c1.html>); award of 10 January
1998 of the Tribunal of International Commercial
Arbitration at the Russian Federation Chamber of
Commerce and Industry (at <http://cisgw3.law.pace.edu/cases/980110r1.html>); Peter
Schlechtriem ibid (fn 3) Art 4 para 23, Art 7 para
35; Martin Schmidt-Kessel in Peter Schlechtriem
and Ingeborg Schwenzer (eds) Commentary on the UN Convention on the International Sale of Goods (CISG) (2nd ed, Oxford University Press, Oxford,
2005) Art 8 para 30; Hans Stoll and Georg Gruber
in Peter Schlechtriem and Ingeborg Schwenzer
(eds) Commentary on the UN Convention on the International Sale of Goods (CISG) (2nd ed, Oxford
University Press, Oxford, 2005) Art 74 para 49.
11. Martin Schmidt-Kessel ibid
(fn 10) Art 8 para 44 referring to a decision of the Regional Court of
Munich dated 8 February 1995, CISG-online 143
(for an English translation see <http://cisgw3.law.pace.edu/cases/950208g1.html>) as an example for
the application of Article 8 CISG to the question
of whether the parties agreed on a pre-payment
obligation only or, in addition, on a penalty clause.
Contrast Klaus Peter Berger "Vertragsstrafen und
Schadenspauschalierungen im Internationalen
Wirtschaftsvertragsrecht" RIW 1999, 401, 402.
12. With respect to these delicate damages issues see
only Peter Schlechtriem "Damages, avoidance of the
contract and performance interest under the CISG"
at <http://www.cisg-online.ch/cisg/publications.html>.
13. On limitation clauses see generally Hans Stoll and
Georg Gruber ibid (fn 10) Art 74 para 50.
14. ICC award 7585 of 1992
(at <http://cisgw3.law.pace.edu/cases/927585i1.html>) enforcing a penalty clause which stated that "[i]f the
agreement is terminated by fault or request of the
purchaser -- including force majeure -- the buyer
is entitled to a compensation fee of 30% of the
price" in addition to damages for the preservation
of the undelivered machinery, the legal and arbitration
costs and loss of profit; Hans Stoll and Georg
Gruber ibid (fn 10) Art 74 para 49.
15. See specifically UNCITRAL digest, A/CN.9/SER.C/DIGEST/CISG/74, point 6.
16. See the decision of 23 November 1994 of the
Tribunal of International Commercial Arbitration
at the Russian Federation Chamber of Commerce
(<http://www.unilex.info/case.cfm?pid=1&do=case&id=250&step=Abstract>) implying that a clause
providing for a penalty in the event of delay did
not bar the buyer's claim for damages based on the
non-conformity of the goods. In the end, however,
the damages claim for non-conformity was denied
on other grounds (insufficient proof). See also the
award of 27 July 1999 of the Tribunal of International
Commercial Arbitration at the Russian
Federation Chamber of Commerce and Industry
(at <http://cisgw3.law.pace.edu/cases/990727r1.html>) where the tribunal held that
in a claim for the recovery of penalties to be paid to
a third party (final purchaser) the buyer could not
recover for both delay and non-delivery.
17. See the decisions of 19 February 2004
(at <http://cisgw3.law.pace.edu/cases/040219r1.html>), 19 March 2004
(at <http://cisgw3.law.pace.edu/cases/040319r1.html>)
and 20 April 2004
(at <http://cisgw3.law.pace.edu/cases/040420r1.html>) of the
Tribunal of International Commercial Arbitration
at the Russian Federation Chamber of Commerce,
all granting the seller, although under Russian law,
a penalty for delay in addition to their claim for
payment of the purchase price; for a case where liquidated
damages for delay were granted in addition
to the purchase price see the award of 22 January
1996 of the Tribunal of International Commercial
Arbitration at the Russian Federation Chamber of
Commerce and Industry
(at <http://cisgw3.law.pace.edu/cases/960122r1.html>). The
same result was reached under the CISG in the ICC award 8247 of 1996
(at <http://www.unilex.info/case.cfm?pid=1&do=case&id=458&step=FullText>).
But see the decision of 23 November 1994 of the
Tribunal of International Commercial Arbitration
at the Russian Federation Chamber of Commerce
(at <http://www.unilex.info/case.cfm?pid=1&do=case&id=250&step=Abstract>) striking out the buyer's
claim for damages for non-delivery because of a
clause providing for a penalty in the event of delay.
18. ICC award 9978 of 1999, CISG-online 708
(<http://www.cisg-online.ch/cisg/urteile/708.htm>) holding
that a clause providing for a penalty of 2% of the
contract value in the event of non-delivery barred
only the buyer's claim as to damages under Articles
45(1)(b), 74 but not as to the purchase price under
81(2); award of 16 April 2003 of the Tribunal of International
Commercial Arbitration at the Russian Federation Chamber of Commerce and Industry
(at <http://cisgw3.law.pace.edu/cases/030416r1.html>).
19. Contrast ICC award 7197 of 1992
(at <http://www.unilex.info/case.cfm?pid=1&do=case&id=37&step=Abstract>) applying Austrian law pursuant to
Article 7(2) CISG as to the aggrieved party's right
to recover damages notwithstanding the limits of
a penalty clause; award of 18 February 2002 of
Tribunal of International Commercial Arbitration
at the Russian Federation Chamber of Commerce and Industry
(at <http://cisgw3.law.pace.edu/cases/020218r1.html>) not allowing a claim for further losses pursuant to Russian law.
Pace Law School
Institute of International Commercial Law - Last updated July 14, 2006
Go to Database Directory || Go to Bibliography
Comments/Contributions