Reproduced with permission of 15 Arizona Journal of International & Comparative Law (1998) 583-634
Elbi Janse van Vuuren [a1]
I. INTRODUCTION
The traditional approach to solving international commercial disputes has
been to look to the domestic law of a country for the answers. This is by no
means the ideal solution to the intricacies inherent in international
commercial disputes and leads to a number of problems.
The first problem encountered stems from the use of private international
law to find the domestic law applicable to the contract. Every scholar of
private international law knows its problems of characterization, renvoi, gap,
accumulation, and the like. It is not always possible to predict with
certainty which legal system will be applicable and the determination of the
applicable law is often a lengthy and costly affair.[1] This problem is, of
course, easily overcome by including a choice of law clause in the contract.
Even if a choice of law clause is included in the contract, a second problem
still remains. Most choice of law clauses provide for the application of the
domestic law of a specific country to disputes arising from the contract.
While domestic law is able to adequately govern and regulate domestic
contracts, this is not always the case with contracts with an international
flavour. International contracts introduce problems unique to their nature,
such as the intricacies of goods and money crossing international borders.
These contracts also require parties and lawyers of different backgrounds -- be
it common law, civil law, developed, or developing countries -- to meet minds
over involved issues and difficult concepts.[2]
Yet another problem exists with the potential for bias. Above and beyond the
possible inadequacy of a domestic law to regulate the position to [page 583]
satisfaction, the application of domestic law will often favour the party
whose national law it is.
Depending on where the dispute is heard -- in the national courts of a country
or before an arbitrator (whether governed by national or international
arbitration rules) -- the parties may have two last options to try and avoid the
above problems.[3] These options are only available where the dispute is
addressed by way of arbitration, and not in national courts, as those courts
must predominantly apply only their own laws or those of another country.[4] The first option available to the parties is to provide in their
contract that a dispute will be resolved by "general principles of law," the
lex mercatoria, or something similar. In addition to this first option, where
the arbitrator is authorised to act ex aequo et bono or as an amiables
compositeur,[5] he may, on his own initiative, rely on the general
principles of law or the lex mercatoria.[6] The parties may provide legal
certainty to their relationship by removing the contract from the domain of
private international law and by regulating it with a more effective and
uniform set of substantive rules, which specifically provides for the problems
arising out of international trade.[7]
Although this would seem to be the ideal solution to the intricacies
inherent in international commercial disputes, there has been sufficient
scepticism surrounding the existence of a clearly identifiable set of general
rules or lex mercatoria, to render it both uncertain and unclear, thereby not
fulfilling these paramount requirements of legal rules.[8] International
model laws, conventions, and organizations such as the WTO and the ICC, have
made leaps and bounds toward creating an internationally uniform set of rules
to govern [page 584] international trade and commercial transactions. However,
these instruments are often fragmentary in nature and limited in scope, thus
limiting their usefulness.[9]
The UNIDROIT General Principles of International Commercial Contracts
[10] (hereinafter "UNIDROIT Principles" or "Principles") aspire to solve
some of these stumbling blocks.[11] The objective of the UNIDROIT
Principles is to establish a balanced set of rules designed for use throughout
the world irrespective of the legal traditions and the economic and political
conditions of the countries in which they are to be applied.[12] The notes
to the UNIDROIT Principles provide that:
To fulfill this goal, the UNIDROIT Principles must meet a number of minimum
requirements. In the first place, they should be clear and well-defined.
Secondly, they should contemplate the unique character of the international
commercial transactions they aim to regulate. Finally, they should be
sufficiently flexible to allow for the simultaneous application of the several
conventions regulating various aspects of international commercial trade.
The purpose of this paper is to examine the extent to which the UNIDROIT
Principles are a "systematic and well-defined set of rules" as contemplated by
the drafters. This will be done by means of a comparative study between the
circumstances under which a contract may be terminated under the UNIDROIT
Principles and under a number of domestic law systems and by identifying which
of these legal systems is most suited to an international commercial setting.
Although the focus of the paper will be mainly on the termination of the
contract and the policy considerations motivating the rules of termination,
the different forms of breach or non-performance giving rise thereto will be
touched upon where necessary.
The domestic law systems on which this paper focuses are U.S. law, as an
example of a common law system, German law as an example of a civil law
system, and South African law which is a Roman Dutch common law system and
[page 585] shows the characteristics of both a common law and civil law system.
In addition, these countries were chosen because two of them, the United States
and Germany, have commercial codes while South Africa does not.
At the outset, it must be pointed out that there is no single, simple, or
universal term that describes the issue addressed in this paper accurately for
all domestic legal systems. Subtle differences in the underlying foundation of
the remedy influence the terms used to describe it. In explaining the
foundation of the different legal system's remedies, the different national
terms will be used where necessary, but in as much as the consequences of the
remedies converge, the terms used in the UNIDROIT Principles will be utilised
to facilitate comparison.
A distinction can generally be drawn between the avoidance of a contract and
the termination thereof.[14] Avoidance is usually the only remedy available
where there is a defect in the conclusion of a contract affecting its
validity.[15] The effect of avoidance is that it completely extinguishes
the contract ab initio, and places the parties in the position they were in
prior to the conclusion of the contract as if no contract were ever concluded.
The UNIDROIT Principles also make the distinction between avoidance and
termination. The UNIDROIT Principles explain that avoidance takes effect
retroactively and that on avoidance either party may claim restitution of
whatever it has supplied under the contract, provided that it concurrently
makes restitution. If it cannot make restitution in kind, it must make an
allowance for what it received.[16]
Article 3.7 of the Principles provides that if there is an option between
avoiding the contract and using the remedies for non-performance, the contract
may not be avoided. In those situations, the remedies for non-performance must
be used. Preference is given to those remedies because they are better suited
and more flexible than the radical solution of avoidance.
Avoidance is not a concept foreign to national legal systems and is often
also referred to as rescission or cancellation followed by restitution.
[17] It is important to note that avoidance is not a synonym for
restitution. Restitution is a consequence of avoidance, but, as will be seen
in later discussion, may also be a consequence of termination. [page 586]
Termination, on the other hand, is a term not frequently encountered in
national legal systems,[18] but is a remedy found in all three domestic law
systems used in this paper. "Termination" has a very particular meaning in the
UNIDROIT Principles. The availability of termination as a remedy presupposes
the existence of a valid contract. Article 7.3.5 of the Principles provides as
follows:
In its purest form, termination means that none of the parties may insist on
specific performance. The result of an election in favour of termination is
that both parties are released from their obligation to effect and receive
future performance, as is clear from Article 7.3.5(1). Note that termination
does not mean that restitution has to take place. It is therefore
distinguishable from avoidance where restitution has to take place as a
general rule. It also does not mean that an aggrieved party is automatically
claiming damages. Article 7.3.5(2) clearly states only that termination does
not preclude a claim for damages-not that it includes such a claim.
Finally, article 7.3.5(3) may be interpreted to mean that the contract is
extinguished ex nunc, and not ab initio.[20] Not all consequences of the
contract are destroyed, but only the future obligations of the parties. This
provision is extremely important for international commercial contracts
-- especially since the UNIDROIT Principles will frequently be enforced
through arbitration proceedings. It affirms beyond a doubt that provisions of
the contract meant to deal with situations arising after its termination will
remain enforceable between the parties. [page 587]
After the aggrieved party has terminated the contract, he may then
further choose between a claim for damages or restitution. This paper will
only look at those circumstances where the aggrieved party decided not to
insist on specific performance (i.e. decided to terminate the contract), but
nevertheless wants to claim damages which would put the party in the position
he would have been in had the contract been performed according to its terms.
This particular remedy was chosen because it is the route most frequently
taken by the aggrieved party after a breach of the other party. The paper does
not address the situation where a party terminates a contract and subsequently
claims restitution to be put in the position he would have been in had there
been no contract concluded.
The discussion will now focus on the various situations under which one
party to a contract may terminate that contract and subsequently claim damages
from the other party. These situations arise typically where there is breach
of contract by one of the parties.
Given the fact that both the United States and Germany are signatories to
the United Nations Convention on the International Sale of Goods (CISG) [21]
and that South Africa will undoubtedly follow suit in the near future, a
comparison between the national general principles relating to sales contracts
and those of the UNIDROIT Principles will be unsuitable. Where international
sales contracts are the subject of dispute, the national legal systems will
look to the CISG for solutions and not national law. This paper will attempt
to steer clear of principles applicable to only sales contracts, although some
examples may use sales contracts as their basis because they tend to make for
clear illustrations.
A. General Remarks
South Africa does not have a commercial code comparable to the United
States' Uniform Commercial Code (U.C.C.) or to Germany's Handelsgesetzbuch.
Apart from statutes governing particular contracts or aspects thereof,[22]
the general principles of South African contract law must be found in South
Africa's Roman Dutch common law and case law.
South African law recognises five forms of breach of contract, namely: (i)
mora debitoris (delay of the debtor); (ii) mora creditoris (delay of the [page
588] creditor); (iii) positive malperformance; (iv) repudiation; and (v)
impossibility attributable to the fault of one of the parties.[23] Upon
breach, the aggrieved party may have two options: either to keep the contract
alive by claiming specific performance and compensation for any damage caused
by the breach or alternatively, to terminate the contract and claim
compensation for any damage caused by the breach. Any of the above forms of
breach can potentially give rise to the right to terminate the contract.
Termination does not, however, follow automatically from breach of contract.
Breach of contract only gives rise to the right to terminate the contract and
then only in some circumstances. The reason for this approach is that the
basic principle underlying South African contract law is pacta sunt servanda
and the law first and foremost tries to uphold a contract before allowing any
of the parties to terminate. Additionally, as R.H. Christie aptly explains:
In accordance with its underlying principle of pacta sunt servanda, South
African law only allows for the termination of a contract where there has been
a material breach, or as is often stated, where the breach goes to the root of
the contract. Where there is no material breach, the aggrieved party may not
terminate the contract, but may only claim damages to compensate for the loss
he suffered as a result of the breach in addition to insisting on specific
performance and fulfilling his own obligations. Not all forms of breach use
the same construction or criteria to determine the materiality of the breach
and the following sections will examine the requirement for materiality as
manifested in the different forms of breach. [page 589]
B. Mora Debitoris
South African law requires that two hurdles be passed before an aggrieved
party may terminate the contract due to the delay of the other party. In the
first place, the other party must be in delay, or as is said in South African
law, in mora.[25] Secondly, the aggrieved party must have acquired the
right to terminate the contract. It is the second requirement that evinces the
requirement that the breach should be material.
The first hurdle will be met and a party will consequently be in mora when:
To determine whether performance is due, a distinction is made between mora ex re and mora ex persona. A party will be in mora ex re when the contract
fixes the time for performance and the party has not performed by the agreed
upon time. Mora ex re therefore does not require the obligee to notify the
obligor that he will be in breach unless he fulfils his obligations within a
reasonable time.[27] South African courts consistently apply this principle
no matter how harsh the result may be.[28] Even where no time for
performance was stipulated, the obligor will still be in mora ex re if it is
clear that immediate performance was contemplated, and the immediacy was
essential by reason of the subject matter of the contract or the relevant
circumstances.[29] Furthermore, if no time for performance was expressly
stipulated in the contract, but by necessary implication it can be shown that
performance by some specific time was intended, and was essential, the obligor
will be automatically in mora if, at that specific time, he has not performed.[30] Where the contract does not stipulate a time for performance and
immediate performance is not possible and not contemplated, the obligor has to
be placed in mora ex persona, which requires a demand by the obligee to the
obligor to perform his obligations within a reasonable time.[31] Whether
the demand allows the obligor a reasonable time within which to perform
depends on the circumstances of each case.[32]
The mere fact that a party is in mora is not, however, a ground for
termination of the contract. Being in mora is only a form of breach of
contract. [page 590] Although the rules governing this aspect do not in all
instances expressly provide that the delay should be material, their
consequences are to the effect that the breach has to be material or that the
non-performing party is aware or should be aware that timely performance is
important to the aggrieved party, before the right to terminate will accrue to
the aggrieved party. The aggrieved party will have the right to terminate the
agreement in the following situations.
Where the contract contains a forfeiture clause (i.e. where it expressly
states that if one party fails to perform a particular obligation by a
specified time, the other party will be entitled to cancel the contract), the
failure by the obligated party to perform at the agreed upon time is material
and the aggrieved party may terminate the contract.[33] It may be argued
that by expressly providing so, the parties to the contract elevated timely
performance to being of the utmost importance to the contract and that any
non-compliance with the clause stipulating the agreed upon time consequently
constitutes a material breach.
Where the contract states expressly when the performance of a party must occur, but does not state that the other party will have the right to terminate the contract when there is delay in that performance, it then becomes necessary to decide whether time is of the essence of the contract.[34] In this situation there is already a breach, but it has not yet been
determined whether that breach is material. If the breach is of the essence of
the contract (or material), then it is of sufficient magnitude to justify the
obligee in terminating without a prior demand for performance.[35] Whether
time is of the essence of a contract is determined by looking at the nature of
the contract and the surrounding circumstances. It has frequently been held
that time is of the essence in what is described as a mercantile transaction.[36] A mercantile transaction is described as one in a fluctuating market or
a market in which prompt delivery or payment is necessary to keep the wheels
of commerce turning.[37] Greenfields Manufacturers (Temba) (Pty) Ltd. v. Royton Electrical Engineerning (Pty) Ltd.[38] explains that what is looked
for is essentially a tacit term and that the nature of the tacit term is that
failure to perform by the specified time entitles the other party to terminate
the contract. When it is said that there is "a strong presumption that time is
of the essence in a mercantile transaction proper,"[39] the Court
interprets it as meaning that the circumstances in which a "'mercantile
transaction proper' is concluded [page 591] and the terms thereof might afford
cogent evidence that the parties had in fact agreed that 'time is of the
essence."'[40]
The last situation where an aggrieved party may terminate the contract is
where there is neither a forfeiture clause included in the contract, nor is
time of the essence of the contract, but the aggrieved party has earned the
right to terminate the contract. As the case of Microutisicos v. Swart
explains,[41] where time is not of the essence of the contract, the other
party can make it so by giving notice that if the obligation is not complied
with by a certain date, allowing a reasonable time, he will regard the
contract as at an end. This principle that time can be made of the essence by
notice applies only to failure to perform what is described as an essential,
vital, or important term, or a term going to the root of the contract and the
law does not permit termination after notice for breach of a non-essential
term.[42]
It is clear that South African law allows for the termination of a contract
only where the delay was material, and that materiality is established when
the parties expressly or impliedly provided that timely performance is
material or, in the absence of either of these, when the aggrieved party has
subsequently informed the breaching party that timely performance is an
essential term.
C. Mora Creditoris
Mora creditoris is present where the obligee fails to co-operate with the
obligor to the extent necessary to enable the obligor to perform.[43] After
the presence of mora creditoris has been determined, South African law moves
over to the principles of repudiation and allows the obligor to terminate the
contract only if the failure to co-operate amounts to repudiation of the whole
contract. Repudiation contains its own requirements as to materiality of the
breach.[44]
D. Positive Malperformance
Positive malperformance is distinguished from delay in that the obligor does
perform, but in the wrong manner. The mere presence of positive malperformance
does not per se entitle the aggrieved party to summarily cancel the contract.
The aggrieved party will only be entitled to terminate the contract, if, in
the first place, the contract contains a forfeiture clause entitling him to
terminate the contract for any specified breach or, secondly, where the breach
[page 592] justifies termination.[45] In Oatorian Properties (Pty) Ltd v.
Maroun,[46] Potgieter JA held that:
From this quotation it is clear that the materiality requirement for
positive malperformance really encompasses two distinct branches, namely that
the term breached should go to the root of the contract and that the breach
should not be minor, but substantial or material. This point is illustrated by
Spies v Lombard [48] where the court held that breaches by a tenant of a
term that he should not damage the property were insufficiently serious to
justify the landlord's termination of the contract.
South African law uses the test of the "officious bystander," amongst
others, to determine whether the breach is material. Christie describes the
test as follows:
The objective bystander test illustrates one way to determine the
reasonableness of contract termination.[50] The aim of the test is to
determine what reasonable contracting parties would agree upon in similar
circumstances and [page 593] thereby to establish an objective standard of
firstly, what is a vital or essential term, and secondly, whether the breach
thereof is substantial. The relevant considerations looked at are the express
terms of the contract and the surrounding circumstances at the time when the
contract was entered into. It is important to note that this is the test used by
courts to determine whether a term should be implied into a contract and that it
is a strict test, since South African courts are unwilling to imply terms into
contracts. Van den Berg v. Tenner [51] involved the case where two parties
to an agreement agreed in a second agreement to withdraw from the first
agreement after its conclusion. The plaintiff in the case had already
partially performed in terms of the first agreement. The court held that, even
though the second agreement did not expressly provide so, there arose from the
second agreement an obligation to return that which had been delivered. In
Aucamp v. Morton [52] the court was unwilling to allow termination of a
contract where malperformance was easily remediable. Greenfield Manufacturers v. Royton Electrical Engineering [53] involved a case of delayed
performance, rather than malperformance, but illustrates some important points
regarding implied terms. The parties to the contract did not expressly agree
that time was of the essence, but the respondent relied on special facts and
circumstances in alleging that time was of the essence [54] and that the
parties agreed tacitly that the respondent would be entitled, at its election,
to repudiate the contract in the event of a failure by the appellant to
perform timely. In holding that the parties did indeed so tacitly agree, the
court looked at a number of circumstances, including the fact that the
respondent contracted with another party to deliver the goods in question
before a certain date [55] and that the appellant was aware of this.[56]
Another way of approaching the question of whether there was material
malperformance or not, is by inquiring whether the obligation which was broken
was so vital or material to the performance of the whole contract, that the aggrieved party could say that the foundation of the contract was destroyed.[57] It goes without saying that no single test can serve for all cases and
that every case has to be judged in light of its particular facts.
In summary, South African law allows for the termination of a contract due
to positive malperformance only if the malperformance was material. An
objective test is used to determine whether there was material malperformance.
If the parties expressly provided for strict compliance with the terms of the
contract or if the seriousness of the malperformance, in light of all the [page 594] circumstances, justifies termination in the eyes of the officious
bystander, the malperformance is material.
E. Repudiation
Repudiation does not involve the two tiered approach encountered above in
Sections B through D where the presence of a breach has to be determined first
and the severity thereof subsequently. Under South African law, repudiation is
only present where one party evinces an intention no longer to be bound by the
contract.[58] A dispute over one or several minor provisions in an elaborate contract should not as a rule be deemed to amount to repudiation.[59] The definition of repudiation, therefore, has the requirement of
materiality already built into it. Conduct will only amount to repudiation
when the conduct exhibits a deliberate and unequivocal intention no longer to
be bound and such an intention will only be present when a material term of
the contract is denied. An important factor in determining whether a term is
of sufficient importance so that its denial will amount to repudiation is
whether, had the term now denied not been agreed upon, the other party would
have concluded the contract.
F. Impossibility Attributable to the Fault of one of the Parties
Impossibility attributable to the fault of one of the parties is
distinguishable from the above forms of breach in that in the case of the
previous forms of breach, performance is still possible, but here it is not.[60]
If the impossibility is attributable to the fault of one of the parties,
that party is in breach of the contract.[61] This rule is explained by
saying that there is an implied term in the contract that the parties will
refrain from doing anything that will prevent them from performing.[62] The
construction is therefore essentially one of breach of an implied term. A
party may not plead discharge of the contract through loss of the subject
matter where he, by his deliberate or negligent act, has been responsible for
such loss.[63] This is distinguished from where the party had no fault,
e.g., where the subject matter of the contract was [page 505] destroyed through
vis major or casus fortuitus, where the destruction would then operate to
discharge the contract.[64] Both negligence and intent are sufficient to
form the basis of this form of breach of contract.
This form of breach does not require an additional or separate test with
which to measure the materiality of the breach. The prerequisite that
performance should be impossible already includes the materiality requirement.
G. Conclusion
Consistent with the principle of pacta sunt servanda, South African law
allows for the termination of a contract only in extraordinary circumstances.
South African law generally mandates a two tiered approach to determine
whether an aggrieved party has the right to terminate the contract. It must
first be established whether the breach is present, and secondly whether it is
material enough to justify termination of the contract. The parties may
expressly provide that any or specific breaches are material, or the
circumstances may indicate the materiality, thereby also allowing for the
situations where the parties themselves failed to provide for such an event in
their contract.
III. GENERAL PRINCIPLES OF U.S. CONTRACT LAW REGARDING THE RIGHT TO TERMINATE A CONTRACT FOR BREACH
A. General Remarks
The U.C.C. purports to deal with all the phases which may ordinarily arise
in the handling of a commercial transaction, from start to finish.[65]
However, the nature of the U.C.C. makes it largely unsuitable for the
comparative study undertaken in this paper. In the first place, the U.C.C.
contains too much detail and focuses too specifically on enumerated types of
transactions to allow for a general principle comparative study. Secondly, the
U.C.C. does not cover a broad enough spectrum of transactions. The law of
agency is, for example, not addressed. Article 2, which provides an exhaustive
exposition of the principles of sales agreements is, as explained in the
introduction, not included in this paper since the CISG already usurped the
application of national law in the context of international sales agreements
and Article 2 remains applicable only with regard to sales within the United
States. Some references will be made to the general provisions of Article 1.
[page 596]
An alternative source for the general principles of U.S. contract law
on the termination of an agreement is found in U.C.C. Section 1-103 which
provides that "[u]nless displaced by the particular provisions of this Act,
the principles of law and equity, including the law merchant ... shall
supplement its provisions."[66] The common law principles should therefore
be utilised in addition to the U.C.C. In light of the fact that the UNIDROIT
Principles have been compared to the Restatement Second of Contracts
(hereinafter the Restatement),[67] this paper relies heavily on the general
principles found in the Restatement.
Under U.S. law, any repudiation [68] and any non-performance,[69] which
includes delay of presumably both the obligor and obligee and impossibility
attributable to one of the parties, constitutes a breach when performance is
due.[70] Although this is generally the case even though the
non-performance is insubstantial,[71] the court may ignore a trifling
departure from the provisions of the contract to avoid a finding of breach.[72] The mere presence of breach, however, does not entitle the aggrieved
party to terminate the contract in every situation. It is generally stated
that only a material failure by the other party will entitle the aggrieved
party to terminate the contract.[73] United States law therefore exhibits
the same two tiered approach found in South African law where the presence of
a breach is determined first and then assessment of whether the breach is
material enough to justify termination of the contract occurs.
The Restatement has a unique way of distinguishing between what the UNIDROIT
Principles call "termination" and "requiring performance."[74] The
Restatement draws a distinction between damages for total breach and damages
for partial breach. Section 236(1) defines a claim for damages for total
breach as "one for damages based on all of the injured party's remaining
rights to performance."[75] In contrast, Section 236(2) defines a claim
for damages for partial breach as "one for damages on only part of the injured
party's remaining rights to [page 597] performance."[76] A party may claim
only one or the other, or have an election between the two,[77] but may not
claim both simultaneously. This prohibition on the simultaneous application of
both remedies demonstrates their inconsistency with one another. A claim for
partial breach implies that the contract is enforced by way of specific
performance and that the aggrieved party only claims damages in as far as he
suffered them. Whereas, a claim for total damages means that the contract is
terminated -- i.e. no specific performance is claimed, and the aggrieved party
claims damages to put him in the position he would have been in had no breach
taken place.
A material breach of contract gives the aggrieved party the right to
terminate the contract and either claim restitution or maintain an action for
damages for total breach.[78] Where there is total breach of the contract,
the aggrieved party is at liberty to treat the contract as broken and desist
from any further effort on his part to perform it.[79] In other words, he
may abandon the contract and recover, as damages for the breach, the benefits
he would have received by a full performance.[80] Abandonment is not
technically a rescission of the contract, but the mere acceptance of a
situation created by the wrongdoing of the other party.[81]
In Restatement terminology, therefore, focus will be on the forms of breach
which give rise to a claim for total breach. This is the closest U.S.
equivalent to contract termination under the UNIDROIT Principles.
B. Breach as Non-fulfilment of a Condition
The Restatement explains breach as the non-fulfilment of a condition.
According to Section 225 the non-occurrence of a condition has two possible
effects on the duty subject to that condition. In the first place, it prevents
performance from becoming due, at least temporarily.[82] It secondly
discharges the duty when the condition can no longer occur.[83] Section
237, comment (a) explains how these effects also find application in the
sphere of material failure of performance. According to Sections 237
and 238, performance or an offer of performance is a condition for the
aggrieved party's remaining duty under the contract. If the other party fails
to perform, the aggrieved party is not obliged to perform his own [page 598]
obligation.[84] The aggrieved party immediately gets the right to suspend
his own performance and ultimately, subsequent to the meeting of further
requirements, to refuse to perform altogether and to claim damages for total
breach if the non-performance is not justified. There is no general
requirement for fault.
Only a "material failure" operates as the non-occurrence of a condition.[85] A material failure delays reciprocal performance temporarily and
permanently discharges reciprocal performance if the material failure is not
cured during the time in which performance can occur.[86] The presence of a
material failure is, of course, a precondition for the onset of these effects.
It has to be determined therefore, what a "material failure" is.
Restatement Second of Contracts Section 237 refers to a "material failure"
and not to the more traditional "material breach" of contract with good
reason. Material failure is a broad concept including, but not limited to,
breach. "Failure" could be explained as being any non-performance, defective
performance, or late performance, but it also implies an absence of judgement
as to where the loss caused by the failure should rest. The allocation of the
loss depends upon whether or not the failure was justified, for example by
impracticability.[87] If the failure was not justified, the failure amounts
to a breach of contract. A non-justified material failure is the Restatement
terminology used to refer to a material breach, but because "material breach"
is the term more frequently used in case law, this paper utilises the latter
term in the remaining discussion of United States law.
A material breach is a breach that goes to the whole consideration of the
contract.[88] As a general rule, the breach of any duty that was made
expressly a condition of the contract, is material.[89] The Restatement
Second of Contracts Section 241 provides further that:
Comment (a) to this section warns that these are only circumstances and not
rules and that Sections 237 and 238 should be applied in light of the
facts of each case and with the purpose of securing for each party his
expectation of an exchange of performances.[91] In O. W. Grun Roofing and
Construction Co. v. Cope,[92] the Court explained the approach to the
question of materiality as follows:
The tendency of the courts to refer to material breach and to substantial
performance as opposite sides of the same coin is clear. There will be a
material breach if a party failed substantially to perform in terms of the
contract. The following discussion will show that, in addition to the rules
applicable to each form of breach, these general rules also find application
in their own peculiar way.
C. Delay
When performance of a duty under a contract is due, any non-performance is a
breach.[94] That does not mean, however, that the aggrieved party will
summarily have the right to terminate the contract. United States law will
only allow termination on account of delay where time is of the essence of the
contract. There are three ways in which time may be of the essence.
In the first place, time may be made of the essence of the contract by
express stipulation.[95] This position is very similar to what South
African law calls mora ex re.[96] When the parties so agree in their
contract, then time must be regarded as of the essence both at law [97] and
in equity [98] even where damages may compensate for the delay [99] and
no matter how harsh or exacting the terms may be.[100] A refusal of a court
to give effect to a timing term in the agreement would amount to not giving
effect to the intention of the parties embodied in their contract.[101] It
is not sufficient if the contract merely states a particular day for
performance. If a party should fail to perform on the stated date, it only
entitles the injured party to withhold his performance and gives him a claim
for damages for delay, but it does not of itself discharge his remaining
duties.[102] A timing clause should, in addition to merely stating a date, make clear that the parties [page 601] intended time to be of the essence.[103] It is only when the circumstances indicate that performance on the stated day was of genuine importance that the injured party's remaining duties are discharged immediately with no period of time during which they are merely suspended.[104]
There is some indication that if enforcement of the time of the essence
clause in a bilateral contract will result in an excessive penalty or
forfeiture, the courts will ameliorate the offender's position by the
application of equitable principles.[105]
The second way in which time may be of the essence of the contract is where
there is a manifestation of intention to that effect from the contract or
subject matter involved,[106] or by implication from the nature of the
contract or circumstances of the case.[107] Examples of the latter include,
conditions arising from the nature of the subject matter of the contract
[108] or the character of the interest bargained for.[109] No one rule
can be formulated as to when the facts and circumstances, the nature of the
subject matter of the contract, or the character of the interest bargained for
make time of the essence.[110] If time becomes material to the rights and
interests of the parties to any substantial degree, it will be regarded as of
the essence.[111]
In this regard, Restatement Section 242 is relevant. In the case of
material failure, the reciprocal performance is temporarily not due. The
reciprocal performance is discharged if the material failure is not cured
during the time in which performance can occur. Section 242 (a) and (b)
provides the circumstances significant in determining when remaining duties
are discharged.[112]
It is often said that in commercial transactions, notably those for the sale
of goods, prompt performance by a party is essential or "time is of the
essence." This is a particular application of the general principle that the
extent to which it reasonably appears to the injured party that delay may
prevent or hinder him from making reasonable substitute arrangements is a
consideration in determining the effect of delay.[115]
The last way in which time may be of the essence of the contract, is where
one party makes it so ex post facto.
In the ex post facto situations it is assumed that there is a time for
performance and that it passed without performance. This situation is
distinguishable from the first and second possibilities above in that timely
performance is not essential. It is, nevertheless, possible to make timely
performance essential by notifying the non-performing party to that effect.
Even where there is no agreed upon time, time may be made of the essence of
the contract by one of the parties fixing a reasonable time for the completion
of the contract and giving notice to the other party of an intention to
abandon the contract unless it is completed within the time fixed, provided
that the time allowed is reasonable. Whether the time is reasonable is a
question of fact depending on the circumstances of every case.[117]
In summary it could be said that U.S. law only allows for the termination of
a contract due to delay where time was of the essence of the contract. The
ultimate criterion as to whether or not time is of the essence of a contract
is a sufficient manifestation of intention of the parties, actual or apparent.[118]
D. Positive Non-performance
Positive non-performance is the situation where an obligor does perform, but
not completely in conformance with the provisions of the contract. From this
definition it is clear that even the smallest deviation from the strict terms
of the contract will constitute breach. The obligee is, however, not entitled
to terminate the contract for any non-performance. There has to be material or
fundamental non-performance before the aggrieved party acquires this right.
The requirement of fundamentalness is often explained in terms of the
substantial performance doctrine.
The effect of the substantial performance doctrine is explained as follows
in American Jurisprudence Section 631:
The substantial performance doctrine is arguably the positive side of the
general rule that an aggrieved party may not terminate the contract unless
there was a substantial breach thereof. The doctrine states that the
mal-performing party may enforce the contract, although he may be limited as
to what he receives in return for his defective performance.
There is authority for the statement that the substantial performance
doctrine is only applicable where there has been an honest effort to perform,
and not a wilful omission.[120] It is unclear why this exception should be
made, since the motive of the obligor is generally not relevant to the loss
the aggrieved party might suffer and U.S. law has no general requirement of
fault for breach of contract. The only apparent reason for this exception is
that a wilful omission or performance in bad faith could be an indication of
the reluctance of the obligor to perform any remaining obligations. American
Jurisprudence Section 639 reinforces this reasoning by adding that a rule
which would enable a person voluntarily to abandon his contract and lose
nothing thereby would have a tendency to encourage bad faith and lessen the
sacredness of obligations. It is the duty of the courts to uphold and enforce
the sacredness of obligations so far as it does not lead to injustice. Most
courts would be unwilling to enforce a rule which undermines this principle.
As to what constitutes substantial performance, the example of construction
contracts provided by American Jurisprudence Section 634 is illuminating.
Section 634 explains that "there is substantial performance where all the
essentials necessary to the full accomplishment of the purposes for which the
thing contracted for has been constructed are performed with such an
approximation to complete performance that the owner obtains substantially
what is called for by the contract."[121] Whether this approximate state of
completion has been reached, will depend on the facts and circumstances of
each case and in light of the language of the entire contract and what has
been done or omitted under it.[122] Restatement Section 243(4) provides
that "a breach by non-performance gives rise to a claim for total breach only
if it so substantially impairs the value of the contract to the injured party
at the time of the breach that it is just in the circumstances to allow him to
recover damages based on all his remaining rights [page 605] to performance."[123] The factors enumerated in Restatement Section 241 are useful in
determining the materiality of the non-performance.
In summary, any non-performance of a contract amounts to breach of contract,
but U.S. law allows the aggrieved party to terminate the contract after part
performance only where there was a material breach of the contract.
E. Repudiation and Anticipatory Repudiation
Anticipatory breach is committed before the time for performance is due and by words or acts that evince an intention to refuse performance in the future.[124] Where a party bound by an executory contract repudiates his
obligations before the time for performance, the promisee has the option to
treat the contract as ended, so far as further performance is concerned, and
maintain an action at once for the damages occasioned by the anticipatory
breach.[125] The aggrieved party need not wait until the time for
performance arrives [126] and need not complete his own performance or even
offer performance in order to have the right to claim damages.[127]
Where a party refuses to recognise the existence of a contract, or does
something inconsistent with its existence, including refusing to perform in
accordance with the contract, these actions may be treated as a breach of the
contract where it occurs after the time for performance of the contract.[128] The situation foreseen here, is where a repudiation accompanies or
follows a breach by non-performance.[129]
A repudiation is a statement by the obligor to the obligee indicating that
the obligor will commit a breach that would of itself give the obligee a claim
for damages for total breach under the Restatement Section 243.[130] The
renunciation must go to the whole contract and must be absolute and
unequivocal.[131] This definition of repudiation already includes the
requirement of materiality in that the statement should be serious enough to
give rise to a claim for total breach. In [page 606] Mobley v. New York Life
Ins. Co., the requirement for fundamentalness is further explained as follows:
The words "substantially to perform" recalls the substantial performance
doctrine and the principles there applicable can be meaningfully used in this
regard.
F. Impossibility Attributable to a Party
Impossibility is distinguishable from frustration. Performance is still
possible in the case of frustration, though that performance may be difficult.
In the case of impossibility, however, performance is completely impossible.[133]
As a general rule, supervening impossibility is not an excuse for the
non-performance of a contract [134] in the absence of a provision therefor.[135] Especially included within the ambit of this general rule is the
situation where the fault of one of the parties gave rise to the
impossibility. It is an implied condition of every contract that one party
will not prevent performance by the other party.[136] This condition is
implied from the duty of good faith and fair dealing. Where impossibility
might have been anticipated and guarded against in the contract, or where the
impossibility arises from the act or default of the promisor, the parties
remain bound to the contract.[137] Therefore, where one party to a [page 607]
contract makes performance, either for himself or for his counterpart,
impossible, he breaches the contract.[138]
The fact that the performance is impossible, already includes the
requirement that the breach should be fundamental. The non-breaching party
will therefore have the right to terminate the contract upon impossibility
attributable to the fault of the other party.[139]
G. Conclusion
The general principles of U.S. contract law as stated by the Restatement
only allow for the termination of a contract in case of a material failure to
perform, while case law generally refers to a material breach as opposed to a
material failure. Termination is therefore not the first remedy available to
an aggrieved party, but the exception rather than the rule due to the
requirement that the breach should be material. The parties may expressly
provide which forms of breach they will regard as material, but the law also
allows for the determination of materiality with reference to the
circumstances of each case.
IV. GENERAL PRINCIPLES OF GERMAN CONTRACT LAW REGARDING THE RIGHT TO TERMINATE A CONTRACT FOR BREACH
A. General Remarks
In Germany, the central codification in the field of commercial law is the
Handelsgesetzbuch (HGB). This code builds on the general principles found in
the Burgerliches Gesetzbuch (BGB). The HGB details how the relationship
between merchants differs from the relationship described in the BGB and where
different principles govern commercial transactions. Any aspect not governed
by the HGB must be solved in terms of the BGB.[140] The HGB does not
provide general principles applicable to the termination of commercial
contracts and instead the HGB provides a limited number of provisions
regarding the [page 608] termination of specific contractual relationships.[141] Where relevant, reference will be made to these provisions, but the
provisions on the termination of contracts found in the BGB are the main source
of general provisions used in this comparative study.
German law recognises three forms of breach of contract, namely: (i)
impossibility (Unmöglichkeit); (ii) delay of both the debtor and the creditor
(Verzug); and (iii) the positive breach of an obligation or contractual duty
(positive Forderungsverletzung) which includes repudiation or anticipatory
breach. The BGB expressly provides for the first two forms, but the rules
governing the positive breach of an obligation were developed by the courts
when it became apparent that not all forms of breach could be characterised as
either impossibility or delay. For breach of contract, German law requires
fault.[142]
Breach by one of the parties does not automatically terminate the contract.
Upon breach, the aggrieved party will have a claim for damages [143] and may
in some cases be entitled to terminate the contract. Termination is not,
however, the rule where breach is present, but will only be allowed if the
requirements set by the BGB or by the courts in the case of positive
non-performance are met. Although the requirements for termination are
generally not expressed in terms of a requirement for materiality, a very
similar effect is achieved. This phenomenon will be examined with reference to
the different forms of breach.
B. Impossibility (Unmöglichkeit)
This discussion will focus only on subsequent impossibility (nachträchliche
Unmöglichkeit) -- i.e. impossibility after the contract has been concluded. The
reason for this limitation is that initial impossibility is not breach of
contract, but rather affects the formation and validity of the contract and
gives rise to the remedy of avoidance, while breach presupposes a valid
contract.
The most relevant provisions of the BGB regarding impossibility are
Sections 280 and 325. Section 280 is applicable to both unilateral
obligations and reciprocal obligations, while Section 325 further regulates
reciprocal obligations.[144] [page 609]
Sections 280 and 325 contain the two basic prerequisites required for
impossibility to qualify as breach of contract, namely: (i) that performance
by the obligor must become impossible after formation of the contract; and
(ii) that the impossibility must be a result of circumstances imputable to the
obligor.[145]
These rules apply regardless of whether the impossibility is objective or
personal.[146] The impossibility must, however, be permanent.[147]
Temporary impossibility is treated as delay and therefore falls under
Section 284.[148] The concept of impossibility encompasses both physical
impossibility and cases where the performance, though physically still
possible, has become economically or otherwise so difficult that it would be
contrary to the good faith rule of Section 242 to require the obligor to
perform.[149] [page 610]
Not every case of impossibility gives rise to the right to terminate
the contract. A general distinction is drawn between complete impossibility
and partial impossibility.
In the case of complete impossibility, the obligee has a claim for
compensation for any damage arising from the non-performance.[150] The
purpose of the obligee's claim is to receive his positive interest, i.e. to be
placed in the position he would have been in had there been no breach.[151] In the case of reciprocal obligations, the obligee is also released from his own obligation to perform.[152] In both cases, the obligee has the
right to terminate the contract, subject to the provisions of Sections 246-356.[153] It is clear that complete impossibility is a very material breach indeed
and it follows that the aggrieved party should have the right to terminate the
contract.
In the case of partial impossibility, the obligee may accept partial
performance and claim compensation for any damages arising from the non-
performance.[154] The compensation is then limited to the impossible part
of the performance and the obligor's obligation to perform survives for the
remaining possible part.[155]
Should the aggrieved party wish to terminate the contract in the case of
partial impossibility, he has to meet a further requirement. Both Section
Section 280(2) and 325(1) provide that if the obligee has no "desire for the
partial performance," he may demand compensation for non-performance of the
entire obligation, in other words, terminate the agreement.[156] The
English translation of the original German text may be somewhat misleading in
that it erroneously suggests that a subjective standard is used to determine
whether the aggrieved party has the right to terminate. The German phrase is
"wenn die teilweise Erfüllung für ihn kein Interesse hat"[157] and may also
be translated as "when the partial performance has no interest (or worth) for
him." The determining standard of whether or not the performance has "worth"
for the aggrieved party is an objective one.[158]
In summary, in both unilateral and reciprocal relationships, the obligee has
the right to claim damages for non-performance or to rescind the contract. He
may, however, only choose to terminate the contract if the performance is
completely impossible or if, objectively speaking, the obligee cannot
reasonably be expected to continue with the performance. Even here it is
structurally not a new liability that is created, but the transformation of
the obligation to perform to [page 611] the obligation to restore damage.[159] Therefore, the rules are primarily designed to enforce the existing
relationship and allow termination in more narrowly defined circumstances only
secondarily.[160]
C. Delay (Verzug)
The BGB regulates delayed performance as a second form of default of
performance. The rules of delay are applicable only if performance is still
possible. Section 275 et seq. provide the general rules applicable to delay,
while Section 323 et seq. add further rules governing reciprocal
obligations. The most important sections are Sections 284, 285, 286,
and 326.[161] [page 612]
The three basic requirements for delay may be distilled from these
provisions:
In the case of a unilateral obligation, the obligor must compensate the
obligee for any damage arising from his default.[166]
The mere presence of delay does not, however, entitle the innocent party in
a bilateral contract to summarily terminate the contract. Very similar to the
position under South African law, the creditor may only rescind from the
contract or claim damages for non-performance in very specific circumstances.
The aggrieved party may terminate the contract if, in consequence of the
delay, the performance will be of no use to the innocent party,[167] i.e.
the later performance would not fulfil the purpose for which the contract was
concluded.[168]
Where delay per se would not frustrate the purpose of the contract, i.e.
where time is not of the essence, the obligee must fix a reasonable period of
grace (Nachfrist) for the obligor before resorting to either remedy.[169]
The period of grace must be long enough to allow an obligor, who has already
taken the [page 613] necessary preparatory steps, to perform the contract within
this time.[170] The obligee must make it clear in his notice that after the
period of grace he will refuse to accept any performance.[171] If the
obligee has given notice and the obligor has not performed within the period
of grace, the obligee may no longer claim performance.[172] The contract
can now only be wound up, either by a claim for damages for non-performance,
or by a claim for rescission. A claim for specific performance is expressly
prohibited by Section326(1) and the options available to the aggrieved party
are thereby limited. The obligee is not required at this stage to indicate
whether he will rescind and claim restitution or claim damages, but he has to
stay with the choice once it is unequivocally made.[173] The choice is
exercised by means of a unilateral declaration [174] and must be exercised
without undue delay, otherwise the aggrieved party may lose his right to
rescind.[175] It is generally more favourable to claim damages.[176]
These general rules do not apply to sales transactions between merchants.
Rather, taking into account the specific needs of merchants, the merchant
loses his claim for specific performance and remains restricted to termination
or damages for non-performance, unless, immediately after expiration of the
time limit, he gives notice to the other party that he insists on specific
performance.[177] Also, the merchant's right to terminate exists not only
"in case of doubt," but in all cases.[178]
The obligee may combine the warning under Section284 BGB with the fixing
of the period of grace under Section326 BGB, so that both can be done by one
letter.[179]
The purpose of the compensation for breach is to put the aggrieved party in
the position he would have been in had the obligor performed on time.[180] This [page 614] is once again the protection of the positive interest of the innocent party, which includes his profit.[181]
In summary, the mere presence of delay does not entitle the aggrieved party
to terminate the contract. This may only be done in three instances. First,
if, as a consequence of the delay, the performance will no longer fulfil the
purpose for which the contract was concluded, the aggrieved party may
terminate without giving notice to the breaching party. It may be said that in
these cases, there has been material breach of the contract. Secondly, if the
delay does not have this effect, the aggrieved party must give the breaching
party a period of grace in which to remedy his default, failing which he may
then terminate the contract. In these cases, the effect of the notice is to
elevate the delay to a level of such materiality, that it justifies
termination. German law takes the effect of this notice so seriously, that it
precludes the possibility of claiming of specific performance. An aggrieved
party would therefore be well advised to carefully consider this consequence
before giving the notice. Lastly, in the case of a transaction between
merchants, there is a presumption that delay is of sufficient materiality to
justify termination and the aggrieved merchant must terminate the contract
unless he gives notice immediately after the delay that he will insist on
specific performance. This exception for merchants constitutes a major
deviation from the South African and U.S. law position. Both of these
countries allow the aggrieved party, even if he is a merchant, an election
between terminating the contract and claiming specific performance, without
the need to reserve that right by giving notice to the non-performing obligor.
D. Repudiation
Anticipatory breach of contract is usually dealt with under the provisions
of delay.[182] Even though performance is not past due, the aggrieved party
has the same remedies, termination or damages for non-performance, as with
delay.[183] The aggrieved party will, however, have these remedies
immediately upon the declaration by the debtor that he will not perform.[184] BGB Section 326(2) governs a comparable class of cases, namely if, as
a consequence of the delay, performance in terms of the contract is of no use
to the obligee, he [page 615] need not fix a time for performance. In such cases
the obligor too must know that performance is futile, so the setting of a period
for performance is dispensed with.[185] In the case of anticipatory breach,
the irregularity consists of the obligor's own announced decision that he will
not perform. It would be futile to set a time for performance and await it. It
is, of course, required that the obligor make it unequivocally clear that he
is not going to perform in terms of the contract when performance is due.[186] In this sense, German law paints a picture very similar to South
African and U.S. law, where the materiality requirement for termination is
already met by the mere presence of repudiation and the aggrieved party is
therefore immediately entitled to terminate the contract.
E. Positive Breach of an Obligation (Positive Forderungsverletzung)
The third category of default performance is not treated in the general part
of the BGB chapter on the law of obligations. The courts began to develop the
general theory of breach of contract other than delay and impossibility on the
basis of Section 242 BGB.[187] It is recognised today that pursuant to
Sections 280, 286, 325, and 326 BGB the obligee can claim damages or,
possibly, can avoid the contract if he incurs a loss because of an
insufficient performance for which the obligor is responsible. Courts have
applied by analogy the remedies available for impossibility and delay.[188]
The basic requirements to be met before the remedies for positive breach of
an obligation are available, are the following:[189]
An insufficient performance occurs when the obligor, by action or omission,
fails to comply with a contractual duty [190] and the obligee consequently
incurs a loss even though the obligation was timely performed.[191] [page 616]
These qualifying factors, however, only determine whether or not there
was a positive breach of contractual duty, and not whether the aggrieved party
is entitled to terminate the contract. Horn, Kotz, and Leser state [192]
that there is "still a difference between principal and ancillary duties as
regards the legal consequences of breach: only breach of a principal duty
leads to damages for non-performance of the contract as a whole or to
rescission of the contract; in other cases damages are awarded to compensate
for the harm actually suffered, which can admittedly exceed the value of the
performance." The differentiation between principal and ancillary duties goes
a long way toward expressing a requirement for a material breach, but is not
foolproof. An obligor can arguably breach a principal duty of the contract,
but only in some minor way. Such a trivial breach can hardly be serious enough
to justify termination of the agreement, but a test looking only at whether a
principal duty was breached, does not draw this distinction. Alternatively, an
obligor may breach an ancillary duty but to such an extent that performance
becomes worthless to the obligee. The breach should, in turn, be sufficient
grounds for termination. Not all writers explain the grounds for termination
in terms of principal and ancillary duties, however. An explanation more in
line with that of South Africa and the United States is that the aggrieved
party may only terminate the contract if the violation of the contractual duty
jeopardises the whole purpose of the contract [193] to the extent that it
would be unreasonable in good faith to force the creditor to continue the
contractual relationship with the debtor,[194] or where the creditor has no
more interest in the specific performance.[195]
A claim for the positive breach of an obligation is a residual claim -- it
may only be used if the irregularity is not actionable under any other basis
of claim in the BGB.[196] In the leading case considered by the
Reichsgericht in 1902,[197] a gravel merchant contracted to supply gravel
to a bridge builder. Payment was to be on the basis of the size of the
completed bridge. The builder, however, also used gravel for construction of
the approach roads, thus falsifying the payment calculation. The court held
that there was no delay, nor was the payment impossible or performance
defective, but held that positive breach of contract had occurred and that the
supplier could rescind the contract.
Even though the BGB makes explicit provision for defective goods in sales
contracts, this remedy remains of considerable importance. The following
sections from the seventh section of the BGB, Particular obligations, First
title: [page 617] Sale and Exchange, is relevant in explaining how this general
remedy may still be preferred over the specialist provisions.
(1) The seller of a thing warrants the purchaser that, at the time when
the risk passes to the purchaser, it is free from defects which diminish or
destroy its value or fitness for its ordinary use, or the use provided for in
the contract. An insignificant diminution in value or fitness is not taken
into consideration.
"Section 462. Cancellation, reduction.
On account of a defect for which the seller is responsible under the
provisions of Sections 459, 460, the purchaser may demand annulment
of the sale (cancellation), or reduction of the purchase price (reduction)."
"Section 463. Compensation for non-performance.
If a promised quality in the thing sold was absent at the time of the
purchase, the purchaser may demand compensation for non-performance instead of
cancellation or reduction. The same applies if the seller has fraudulently
concealed a defect."[198]
Under Section 459, defective performance may only be remedied by rescission
of the contract and return of the money. However, there is no compensation for
lost profits.[199] In contrast, the use of a claim under positive breach
may result in compensation for any consequent harm.[200] It would appear
that the courts do [page 618] allow a choice between a claim for positive breach
and one under Section 459. For example, in the case of the poisonous horse
fodder,[201] a farmer delivered horse feed which contained a poisonous
component. As a result of using the feed, two horses died. The farmer complied
with the requirements of the BGB and with the contractual obligations entered
into in terms of the performance of the delivery, but injured the property of
the creditor. The horse owner could not claim against the farmer on the
grounds of impossibility (Section 280 et seq.) or delay (Section
Section 320 et seq.). Performance was possible and the preconditions for
delayed performance and rescission had not been met. Section 459 et seq. would
allow a claim for defective goods and impose liability for a defect in the
quality of the thing, but would award only the price of the fodder itself and
not compensation for the harm caused. Neither would a claim under Section
463 (lack of quality) compensate the damage. Positive breach of obligation
would be the only basis for such a claim (i.e. where the defective goods
themselves caused damage), and this was upheld in the case. Therefore, where a
seller warranted the quality of his product or acted fraudulently, Section
463 can be used to claim compensation for consequential damage, but where a
seller acted negligently, the buyer will need to use this residual remedy to
get his positive interest. It is therefore used as a gap-filling device to
recover consequential damages which are otherwise recoverable only under the
restrictive prerequisites of BGB Section 463.[202]
In summary, German law allows the termination of a contract for positive
breach of a duty only where the breach was material. In determining whether
the breach was material, German law uses tests, some of which are similar to
those in South African and U.S. law and some which differ, but all of which
lead to a similar result.
F. Conclusion
German law does not have a general requirement that breach should be
material before the aggrieved party will have the right to terminate the
contract. The application of the provisions of the BGB and HGB and the
principles enunciated by the courts do, however, lead to results similar to
those of South African and U.S. law which require a material breach of
contract as a prerequisite for the right to terminate the contract. [page 619]
V. UNIDROIT PRINCIPLES REGARDING THE RIGHT TO TERMINATE A CONTRACT FOR BREACH
From the discussion of the general principles of South African, U.S., and
German law, regarding the termination of a contract due to the breach of a
contracting party, it appears that there are some principles common to all of
the three systems.
In the first place, consistent with the principle of pacta sunt servanda,
the breach must be material before the aggrieved party will have the right to
terminate the contract. The right to terminate the contract is the most
extreme of remedies and runs contrary to the nature of a contract. The policy
of national legal systems is therefore to allow the aggrieved party to insist
on specific performance by the non-performing party and to claim damages
suffered as a consequence of the breach of the non-performing party to put the
aggrieved party in the position he would have been in had there been no
breach. Only in select situations do the national systems allow the aggrieved
party to terminate the contract and claim only damages and not specific
performance. To qualify as one of the select situations where an aggrieved
party has the right to terminate the contract, the breach must be material.
Not all three of the legal systems express the requirement for materiality in
a similar fashion or in so many words, but the application of the principles
of each system lead to similar results.
In the second place, under South African and U.S. law, the aggrieved party,
even upon material breach of the contract, may elect between specific
performance and termination. Even though, in a limited number of situations,
they go as far as saying that the materiality of the breach is presumed, they
do not prescribe to the aggrieved party whether termination should take place
or not. German law restricts the choice of the aggrieved party in a number of
cases regarding delay.
Thirdly, any form of breach can give rise to the right to terminate a
contract if it is sufficiently serious. Four forms of breach can be
identified: delay, defective performance, repudiation, and impossibility
attributable to the fault of one of the parties.
More generally, the three systems do not use identical constructions to
explain the availability of the remedy and the applicable law is not found in
identical sources or in identical formats. The unique approach followed by
each system could lead to time-consuming research and uncertainty between the
parties concerning their legal position.
The focus will now shift to the extent to which the UNIDROIT Principles
reflect the three general principles identified above and how they improve on
the disparate nature of the national legal principles. [page 620]
A. General Remarks
While national legal systems are often encumbered by a vast amount of
caselaw or treaties and bear the burden of centuries of policy changes, the
UNIDROIT Principles are in the unique position of starting on a clean slate.
The drafters of the Principles were very much aware of this unique opportunity
when they drafted the Principles.
The very first qualities of the Principles to be commended, are their
conciseness and their clarity. The Principles, even without their comments,
are clear, concise, and well organised. They are, furthermore, easily
accessible via electronic databases and the Internet.[203]
A further laudable characteristic of the UNIDROIT Principles is their use of
a set of terms not associated with any particular national legal system. When
interpreting the Principles, care should therefore be taken not to approach
them from the point of view of any national legal system or to summarily
ascribe meanings to terms simply because they seem to coincide with existing
legal terms. While the Principles contain several general contract law
principles common to most national legal systems, they are still separate and
independent from those national legal systems.
In this independence and uniqueness of the UNIDROIT Principles, lies also
one of their biggest problems -- the lack of a frame of reference. In the case
of a question on the interpretation of any of the Principles, there is very
little supplemental material. This, however, is to be expected, and hopefully
through the frequent use of the Principles some form of "precedent" will be
built up.
The UNIDROIT Principles allow for the termination of a contract "where the
failure of the other party to perform an obligation under the contract amounts
to a fundamental non-performance."[204] The Principles do not use the
traditional term "breach," but opted instead for the more neutral term
"non-performance." This neutral term includes not only breach, but also other
circumstances which do not amount to what is traditionally referred to as
breach, such as situations where performance becomes impossible due to
circumstances not attributable to the fault of either of the parties. In this
regard the Principles most resemble the Restatement which uses "material
failure" in a similar way.
In Principles terminology, a breach is referred to as a "non-excused non-
performance." Only a "fundamental non-excused non-performance" will allow the
aggrieved party to terminate the contract and claim damages from the
non-performing party. There are therefore three essential terms used and each
of them is accompanied by a set of requirements. The following discussion will
define each of these three terms. [page 621]
B. "Non-performance"
Article 7.1.1 defines non-performance as the "failure by a party to perform
any of its obligations under the contract, including defective performance or
late performance."[205] As is clear from this definition, two forms of
conduct -- positive non-performance (or defective performance) and delay -- are
expressly included in this definition. It is also clear, however, that these
are not the only forms of conduct included in the definition. The extent of
the definition's application to other forms of failure remains undetermined.
Article 7.3.3 provides as follows:
The comment to this article makes clear that anticipated non-performance is
to be equated with a non-performance that occurred at the time when
performance fell due.[207] Where it is clear that the performance of one
party will not take place, that party's conduct must be treated as if he has
already failed to perform his obligations under the contract. It is required
that it be clear that there will be non-performance; a suspicion, even though
it may be well-founded, is not sufficient.[208] An express repudiation of
the contract or circumstances that indicate that there will be non-performance
will be sufficient to constitute anticipatory non-performance. The comments [209] provide the illustration of A promising to deliver oil to B by the M/S
Paul in Montreal on February 3. On January 25, the M/S Paul is still two
thousand kilometres from Montreal and will not arrive in Montreal before
February 8 at the speed it is making. In these circumstances, B may treat the
situation as if it is already 3 February and the M/S Paul has not arrived in
Montreal. Although anticipatory non-performance is not expressly included in
the definition of non-performance, it must be treated as such as soon as it is
clear that anticipatory non-performance is present.
The comments to Article 7.1.1 state that non-performance includes all forms
of defective performance as well as complete failure to perform. [page 622]
Presumably, therefore, any failure whatsoever must be included in the
definition of non-performance and so too must impossibility attributable to
the fault of one the parties and even impossibility not so attributable.
In conclusion, the UNIDROIT Principles reflect the third general principle
of national law identified above in that any of the four forms of breach can
potentially give rise to the right to terminate the contract.
Non-performance is a neutral concept and does not indicate that the
non-performing party will be held liable or responsible for any consequences
attributable to that non-performance. The mere determination of the presence
of a non-performance will not entitle the aggrieved party to claim damages
from the non-performing party. Whether or not a party will be held responsible
for those consequences, must be found in one of the remaining two terms
identified in the crucial concept of "fundamental non-excused
non-performance."
C. "Non-excused"
As was indicated above, the definition of non-performance includes all
failures to perform. However, a non-performing party cannot be held
responsible for the consequences attributable to his non-performance in all
circumstances. The UNIDROIT Principles therefore distinguish between
"non-excused" and "excused" non-performance. Although a party who has not
received performance will as a rule be entitled to terminate the contract
whether or not the non-performance is excused, he is not entitled to claim
damages or specific performance of an excused non-performance of the other
party. As may be recalled, this paper is only focusing on the situations where
the aggrieved party chooses not to insist on specific performance, but to
claim damages to put him in the position he would have been in had there been
no breach of contract. In Principles terminology this is the situation where a
party chooses to terminate the contract for non-excused non-performance. Had
the performance been excused, the aggrieved party would not have been able to
claim damages.
The Principles do not expressly state when non-performance is non-excused,
but rather approach the issue by stating when non-performance is excused. In
the first place, Article 7.1.2 provides that "[a] party may not rely on the
non-performance of the other party to the extent that such non-performance was
caused by the first party's act or omission or by another event as to which
the first party bears the risk."[210] This Article contemplates the typical
situation where one party's non-performance was caused by the other's conduct.
In these cases, the non-performing party's conduct is removed from the realm
of "non-performance" and none of the usual consequences of non-performance
arise.[211] The article also contemplates the possibility of one party's
interference acting [page 623] only as a partial impediment to performance by
the other party in which case it will be necessary to decide the extent to which
non-performance was caused by the first party's interference and to which
extent it was caused by other factors.[212]
Article 7.1.2 further contemplates the situation where the impossibility
results from an event the risk of which was expressly or impliedly allocated
by the contract to the party alleging non-performance.[213] It would be
unreasonable to allow a party to rely on the non-performance of the other
party where he bears the risk of such non-performance.
Secondly, Article 7.1.3 provides that where the parties are to perform
simultaneously, either party may withhold performance until the other party
tenders its performance and where the parties are to perform consecutively,
the party that is to perform later may withhold its performance until the
first party has performed.[214] Non-performance is therefore excused as
long as the other has to perform first or tender performance.
Thirdly, unexpected external events will excuse performance. Article
7.1.7(1) provides that "[n]on-performance by a party is excused if that party
proves that the non-performance was due to an impediment beyond its control
and that it could not reasonably be expected to have taken the impediment into
account at the time of the conclusion of the contract or to have avoided or
overcome it or its consequences."
In the absence of one of these three situations, the non-performance is
non-excused and will give rise to a claim for damages by the aggrieved party.
D. "Fundamental"
It is not every non-excused non-performance that allows the aggrieved party
to terminate the contract. The non-excused non-performance must be of a
sufficiently serious nature to justify such termination and this requirement
is expressed by the term "fundamental." This requirement that non-performance
be fundamental reflects the first general principle of national law identified
above, namely that the breach must be material. In this regard, the crucial
Article 7.3.1(2) provides as follows:
The comment to Article 7.3.1 explains that whether, in the case of
non-performance by one party, the other should have the right to terminate the
contract, depends upon the weighing of a number of considerations.[216] The
late or defective performance may be completely useless to the aggrieved party
or the non-performing party's behaviour may be such that it would be unjust
not to allow the aggrieved party to terminate. On the other hand, the drafters
considered the serious detriment that termination may cause for the
non-performing party whose expenses in preparing for and tendering performance
may not be recovered. A weighing of these opposing interests, may lead to the
conclusion that the non-performance is fundamental, i.e. material and not
merely of minor importance. Such a conclusion may also be expressed as meaning
that the interests of the aggrieved party will be more adversely affected if
the contract is not terminated, than the interests of the non-performing party
if it is. If this is the conclusion, the aggrieved party will have the right
to terminate the contract.
This even-handed weighing of the interests of the non-performing party and
the aggrieved party may at first sight appear unusual. When it is kept in mind
that Article 7.3.1 covers both situations of excused and non-excused
non-performance, the reasoning behind this approach becomes clearer. In the
case of excused non-performance, the Principles must, without picking sides,
decide whether it would be in the interest of both parties to keep the
contract alive. The [page 625] factors to be considered in determining whether
termination is allowed, should reflect the possibility of this type of neutral
judgement.[217]
The determining factors must also allow for the situation where
non-performance is not excused and the feeling is created that the
non-performing party is somehow responsible for his non-performance. In this
situation a completely neutral judgement would be unsuitable. The Principles
therefore make provision for this eventuality by including in the factors to
be considered a number of provisions looking specifically at the
non-performing party and his frame of mind. The goal of the provisions is to
protect the aggrieved party from an intentional or reckless non-performer.[218]
The first factor influencing the determination entails two distinct parts.
In the first place, the aggrieved party must be substantially deprived of what
it was entitled to expect at the time of the conclusion of the contract. The
Principles make no further effort to explain "substantial deprivation." This
is presumably a requirement similar to the substantial performance doctrine in
U.S. law and the requirement that breach should go to the root of the contract
in South African law. The Article then continues to provide that the aggrieved
party cannot terminate the contract if the non-performing party can show that
it did not foresee, and could not reasonably have foreseen, that the
non-performance was fundamental for the other party.[219] Even if the
non-performance is seriously detrimental to the aggrieved party, he may not
terminate the contract if the non-performing party did not foresee or could
not reasonably have foreseen that result. The exact interpretation to be
ascribed to this exception is perplexing and two possible interpretations are
present.
This exception may firstly be interpreted as an attempt to reinforce the
difference between excused and non-excused non-performance. If a party did not
foresee and could not reasonably have foreseen the result, it was probably
attributable to an act of God and would then fall within the exception for
unexpected external events. Under this interpretation, less weight should be
given to the deprivation of the aggrieved party where the non-performing
party's non-performance was excused.
This is not, however, the way the comments seem to interpret the exception.
The comments seem to focus not on the non-performance and whether or not it
was foreseeable, but on whether it was foreseeable that the non-performance
would be fundamental, in other words, they focus on the consequences of the
non-performance. Differently stated, they seem to say that the fundamentalness
of the non-performance depends on whether or not it was foreseeable that it
would be fundamental. This argument is distinctly circular.
Although the first interpretation would seem to be the more acceptable one,
there is no indication that it is what the drafters had in mind. Instead of
[page 626] clearing up the question, Illustration 3 accompanying Article
7.3.1(2)(a) rather adds to the confusion. A undertakes to remove waste from B's
site during 1992. B fails to inform A that B has hired excavators at high cost
to begin work on the site on 2 January 1993. B cannot terminate its contract
with A on the ground that A had not cleared the site on 2 January. In this
example, both of the possible interpretations are covered. A could not
reasonably have foreseen, in the first place, that B would suffer injury and in
the second place, that the injury would be fundamental. If anything, this
illustration more aptly explains Article 7.3.1(2)(b).
According to Article 7.3.1(2)(b) the second factor to be considered is
whether strict compliance with the obligation which has not been performed is
of essence under the contract. Here it is not the actual gravity of the
performance that is important, but the nature of the contractual obligation
for which strict performance might be of essence.[220] Not only provisions
expressly made of the essence of the contract, but also provisions that are
impliedly of the essence are included here. This is a principle also found in
South African, U.S., and German law and allows for not only the enforcement of
the express provisions of the contract, but also for the protection of an
aggrieved party where the contract fails to regulate a particular situation,
but good faith or fair dealing necessitates a certain course of action. In
this regard, the actions that reasonable parties would have taken in similar
circumstances may be relevant.[221] The comments state that "in a contract
for sale of commodities the time of delivery is normally considered to be of
the essence, and in a documentary credit transaction the documents tendered
must conform strictly to the terms of the credit."[222] From especially the
first part of this sentence, it appears that custom may also lead to the
conclusion that a specific term was of the essence of the contract. This
further enforces the suggestion that the actions of reasonable parties may be
relevant.
The fact that this second factor "looks not at the actual gravity of the
non-performance,"[223] may imply that the perplexing first factor analysed
above does look at the gravity of the non-performance.
Paragraph 2(c) is one of the provisions that focuses on the non-performing
party and protects the aggrieved party against a contracting party who
intentionally or recklessly fails to perform. This Article recognises that
conduct of this nature will undermine the confidence the aggrieved party has
put in the non-performing party and allows him to terminate their
relationship. Non-performance will not always be fundamental simply because of
the intentional or reckless conduct of the non-performing party. The comments
warn that it may be [page 627] contrary to good faith,[224] to terminate a
contract if the non-performance, even though committed intentionally, is
insignificant.
Closely connected with the previous paragraph, is paragraph 2(d) which
provides that conduct which gives the aggrieved party reason to believe that
it cannot rely on the other party's future performance must be considered when
determining whether non-performance is fundamental. An intentional breach may
sometimes show that a party cannot be trusted.[225] In this case, the fact
that non-performance may be of an insignificant nature, will not prevent its
being fundamental. Illustration 4 [226] gives the example of A, the agent of
B, who is entitled to reimbursement for expenses and submits false vouchers to
B. Although the amounts claimed are insignificant, B may treat A's behaviour
as a fundamental non-performance and terminate the agency contract. This
illustration reveals the broad reach of the term "fundamental." A
determination of fundamentalness is influenced not only by the consequences of
the non-performance for the transaction at issue, but also for future
transactions between the parties.
The last factor to be considered when determining whether a non-performance
was fundamental, is one which should carry more weight when looking at excused
non-performance, but should not be ignored completely when dealing with
non-excused non-performance. Regard must be had to the extent to which a party
who fails to perform, has relied on the contract and has prepared or tendered
performance and how much he stands to lose should the contract be terminated.
Non-performance is less likely to be treated as fundamental if it occurs late,
after the preparation of performance, than if it occurs early before such
preparation.[227] Whether a performance tendered or rendered can be of any
benefit to the non-performing party if it is refused or has to be returned to
that party is also of relevance.[228]
In conclusion, if the conduct of a party amounts to a non-excused
fundamental non-performance as defined above, the other party will have the
right to terminate the contract.
In addition to the general rule formulated above, the Principles expressly
regulate delay and anticipatory non-performance further.
E. Delay
Before a party will be allowed to terminate the contract under the general
rule discussed above, it must be determined that the non-performance is [page 628] fundamental. In the context of delay, it means, for example, that the
aggrieved party informs the non-performer at the conclusion of their contract
that timely performance is essential and the non-performer nevertheless
proceeds to perform 3 weeks late. In this situation, and with reference with
articles 7.3.1 (b) and (c), it can be safely concluded that the
non-performance was fundamental and the aggrieved party will be entitled to
terminate the contract.[229]
Suppose, however, that the parties only agreed that performance should take
place within a reasonable time and there are no other circumstances indicating
that timely performance is fundamental. One party fails to perform within a
reasonable time. Are there circumstances in which the aggrieved party may
terminate the contract?
According to Article 7.3.1(3), in the case of delay, "the aggrieved party
may also terminate the contract if the other party fails to perform before the
time allowed it under Article 7.1.5 has expired."[230] The comment to this
section provides that it refers to Article 7.1.5, paragraph (3), which
provides that the aggrieved party may use the Nachfrist procedure to terminate
a contract which may not otherwise be terminated for delay. Article 7.1.5,
paragraph 3 provides as follows:
By giving notice to the non-performing party, the aggrieved party makes
timely performance an obligation which must be strictly complied with (to use
the words of Article 7.3.1, paragraph (b)) and failure of the non-performing
party to perform within the extended period, will be fundamental
non-performance. During the additional period the aggrieved party may withhold
performance of its own reciprocal obligations and may claim damages, but may
not resort to any other remedy.[232] If the aggrieved party receives notice
from the other party that [page 629] the latter will not perform within the
additional period, or if upon expiration of the additional period performance
has not been made, then the aggrieved party may resort to any remedy available
under the Principles chapter on non-performance.[233] These remedies
include the right to terminate the contract or, alternatively, to claim
specific performance. In both cases the party may claim damages. The aggrieved
party will only have the right to terminate the contract if the period of
extension was reasonable.
In this last respect, the Principles differ substantially from the German
procedure of Nachfrist. Under German law, if the obligee has given notice and
the obligor has not performed within the period of grace, the obligee may no
longer claim performance.[234] The contract may then only be wound up --
either by a claim for damages for non-performance, or by a claim for
rescission. Both of these remedies amount to termination of the contract. A
claim for specific performance is expressly prohibited by the Section326(1)
of the BGB and the options available to the aggrieved party are limited
thereby.[235] The approach taken by the Principles is preferable to the
German law approach. The aggrieved party should have as many options as
possible to choose from and should only be limited where the non-performing
party has materially changed his position in reliance on the conduct of the
aggrieved party. In this regard, the Principles more closely resemble the
position taken by South African and U.S. law.
Further, it should be noted that the Principles also give the aggrieved
party the right to follow the route of Nachfrist, even where the
non-performance was fundamental, without the need for an extended period of
notice.[236] As soon as the aggrieved party gives the extension, he (at
least temporarily) loses the right to resort to any remedies except for a
claim for damages during the extended period. If the non-performing party
performs during the period, the aggrieved party loses the right permanently,
but if the non-performing party fails to perform or indicates that it will not
perform, the right to terminate the contract springs into life again.[237]
A party may not use the Nachfrist procedure when the obligation which has
not been performed is only a minor part of the contractual obligation of the
non-performing party.[238] In the case of a trivial non-performance, not
even the use of the Nachfrist procedure will entitle the aggrieved party to
terminate the contract. [page 630]
South African, U.S., and German law recognise that time is normally of
the essence in mercantile transactions. The comment to Article 7.3.1 also
states that "in contracts for the sale of commodities the time of delivery is
normally considered to be of the essence." Article 1.8 reinforces this brief
reference by providing that the parties are bound not only by any practice
which they have established between themselves, but also by a usage that is
widely known to and regularly observed in international trade by parties in
the particular trade concerned except where the application of such a usage
would be unreasonable.
F. Anticipatory Non-performance
As indicated earlier, anticipatory non-performance is included in the
definition of non-performance and subject to the general rules formulated
above. Article 7.3.3 reaffirms this by providing that "where prior to the date
of performance by one of the parties it is clear that there will be a
fundamental non-performance by that party, the other party may terminate the
contract."
Article 7.3.4 extends the right to termination even further. A party, who
reasonably believes that there will be a fundamental non-performance by the
other party, may demand adequate assurance of due performance and may
meanwhile withhold its own performance.[239] Where assurance is not
provided within a reasonable time, the party demanding it may terminate the
contract.[240] Article 7.3.4 finds application where article 7.3.3 cannot
be invoked because there is still a possibility that performance may take
place.[241] What constitutes an adequate assurance will depend on the
circumstances of each case.
G. Notice of termination
Article 7.3.2 provides how termination is to take place:
"(2) If performance has been offered late or otherwise does not conform to
the contract the aggrieved party will lose its right to terminate the contract
unless it gives notice to the other party within a reasonable time after it
has or ought to have become aware of the [page 631] offer or of the non-conforming performance."[242]
This Article, in effect, shifts the burden to the aggrieved party to express
his dissatisfaction with the late or non-conforming performance, or face the
consequence of losing his right to terminate the contract. It is not entirely
clear what will happen once the aggrieved party loses his right to terminate.
The Principals do not state whether he loses the right in perpetuam, or
whether he can somehow regain the right, for example by using the provisions
of Article 7.1.5. What a reasonable time is, will, of course, depend on the
circumstances of each case. The notice becomes effective when it reaches the
non-performing party.[243]
H. Additional provisions
One of the truly innovative provisions of the UNIDROIT Principles, which
more resembles a rule found in consumer protection legislation than in
commercial codes, is Article 7.1.4 which provides as follows:
This Article allows the non-performing party to unilaterally suspend and
even preclude the aggrieved party's right to terminate the contract. The
Article favours the preservation of the contract because it allows the
non-performing party to extend the period for performance, unless timely
performance is required by the agreement or the circumstances.[245]
The danger of a provision such as the one under consideration is that the
aggrieved party may find itself in a position where it has to await
performance pursuant to the notice of the non-performing party, even where the
likelihood of actual performance is slim. To avoid this, the provisions of
Article 7.1.4 require that cure must be appropriate in the circumstances.
Factors relevant in determining whether cure is appropriate include: (i)
whether the proposed cure promises to be successful in resolving the problem;
(ii) whether the necessary or probable delay in effecting cure would be
unreasonable or would itself constitute a fundamental non-performance; and
(iii) whether the aggrieved party changed its position before receiving notice
of cure.[246] Cure may not take place where the aggrieved party has a
legitimate interest in refusing cure. The comments indicate that "legitimate
interest" is narrowly interpreted to include for example situations where it
is likely that the non-performing party will cause damage to person or
property when attempting to cure, but not where the aggrieved party "simply
decided that it does not wish to continue contractual relations."[247]
The aggrieved party is further protected by the requirement that cure should
be effected promptly. The comments state that time is of the essence in the
exercise of the right to cure.
The notice of cure has important implications on the right to terminate.
Even where an aggrieved party has already validly terminated the contract
pursuant to Article 7.3.1, the non-performing party may suspend the effect of
that termination by giving notice of cure. If the non-performance is cured,
the notice of termination is inoperative. If the non-performance is not cured
by the time the time for cure has expired, then termination takes effect at
that time. The parties may find themselves in a position where the existence
of their contract depends on what is a reasonable period within which the cure
must take place. Although [page 633] this could lead to a substantial amount of
uncertainty, it is the only way in which a problem such as the instant one can
be addressed.
In conclusion, this innovative provision is an exception to the general
principle found in national law that an aggrieved party has an election
between remedies available. It provides a non-performing party with a
unilateral right to suspend and even extinguish the aggrieved party's right to
terminate a contract.
(1) Termination of the contract releases both parties from their
obligation to effect and to receive future performance.
(2) Termination does not preclude a claim for damages for non-performance.
(3) Termination does not affect any provision in the contract for the
settlement of disputes or any other term of the contract which is to operate
even after termination."[19]
(2) the performance is due, and
(3) he is aware or must be deemed aware of the nature of the performance
required of him and the fact that it is due.[26] The requirement that the
performance must be due merits further discussion as it influences the hurdle
calling for the materiality of the breach.
(a) the extent to which the injured party will be deprived of the benefit
which he reasonably expected;
(b) the extent to which the injured party can be adequately compensated
for the part of that benefit of which he will be deprived; [page 599]
(c) the extent to which the party failing to perform or to offer to
perform will suffer forfeiture;
(d) the extent to which the party failing to perform or to offer to
perform will cure his failure, taking account of all the circumstances
including any reasonable assurances;
(e) the extent to which the behaviour of the party failing to perform or to offer to perform comports with standards of good faith and fair dealing."[90]
(a) those stated in s 241; [113]
(b) the extent to which it reasonably appears to the injured party that
delay may prevent or hinder him in making reasonable substitute arrangements;
(c) the extent to which the agreement provides for performance without
delay, but a material failure to perform or to offer to perform on a stated
day does not of itself discharge the other party's remaining duties unless the
circumstances, including the language of the agreement, indicate that
performance or an offer to perform by that day is important."[114]
(b) the obligor must be responsible for not performing in time; [163] and
(c) the obligee must issue a warning after performance has become due.[164] Delay will occur without the need of a warning being given if the
contract has fixed the actual date of performance [165] or if the obligor
has expressly or impliedly refused to make performance.
(2) the obligee is required to have suffered damage as a result of the
breach; and
(3) the obligor must be at fault.
(2) The seller also warrants that, at the time the risk passes, the thing
has the promised qualities."
Where prior to the date for performance by one of the parties it is clear
that there will be a fundamental non-performance by that party, the other
party may terminate the contract."[206]
(a) the non-performance substantially deprives the aggrieved party of
what it was entitled to expect under the contract unless the other party did
not foresee and could not reasonably have foreseen such result;
(b) strict compliance with the obligation which has not been performed is
of essence under the contract;
(c) the non-performance is intentional or reckless;
(d) the non-performance gives the aggrieved party reason to believe that
it cannot rely on the other party's future performance;
(e) the non-performing party will suffer disproportionate loss as a result
of the preparation or performance if the contract is terminated."[215]
(1) The non-performing party may, at its own expense, cure any
non-performance, provided that:
(a) without undue delay, it gives notice indicating the proposed manner
and timing of the cure;
(b) cure is appropriate in the circumstances;
(c) the aggrieved party has no legitimate interest in refusing cure; and
(d) cure is effected promptly.
(2) The right to cure is not precluded by notice of termination.
(3) Upon effective notice of cure, rights of the aggrieved party that are
inconsistent with the non-performing party's performance are suspended until
the time for cure has expired. [page 632]
(4) The aggrieved party may withhold performance pending cure.
(5) Notwithstanding cure, the aggrieved party retains the right to claim damages for delay as well as for any harm caused or not prevented by the cure."[244]
The use of national law for the solution of a dispute arising from an international commercial contract is associated with a number of problems. The conventional approaches used in international commercial contracts do not solve all the problems encountered. The UNIDROIT Principles of international commercial contracts go a long way to solving these problems by establishing a balanced set of rules designed for use throughout the world irrespective of the legal traditions and the economic and political conditions of the countries in which they are to be applied.
The Principles possess a number of characteristics, illustrating the desirability of their wide spread use in international commercial contracts. One of these characteristics is that the Principles are easily accessible and clearly and concisely drafted. Furthermore, the three most important general principles of national systems regarding an aggrieved party's right to terminate a contract for breach by the other party, are reflected in the Principles. First, they allow, in most instances, an aggrieved party the choice to elect between available remedies. They secondly restrict the availability of the right to terminate a contract to cases of material breach and this requirement is often linked to the requirement that the remedy should be reasonable -- a term widely utilised in both national law and the Principles. Lastly, all forms of breach can potentially give rise to the right to terminate a contract.
In addition to effectively including the general principles of national legal systems, the Principles contain a number of innovative characteristics. They use terminology not associated with any specific national legal system and so avoid the political and socio-economical baggage associated with national policy. They allow a non-performing party the right to unilaterally suspend the aggrieved party's right to terminate a contract.
The Principles to some extent still suffer from their novelty. Their relationship with the CISG has often been analysed, but little information is available regarding their application and effectiveness in practice in arbitration awards and the like. However, the amount of attention devoted to the Principles is an encouraging indication of their importance.
In all, the Principles present a systematic and well-defined set of rules suited to international commercial contracts and possess the necessary traits to establish themselves as an authoritative source of the elusive lex mercatoria. [page 634]
FOOTNOTES
a1. Elbe J. van Vuuren, BLC, LL.B (Pretoria), LL.M (Arizona) is completing her articles of clerkship in the International Trade Law Unit of the Johannesburg law firm Webber, Wentzel, & Bowens. This article was written as partial fulfilment of a LL.M in International Trade Law.
1. See Michael J. Bonell, The UNIDROIT Principles of International Commercial Contracts: Why? What? How?, 69 TUL.L.REV. 1121, 1123 (1995).
2. See H. Booysen, The International Sale of Goods, 17 S. AFR. Y.B. INT'L. L. 71 (1991-1992); S. Viejobueno, Private International Law Rules Relating to the Validity of International Sales Contracts, 26(2) CILSA 173, (1993).
3. See Luiz Olavo Baptista, The UNIDROIT Principles for International Commercial Law Project: Aspects of International Private Law, 69 TUL.L.REV. 1209, 1220 (1995).
4. See Bonell, supra note 1, at 1144.
5. In other words, where the arbitrator is authorised by the parties to move away from the strictness of the law in favour of natural equity.
6. See Bonell, supra note 1, at 1145.
7. See Alejandro M. Garro, The Gap-Filling Role of the UNIDROIT Principles in International Sales Law: Some Comments on the Interplay Between the Principles and the CISG, 69 TUL.L.REV. 1149, 1152 (1995) (describing how the "settlement of a dispute can be kept within its international legal habitat").
8. See Bonell, supra note 1, at 1125; see also Franco Ferrari, Defining the Sphere of Application of the 1994 "UNIDROIT Principles of International Commercial Contracts", 69 TUL.L.REV. 1225, 1230 (1995) (describing how the principles provide certainty and predictability by providing rules clarifying the vague concepts of general principles and lex mercatoria); Alejandro M. Garro, The Eason-Weinmann Colloquium on International and Comparative Law: The Contribution of the UNIDROIT Principles to the Advancement of International Commercial Arbitration, 3 TUL. J. INT'L & COMP. L. 93, 94 (1995).
9. See Garro, supra note 7, at 1153; Bonell, supra note 1, at 1124.
10. THE INTERNATIONAL INSTITUTE FOR THE UNIFICATION OF PRIVATE LAW (UNIDROIT), THE UNIDROIT PRINCIPLES OF INTERNATIONAL COMMERCIAL CONTRACTS (1994) [hereinafter UNIDROIT PRINCIPLES].
11. See Bonell, supra note 1, at 1126.
12. UNIDROIT PRINCIPLES, supra note 10, Preamble.
14. Termination is also often referred to as cancellation.
15. Examples of such defects include mistake, fraud or duress. See e.g., UNIDROIT PRINCIPLES, supra note 10, at art. 3.2 (dealing with avoidance and the validity of a contract).
16. UNIDROIT PRINCIPLES, supra note 10, at art. 3.17(1) & (2).
17. See discussion infra Parts II, III, & IV.
18. South African law uses "cancellation" to refer to a strikingly similar concept. See discussion infra. On the other hand, U.S. and German law do not consistently refer to a similar concept.
19. UNIDROIT PRINCIPLES, supra note 10, at art. 7.3.5.
20. That is, the contract is not extinguished from its inception, but the future enforcement thereof by way of specific enforcement is curtailed.
21. U.N. Convention on Contracts for the International Sale of Goods, Final Act, U.N. Doc. A/CONF. 97/18 (1980).
22. See e.g., The Alienation of Land Act 68 of 1982; The Credit Agreements Act 75 of 1980; The Conventional Penalties Act 15 of 1962; The Bills of Exchange Act 34 of 1964.
23. See D. J. JOUBERT, GENERAL PRINCIPLES OF THE LAW OF CONTRACTS 201 (1987).
24. R.H. CHRISTIE, THE LAW OF CONTRACT IN SOUTH AFRICA 587 (2d ed. 1991).
25. In other words, there must be a breach of contract.
26. CHRISTIE, supra note 24, at 590.
27. Law v. Rutherford, 1924 AD 261, 262.
28. CHRISTIE, supra note 24, at 590.
29. Louw v. Trust-Administrateurs Bpk. 1971 (1) SA 896 (W), 903.
31. Breytenbach v. Van Wijk 1923 AD 541, 549.
32. See e.g., Nel v. Cloete 1972 (2) SA 150 (A), 166.
33. See CHRISTIE, supra note 24, at 600.
37. See id. at 602. South African law does not make the formal statutory distinction between civil law and commercial law as is done in Germany with the BGB and the HGB respectively.
38. Greenfield Manufacturers (Temba) (Pty) Ltd v. Royton Electrical Engineering (Pty) Ltd 1976 (2) SA 565 (A), 569.
39. Goldstein and Wolff v. Maison Blanc (Pty) Ltd 1948 (4) SA 446 (C), 453.
40. Greenfield Manufacturers, 1976 2 SA 565 (A), 569.
41. Microutsicos v. Swart 1949 3 SA 715 (A), 730.
42. See CHRISTIE, supra note 24, at 603.
44. See discussion infra Part II.E.
45. See CHRISTIE, supra note 24, at 606.
46. Oatarian Properties (Pty) Ltd. v. Maroun, 1973 3 SA 799 (A), 784.
47. The term "rescission" is here used as synonomous with "termination".
48. Spies v. Lombard, 1950 (3) SA 469 (A), 470.
49. CHRISTIE, supra note 24, at 609.
50. For example, whether the breach was material or not.
51. Van den Berg v. Tenner, 1975 (3) SA 268 (A).
52. Aucamp v. Morton, 1949 (3) SA 611 (A).
53. Greenfield Manufacturers v. Royton Electrical Engineering, 1976 (2) SA 566 (A).
57. Aucamp v. Morton, 1949 (3) SA 611 (A), 619.
58. Schlinkmann v. Van Der Walt, 1947 (2) SA 900 (E), 919.
60. Macduff & Co., Ltd. v. Johannesburg Consolidated Investment Co., Ltd., 1924 AD 573, 600.
61. Werda Hotel (Edms) Bpk v. Daras en andere, 1989 (1) SA 854 (T), Grobbelaar N.O. v. Bosch, 1964 (3) SA 687 (E), Wireohms SA (Pty) Ltd v. Greenblatt and another, 1959 (3) 909 (C).
62. Werda Hotel, 1989 (1) SA 854 (T).
63. Grobbelaar, 1964 (3) SA 687 (E), at 691D.
65. THE AMERICAN LAW INSTITUTE, NATIONAL CONFERENCE OF COMMISSIONERS OF UNIFORM STATE LAWS, General Comment, in UNIFORM COMMERCIAL CODE (1995).
66. U.C.C. Section 1.103 (1989).
67. Joseph M. Perillo, UNIDROIT Principles of International Commercial Contracts: the black letter text and a review, 63 FORDHAM L. REV. 283 (1994); Ferrari, supra note 8; Pillar Perales Viscasillas, UNIDROIT Principles of International Commercial Contracts: Sphere of Application and General Provisions, 13 ARIZ. J. INT'L & COMP. LAW 381, 386 (1996).
68. Restatement (Second) of Contracts Sections 253, 236 cmt. a (1979) [hereinafter Restatement].
71. Id. at Section 235 cmt. b.
74. The requirement of performance is tantamount to claiming specific performance.
75. RESTATEMENT, supra note 68, at Section 236(1).
77. Id. at Section 236, cmt. a.
78. 17 AM. JUR. 2D, Contracts Section 726 (1964) [hereinafter Contracts].
80. Anvil Mining Co. v. Humble, 153 U.S. 540 (1894).
82. RESTATEMENT, supra note 68, at Section 225(1).
87. Id. at Section 237, cmt. a.
88. Contracts, supra note 78, at Section 726.
89. RESTATEMENT, supra note 68, at Section 237 cmt. a.
91. Id. at Section 241 cmt. a.
92. O.W. Grun Roofing & Construction Co. v. Cope, 529 S.W.3d 258 (Tex. Ct. App. 1975).
94. RESTATEMENT, supra note 68, at Section 235(2).
95. Brown v. Guarantee Trust & Safe Deposit Co., 128 U.S. 403, 413 (1988); Cheney v. Libby, 134 U.S. 68, 77 (1890); Emerson v. Slater, 63 U.S. 28, 36 (1859); Secombe v. Steele, 61 U.S. 94, 104 (1857); RESTATEMENT, supra note 68, at Section 237 cmt. d; Contracts, supra note 78, at Section 484.
96. See discussion supra Part II, B.
97. Maryland Steel Co. v. United States, 235 U.S. 451 (1915).
99. Slater v. Emerson, 60 U.S. 224, 238 (1956).
100. See Cheney, 134 U.S. 68, 78.
101. See id. at 78; Stinton v. Dousman, 61 U.S. 461, 466 (1857).
102. See RESTATEMENT, supra note 68, at Section 242 cmt. d.
103. See Secombe v. Steele, 61 U.S. 94, 104 (1857); RESTATEMENT, supra note 68, at Section 242(c).
104. See RESTATEMENT, supra note 68, at Section 242 cmt. d.
105. See Contracts, supra note 78, at Section 484.
106. See Brown v. Guarantee Trust & Safe Deposit Co., 128 U.S. 403, 414 (1988).
107. See Cheney v. Libby, 134 U.S. 68, 71 (1890); Secombe v. Steele, 61 U.S. 94, 104 (1857).
108. See Secombe, 61 U.S. 94, at 104.
109. See Brown, 128 U.S. 403, at 414; Secombe, 61 U.S. 94, at 104; Contracts, supra note 78, at Section 486.
110. See Contracts, supra note 78, at Section 486.
112. RESTATEMENT supra note 68, at Section 242(c) applies to the situation where the parties have agreed on a specific date for performance and has been discussed in the previous paragraphs, but is included here for the sake of clarity.
113. See discussion supra Part III.B (discussing breach as non-fulfilment of a condition).
114. See RESTATEMENT, supra note 68, at Section 242 cmt. (a) and (b).
115. See id. at Section 242 cmt. c.
116. Contracts, supra note 78, at Section 489.
120. See id. at Sections 634, 634 & 639.
123. RESTATEMENT, supra note 68, at Section 243(4).
124. See New York Life Ins. Co. v. Viglis, 297 U.S. 672 (1936).
125. See Central Trust Co. v. Chicago Auditorium Ass., 240 U.S. 581, 589 (1916).
126. See Roehm v. Horst, 178 U.S. 1, 19 (1900).
127. See Contracts, supra note 78, at Section 614; RESTATEMENT, supra note 68, at Section 253(2).
128. See Contracts, supra note 78, at Section 719.
129. See RESTATEMENT, supra note 68, at Section 243 cmt. b.
130. See id. at Section 250(a). Section 250(2) states that a repudiation is also a voluntary affirmative act which renders the obligor unable or apparently unable to perform without such a breach. This situation is discussed under impossibility attributable to the fault of one of the parties.
131. See Roehm v. Horst, 178 U.S. 1, 7 (1900); Dingley v. Oler, 117 U.S. 490, 503 (1886).
132. Mobley v. New York Life Ins. Co., 295 U.S. 632, 638 (1953).
133. Contracts, supra note 78, at Section 667. Impossibility attributable to the fault of the other party is sometimes referred to as implied repudiation. See e.g., Taylor v. Johnston, 15 Cal.3d 130, 539 P.2d 425, (Cal. 1975); RESTATEMENT, supra note 68, at Section 250(2). For sake of clarity and ease of comparison, this terminology will not be used.
134. See Day v. United States, 245 U.S. 159 (1917); United States v. Gleason, 175 U.S. 588 (1900).
135. See Contracts, supra note 78, at Section 673.
136. See id. at Section 702; RESTATEMENT, supra note 68, at Section 245, cmt. a.
137. See Chicago M. & S.P.R. Co. v. Hoyt, 149 U.S. 1, 14 (1893).
138. See Roehm v. Horst, 178 U.S. 1, 18 (1900); Contracts, supra note 68, at Section 679.
139. See Anvil Mining Co. v. Humble, 153 U.S. 540, 552 (1894); Central Trust Co. v. Chicago Auditorium, 240 U.S. 581, 589 (1916); Roehm, 178 U.S. at 18.
140. See GERHARD DANNEMANN, BRITISH INSTITUTE OF INTERNATIONAL AND COMPARATIVE LAW, AN INTRODUCTION TO GERMAN CIVIL AND COMMERCIAL LAW (1993).
141. See e.g., BURGERLICHES GESETZBUCH (Civil Code) (Otto Palandt ed. 44th ed. 1985)[hereinafter BGB] Section 89a (providing principles on termination of an agency relationship).
144. The two sections provide as follows:
Section 280. Liability in case of impossibility for which one is responsible.
(1) Where the performance becomes impossible because of a circumstance for which the debtor is responsible, the debtor shall compensate the creditor for any damage arising from the non-performance.
(2) In the event of partial impossibility the creditor may, by declining the still possible part of the performance, demand compensation for non-performance of the entire obligation, if he has no desire for the partial performance. The provisions of Sections 346-356 applicable to the contractual right of rescission apply mutatis mutandis.
Section 325. Development of impossibility for which debtor is responsible.
(1) If the performance due from one party under a mutual contract becomes impossible because of a circumstance for which he is responsible, the other party may demand compensation for non-performance, or withdraw from the contract. In case of partial impossibility, if he does not desire the partial performance of the contract, he is entitled, subject to the conditions specified in Section 280(2), to demand compensation for non-performance of the entire obligation, or to withdraw from the entire contract. Instead of the claim for compensation and of the rights of rescission he may demand the right specified in the situation provided for by Section 323.
(2) The same applies in the situation provided for by Section 283, if the performance is not made before the expiration of the period, or if at that time it is in part not made. Id.
145. If both parties are at fault, the damages will be apportioned. See BGB, supra note 141, at Sections 40, 332, 426.
146. See BGB, supra note 141, at Section 280.2.a.
149. E. J. COHN, BRITISH INSTITUTE OF INTERNATIONAL AND COMPARATIVE LAW, MANUAL OF GERMAN LAW 120 (2d ed. 1968).
150. See BGB, supra note 141, at Section 280(1).
152. See BGB, supra note 141, at Section 325(1).
153. See id. at Sections 280(1) & 325(1).
154. See id. at Sections 280(2) & 325(1).
155. See id. at Section 280.4.a.
156. See id. at Sections 280(2) & 325(1).
157. See id. at Sections 280(2) & 325(1).
158. See id. at Section 280.4.b.
160. The BGB extends these rules to the situation where performance due from one party under a mutual contract becomes impossible because of a circumstance for which the other party is responsible. See BGB, supra note 141, at Section 324.
161. These sections provide as follows:
Section 284. Default by debtor.
(1) If after his obligation is due, the debtor does not perform after a warning from the creditor, he is in default because of the warning. Bringing an action for performance and service of a warning notice are equivalent to a warning.
(2) If a time is fixed by the calendar for performance, the debtor is in default without warning if he does not perform at the fixed time. The same rule applies if a notice is required to precede the performance, and the time is fixed in such manner that it may be reckoned by the calendar from the time of notice.
Section 285. No default if no liability.
(1) The debtor is not in default so long as the performance does not take place because of a circumstance for which he is not responsible.
Section 286. Compensation for default.
(1) The debtor shall compensate the creditor for any damage arising from his default.
(2) If the creditor does not desire the performance because of the default, he may, by refusing the performance, demand compensation for non-performance. The provisions of SectionSection246-356 applicable to the contractual right of rescission apply mutatis mutandis.
Section 326. Default, fixing of a period with warning of refusal.
(1) If, in the case of a mutual contract, one party is in default in performing, the other party may give him a reasonable period within which to perform his part with a declaration that he will refuse to accept the performance after the expiration of the period. After the expiration of the period he is entitled to demand compensation for non-performance, or to withdraw from the contract, if the performance has not been made in due time; the claim for performance is barred. If the performance is only partly made before the expiration of the period, the provision of Section325(1) sentence 2 applies mutatis mutandis.
(2) If, in consequence of the default, the performance of the contract is of no use to the other party, such other party has the rights specified in (1) without giving any period. Id.
162. BGB, supra note 141, at Section 284(1).
166. See id. at Section 286(1).
167. See id. at Section 326(2).
168. This requirement is very similar to the South African and U.S. requirement that time must be of the essence of the contract.
169. See BGB, supra note 141, at Section 326(1).
170. See DANNEMANN, supra note 140, at 29. This concept is similar to the requirement for a reasonable period of time found in common law countries and reminds of the South African rules requiring that a party be placed in mora ex persona.
172. See BGB, supra note 141, at Section 326(1).
173. See DANNEMANN, supra note 140, at 29; NIGEL FOSTER, GERMAN LAW & LEGAL SYSTEM 217 (1993).
174. See NORBERT HORN ET AL., GERMAN PRIVATE AND COMMERCIAL LAW 104 (Tony Weir trans., 1982).
175. See Ludwig Linder, Law of Contracts, in BUSINESS TRANSACTIONS IN GERMANY (FRG) 10-1, Section 10.04[4] (Dennis Campbell et al. eds. 1996).
176. See DANNEMAN, supra note 140, at 29.
177. HANDELSGESETZBUCH (Commercial Code) Section 376 para. 1 [hereinafter HGB].
178. This position may be contrasted with the South African position where the law is willing to recognise that time is more likely to be of the essence in a mercantile transaction, but do not go as far as prohibiting an aggrieved party to claim specific performance.
179. See DANNEMANN, supra note 140, at 29.
181. See FOSTER, supra note 173, at 217.
182. See HORN, supra note 174, at 104; FOSTER, supra note 173, at 217. Cf. Ingeborg Schwenzer, The Law of Contracts, in INTRODUCTION TO GERMAN LAW 173, 182 (Werner F. Ebke & Matthew W. Finkin eds., 1996) (treating anticipatory breach as a positive breach of an obligation).
183. See ENTSCHEIDUNGEN DES BUNDESGERICHTSHOFES IN ZIVILSACHEN [BGHZ] 11, 80, 84; BGHZ 49, 56, 59; FOSTER, supra note 173, at 217; HORN, supra note 174, at 104.
184. See HORN supra note 174, at 104.
187. See Schwenzer, supra note 182, at 182. BGB Section 242 provides that the debtor is bound to effect performance according to the requirements of good faith, giving consideration to common usage.
188. See FOSTER, supra note 173, at 221.
191. See Schwenzer, supra note 182, at 175; FOSTER, supra note 173, at 220.
192. See Schwenzer, supra note 174, at 106.
193. See DANNEMANN, supra note 140, at 31; COHN, supra note 149, at 112.
194. See BUSINESS TRANSACTIONS IN GERMANY, FRG, supra note 175, at Section 10.04[6][c].
196. See FOSTER, supra note 173, at 220; BGH NJW 1950 (1980).
198. See BGB, supra note 141, at Sections 459, 462 & 463.
199. Compensation for damage can only be claimed under BGB Section 463 where there was express warranty of quality or deceit.
200. See FOSTER, supra note 173, at 220.
202. See BUSINESS TRANSACTIONS IN GERMANY, FRG, supra note 175, at Section 10.04[6][c].
203. The Unidroit Homepage, (visited Apr. 4, 1998) <http://www.agora.stm.it>.
204. UNIDROIT PRINCIPLES, supra note 10, art. 7.3.1(1).
217. See e. g., id. at art. 7.3.1(a) & (e).
218. See e.g., id. at art. 7.3.1(c) & (d).
219. See id. at art. 7.3.1 cmt.
221. It is important to note that the Principles make extensive use of the term "reasonable" in various chapters.
222. See UNIDROIT PRINCIPLES, supra note 10, at art. 7.3.1, cmt.
225. See id. at art. 7.3.1, cmt.
226. See id. at art. 7.3.1, illus. 4.
227. See id. at art. 7.3.1, cmt.
229. See id. at art. 7.3.1(2)(b) & (c).
232. See id. at art. 7.1.5(2).
233. See id. at art. 7.1.5(2).
234. See BGB, supra note 141, at Section 326(1).
235. Note that this is contra South African law which even in this circumstance, still allows the aggrieved party an election between terminating the contract and claiming specific performance.
236. See UNIDROIT PRINCIPLES, supra note 10, at art. 7.1.5, cmt.
238. See id. at art. 7.1.5(4).
241. See id. at art. 7.3.4, cmt.
243. See id. at art. 1.9.2. Article 1.9.3 provides that "a notice 'reaches' a person when given to that person orally or delivered at that person's place of business or mailing address."
245. See id. at art. 7.1.4, cmt.
Pace Law School
Institute of International Commercial Law - Last updated September 6, 2005