Go to Database Directory || Go to Bibliography || Go to Annotated Text of CISG Article 79
Publication of the Faculty of Law of the University of Turku, Private law publication series B:55. Entered on the Internet courtesy of the CISG-Finland website, Prof. Tuula Ämmälä ed.
Tom Southerington
Turku 2001
Abstract (Finnish)
Tables
Table 1. Impossibility, force majeure and hardship
Table 2. Exemptions under the law applicable in Finland
Table 3. Exemptions under the UNIDROIT and EU Principles
Index of authorities
Official travaux préparatoires
Unpublished
Internet
Table of cases
Abbreviations
1. INTRODUCTION
1.1. The problem and objects of study
1.2. Changed circumstances and the law
1.3. Materials used and previous studies
2. IMPOSSIBILITY, FORCE MAJEURE AND HARDSHIP
2.1. Concept of impossibility
2.2. Classifications of types of impossibility
2.3. Force majeure
2.4. Hardship
2.5. Conclusions
3. IMPOSSIBILITY IN FINNISH LAW (Sale of Goods Act, CISG, Contracts Act)
3.1. Applicable law
4. IMPOSSIBILITY IN INTERNATIONAL INSTRUMENTS
4.1. UNIDROIT Principles for International Commercial Contracts 45
4.2. Principles of European Contract Law
4.3. Conclusions
5. IMPOSSIBILITY IN ENGLISH LAW
5.1. Introduction
5.2. Development of the doctrine of frustration
5.3. Operation of the doctrine
6. CONCLUSION
APPENDIX 1: Exempting events under the Sale of Goods Act (SGA) and the CISG.
1. INTRODUCTION
1.1.
The
problem
and
objects
of
study
The
main
question
addressed
in
this
study
is:
How
can
a
party
be
exempted
from
his
obligations
under
a
contract
for
the
international
sale
of
goods
in
a
case
of
changed
circumstances?
The
question
is
studied
with
reference
to
the
law
applicable
in
Finland
and
England
as
well
as
two
recent
international
instruments.
Special
attention
is
given
to
the
role
of
impossibility
of
performance
in
the
systems
studied.
The
focus
is
on
changed circumstances and therefore, for example, initial
impossibility
will
not
be
studied
in
detail.
This
is
justifiable
since
the
solutions
provided
by
the
law
differ
in
cases
of
supervening
and
pre-existing
events.
The
study
does
not
aim
at
giving
a
detailed
description
of
the
rights
and
duties
of
the
seller
and
the
buyer.
Mainly
rules
related
to
release
from
performance
or
damages
are
discussed
and
references
to
other
norms
are
scarce.
The
aim
of
the
study
is
not
so
much
in
comparing
the
individual
rules,
though
this
will
also
be
done
to
an
extent,
but
instead
the
different
structures
in
the
rule
systems.
In
other
words,
the
aim
is
to
compare
and
discuss
the
solutions
the
different
sets
of
rules
as
a
whole
provide
for
the
problem
of
changed
circumstances
and
impossibility
in
particular.
Nevertheless,
the
study
operates
on
two
levels:
individual
rule
and
system.
There
are
four
main
issues
to
which
attention
will
be
given:
The
effects
of
changed
circumstances
on
the
primary
and
secondary
obligations
(performance
and
damages)
of
the
parties
will
be
discussed.
The
nature
and
extent
of
the
changed
circumstances
acknowledged
by
the
law
will
also
receive
attention.
The
possibility
to
adjust
the
contract
and,
finally,
effects
on
the
validity
or
existence
of
the
contract
are
observed
where
appropriate.
The
studied
legal
instruments
are
the
Finnish
Sale
of
Goods
Act,
the
United
Nations
Convention
on
Contracts
for
the
International
Sale
of
Goods
(the
CISG),
the
Finnish
Contracts
Act
(briefly),
the
common
law
doctrine
of
frustration
(with
references
to
the
Sale
of
Goods
Act
1979),
the
UNIDROIT
Principles
of
International
Commercial
Contracts
(UNIDROIT
Principles)
and
the
Principles
of
European
Contract
Law
(EU
Principles).
These
laws
or
instruments
represent
different
types
of
legal
systems.[1]
The
Finnish
Sale
of
Goods
Act
belongs
to
a
Nordic
or
Scandinavian
system,
which
is
a
part
of
the
Roman-German
civil
law
system.
The
doctrine
of
frustration
represents
the
common
law
while
the
CISG
and
the
UNIDROIT
and
EU
Principles
are
internationally
drafted
instruments
which
combine
elements
from
both
civil
law
and
common
law
systems.
The
important
difference
between
the
said
Principles
and
the
CISG
is
that
the
CISG
is
binding
law
in
the
countries
that
have
accepted
it.
One
of
the
reasons
for
choosing
the
above
mentioned
objects
of
study
is
the
question
of
applicable
law
in
international
sales.
Between
parties
from
countries
that
have
ratified
or
acceded
to
the
CISG,
in
most
cases
the
CISG
is
the
governing
law.
However,
from
the
important
trade
partners
of
Finland,
Great
Britain
is
one
of
the
few
that
have
not
accepted
the
CISG.[2]
Therefore
it
may
happen
that
the
applicable
law
is
the
English
law,[3]
which
often
is
not
well
known
in
the
civil
law
countries.
The
reviewed
Principles
on
the
other
hand
may
be
applied
by
arbitral
tribunals
or
used
to
interpret
or
supplement
other
legal
instruments.
There
is
also
another
reason
for
the
choice
of
objects.
This
is
the
historical
or
evolutionary
perspective.
It
seems
that
the
law
has
gradually
changed
from
absolute
contractual
obligations,
the
strict
pacta
sunt
servanda,
towards
more
flexible
attitudes,
especially
in
relation
to
changed
circumstances.[4]
The
doctrine
of
frustration
represents
the
first
phases
of
relieving
the
strict
rules
and
even
within
the
doctrine
development
can
be
observed.
The
Finnish
Sale
of
Goods
Act
and
the
CISG
represent
a
fairly
modern
civil
law
type
of
codification.
The
same
applies
to
the
Contracts
Act
36
§,
which
allows
judicial
review
of
the
contract
on
the
basis
of
unconscionability.
The
UNIDROIT
and
the
EU
Principles
in
turn
represent
the
latest
developments
in
the
field
of
contract
law
and
combine
civil
law
and
the
common
law
as
well
as
international
contract
practices.
The
study
is
organised
so
that
the
more
familiar
civil
law
type
of
codes
are
discussed
first
and
only
after
them
the
English
system.
The
nature
of
the
material
necessarily
leads
to
a
different
kind
of
approach
since
the
common
law
is
based
on
case
law.
1.2. Changed circumstances and the law
According
to
Tallon,
in
the
nineteenth
century
contract
law
abandoned
the
doctrine
of
absolute
obligations
and
legal
systems
started
to
provide
for
the
discharge
of
one
or
both
parties
when
a
contract
becomes
impossible
to
perform.
In
many
systems
this
was
achieved
by
referring
to
the
concept
of
force
majeure,
in
England
by
the
doctrine
of
frustration.
In
the
twentieth
century
a
number
of
new
theories
emerged,
for
example
imprévision,
frustration
of
the
common
venture,
impracticability
and
Wegfall
der
Geschäftsgrundlage.
These
extended
the
existing
doctrines
beyond
the
sphere
of
absolute
impossibility
to
situations
where
unexpected
changes
in
circumstances
made
performance
far
more
expensive
than
anticipated.
In
some
legal
systems,
like
the
French,
such
situations
produce
no
effect.
In
other
systems,
like
the
English,
it
may
be
synonymous
with
impossibility,
while
in
some,
like
the
German
or
American,
it
may
allow
the
court
to
adjust
the
contract
(the
Finnish
system
would
be
in
this
category
too).
In
addition
to
these
theories,
various
types
of
contract
clauses
are
used,
such
as
hardship,
renegotiations
clause
and
the
like.[5]
Frustration
under
the
common
law
will
be
discussed
in
chapter
5
and
the
French
force
majeure
briefly
in
2.3.
According
to
Nystén-Haarala,
for
example,
the
principle
of
pacta
sunt
servanda
has
always
had
the
counter
principle
of
clausula
rebus
sic
stantibus,
under
which
a
contract
becomes
unbinding
in
the
case
of
changed
circumstances.
In
the
nineteenth
century, from
this
principle
as
well
as
from
another
principle
of
Roman
law,
namely
the
impossibilium
nulla
est
obligatio,
evolved
the
German
doctrine
of
impossibility,
which
later
was
codified
in
the
German
Civil
Code.[6]
In
the
middle
of
the
nineteenth
century, the theory
of
assumptions
arose
in
Germany.
This
theory
was
later
succeeded
by
the
doctrine
of
Wegfall
der
Geschäftsgrundlage,
under
which
a
contract
becomes
ineffective
if
the
basic
assumptions
under
which
it
was
entered into cease to exist.[7]
The
theory
of
assumptions
was
further
developed
in
Scandinavia
in
the
beginning
of
the
twentieth
century
and
is
still
in
use
at
least
in
Sweden.
In
Finland
the
theory
of
assumptions
has
been
rejected.[8]
Also
in
Germany
a
theory
of
termination
for
an
important
reason
(aus wichtigen Grund)
was
developed.
Traces
of
this
theory
can
also
be
found
in
Scandinavian
legislation.[9]
Changed
circumstances
have
also
been
addressed
by
adjusting
the
contract.
In
the
Nordic
countries
this
can
be
done
under
the
general
clause
in
Contracts
Act
36
§.[10]
There
is
also
special
legislation,
in
Finland
for
instance
on
consumer
protection
and
marriage
settlements.
Contracts
Act
36
§
will
be
briefly
discussed
in
chapter
3.4.
In
addition
to
the
above-presented
national
theories
on
changed
circumstances,
international
measures
have
been
developed.
These
combine
the
different
domestic
rules
and
compromise
between
various
approaches.
Such
instruments
are
in
this
study
represented
by
the
CISG,
and
the
UNIDROIT
and
EU
Principles.
For
example,
the
solutions
adopted
in
CISG Article 79 do not follow
any
of
the
national
laws
as
such.
It
does
not
use
the
terms
force
majeure,
frustration
or
the
like,
and
it
forms
a
system
of
its
own
autonomic
from
the
national
systems.[11]
From international instruments, the newly
formed
rules
may
find
their
way
back
into
national
systems
which
in
part
harmonises
the
law
(cf.
KL
27
§
and
CISG
Article
79,
for
example).
1.3.
Materials
used
and
previous
studies
Two
important
studies
on
impossibility
of
performance
were
published
in
the
1950's
in
Finland:
Godenhielm's
"Om
säljarens
bundenhet
under
ändrade
förhållanden"
in
1954
and
Vihma's
"Suorituksen mahdottomuus varallisuusoikeudellisessa sopimussuhteessa"
in
1956.
These
works
have
served
as
an
introduction
to
the
subject
of
impossibility
and
changed
circumstances
and
have
been
used
as
sources
of
information
mainly
in
chapter
2.
It
is
to
be
noticed
that
after
these
works
considerable
changes
have
taken
place
in
the
field
of
trade
law.
A
number
of
other
works,
such
as
Hellner's
"Speciell avtalsrätt II,"
have
also
been
valuable.
In
the
discussion
on
the
Finnish
Sale
of
Goods
Act
the
Government
Bill
93/1986
has
been
used
quite
extensively.
For
this
part
of
the
study
also
Sevón,
Wilhelmsson
and
Koskelo:
"Kauppalain pääkohdat,"
and
the
second
edition
of
this
work
Wilhelmsson,
Sevón
and
Koskelo:
"Huvudpunkter i köplagen,"
as
well
as
Eero
Routamo's
"Kaupan lait"
have
been
important.
Decisions
of
the
European
Court
of Justice
have
been
available
on
the
Celex
database.
In
chapter
3.3.
on
the
CISG,
the
main
sources
of
information
have
been
Honnold's
"Uniform
Law
for
International
Sales
under
the
1980
United
Nations
Convention,"
Schlechtriem's
"Uniform
sales
law"
and
"Commentary
on
the
UN
Convention
on
the
International
Sale
of
Goods
(CISG)"
edited
by
him,
as
well
as
"Commentary
on
the
International
Sales
Law"
edited
by
Bianca
and
Bonnell.
Also
a
number
of
articles
have
been
reviewed,
most
of
which
have
been
conveniently
available
on
the
world
wide
web
service
provided
by
the
Pace
University.
A
few
cases
have
also
been
discussed.
In
finding
them
the
Pace
www-service
has
again
been
helpful.
Chapter
4.1.
on
the
UNIDROIT
Principles
is
indebted
to
the
commentary
by
UNIDROIT
and
chapter
4.2.
on
the
EU
Principles
to
the
work
by
Lando
and
Beale
(eds.):
"The
Principles
of
European
Contract
Law,"
which
has
provided
material
for
other
parts
of
the
study
as
well.
On
the
doctrine
of
frustration,
mainly
acknowledged
textbooks
have
been
used.
These
include
most
importantly
Atiyah's
"The
sale
of
goods"
and
"An
introduction
to
the
law
of
contract,"
Cheshire,
Fifoot
and
Furmston's
"Law
of
contract"
as
well
as
Treitel's
"The
law
of
contract."
"Force
majeure
and
frustration
of
contract"
edited
by
McEndrick
has
also
been
useful.
Unfortunately, attempts
to
find
some
of
the
fairly
recent
materials
on
this
subject
have
failed.
For
example,
only
parts
of
Treitel's
"Frustration
and
force
majeure"
have
been
available
for
the
study.
2. IMPOSSIBILITY,
FORCE
MAJEURE
AND
HARDSHIP
2.1.
Concept
of
impossibility
Vihma
presents
four
definitions
of
impossibility
of
performance.
The
concept
of
impossibility
of
performance
in
every
day
use
seems
to
be
referring
to
a
situation
where
performance
by
no
means
can
be
accomplished
(at
the
time
and
in
the
manner
required).
The
performance
is
physically
impossible,
like
when
in
a
sale
of
specific
goods
the
goods
are
accidentally
destroyed.
Such
impossibility
has
been
called
natural
or
logical
impossibility.
On the other hand, the law may give impossibility less strict definitions.
It
may
also
take
into
consideration
circumstances
where
performance
is
in
practice
impossible
(practical
impossibility).
The
specific
goods
subject
to
the
sales
contract
have
not
been
destroyed
but
stolen,
for
instance.
Furthermore,
the
concept
may
include
situations
where
performance
is
illegal
(juristic
impossibility).
According
to
Vihma,
juristic
impossibility
is
sometimes
understood
more
widely
to
include
situations
where
performance
would
require
unreasonable
sacrifices.
As
examples,
he
gives
an
abnormal
rise
in
prices
and
the
death
of
a
child
of
a
comedian
just
before
the
show.[12]
In
this
study,
juristic
impossibility
is
understood
as
referring
only
to
illegality.
In his study, Vihma uses a definition of
impossibility
which
includes
logical
and
practical
impossibility
as
well
as
illegality.[13]
The
concept
is,
however,
somewhat
elusive.
According
to
Vihma, his
definition
is
well
justified
because
it
covers
all
the
occasions
where
performance
in
practice
cannot
be
done
without
infringing
the
legal order.[14]
Nevertheless,
the
definition
leaves
considerable
room
for discretion. First of all, it may in many cases be difficult if
not
impossible
to
judge
whether
performance
is
logically
impossible
or
illegal.
A
bigger
problem
yet
may
be
the
question
as
to
when
performance
is
practically
impossible.
To illustrate the problems mentioned, we may consider two examples: If
there
is
a
contract
for
the
sale
of
a
painting
by
Gallen-Kallela,
and
the
painting
is
destroyed
before
the
contract
is
fulfilled,
the
performance
of
the
contract
clearly
becomes
(logically)
impossible.
If
there
is
instead
a
contract
to
provide
a
hall
where
to
keep
concerts
as
in
Taylor
v.
Caldwell,
a
leading
case
representing
the
common
law
doctrine
of
frustration
(see
below
chapter
5),
and
the
hall
burns
down
in
an
accidental
fire
six
days
prior
to
the
concerts,
how
do
we
judge
the case? In the said case, the
court
considered
the
performance
to
have
become
impossible.[15]
It
is
submitted
that
how
we
judge
impossibility
in
this
case
may
depend, for example, on how
we
interpret
or
construe
the
contract.
A
reasonable
construction
of
the
contract
perhaps
were
that
it
was
to
allow
the
plaintiffs
to
use
one
particular
music
hall,
which
cannot
be
replaced
by
another
hall
even
if
it
would
be
exactly
like
the
one
intended
and
situated
in
the
same
place.
In
this
case
we
could
speak
of
logical
impossibility.
However,
we
might
construe
the
contract
so
that
it
could
have
been
performed
by
rebuilding
the
burned
down
music
hall
and
allowing
the
plaintiffs
to
use
the
new
one.
This
might
have
been
possible
in
the
logical
sense,
but
the
costs
and
trouble
would
have
been
enormous.[16]
Now
we
may
speak
of
practical
impossibility.
But
what
if
the
hall
had
been
destroyed
not
six
days
but
six
weeks
or
six
months
before
the
concerts?
Would
the
performance
still
have
been
impossible?
How
do
we
distinguish
practical
impossibility
from
less
serious
occurrences
like
hardship
or
mere
inconvenience?
Treitel
has
stated
in
reference
to
Taylor
v.
Caldwell
that
in
the
given
circumstances
no
reasonable
businessman
would
perhaps
be
expected
to
incur
such
expenditure
as
would
be
required
in
order
to
be
able
to
perform
the
contract.
According
to
him, this
has
lead
to
a
trend
in
the
U.S.
to
use
words
like
impractical
and
impracticality
instead
of
impossible
and
impossibility,
which
in
his
opinion
would
seem
"to
be
intended
to
widen
the
scope
of
the
doctrine
of
discharge
by
supervening
events."[17]
The
Finnish
legal
order,
including
the
CISG,
does
not
refer
to
impossibility
as
such
as
will
be
seen
later.
The
law
is
built
on
other
more
general
kind
of
concepts.
Though
according
to
Vihma,[18]
for
instance,
the
concept
of
impossibility
deserves
special
attention
in
law
and
jurisprudence,
the
situation
seems
to
have
somewhat
changed
after
his
dissertation.
It
is
submitted
that
in
Finland
especially
the
enactment
of
the
Sale
of
Goods
Act
and
the
new
36
§
of
the
Contracts
Act
as
well
as
the
adaptation
of
the
CISG
have
diminished
the
role
of
impossibility
at
least
in
sale
of
goods
cases [19]
and
that
force
majeure
type
of
concepts
(see
2.3.
below)
have
taken
its
place.
At
Vihma's
dissertation's
time,
the
only
reference
to
impossibility
was
to
be
found
in
the
Maritime
Act
(merilaki)
131
§,
now
it
is
in
chapter
14,
32
§.
In
England,
on
the
other
hand,
the
concept
of
impossibility
would
seem
to
have
more
significance
since
the
common
law [20]
doctrine
of
frustration
revolves
around
it
(see
5.3.1.6
below).
However,
as
Hellner
has
stated,
the
focus
is
not
on
the
impossibility
or
increased
difficulty
of
performance.
Instead
the
contract
as
a
whole
has
to
be
looked
at.[21]
Nevertheless,
the
concept
and
the
classifications
of
types
of
impossibility
may
be
helpful
in
analysing
cases
and
court
decisions
as
well
as
in
classifying
different
types
of
changed
circumstances.
Despite
the
difficulties
with
the
definitions
of
impossibility
described
above, it is
submitted
that
Vihma's
concept
of
impossibility
(logical,
practical
and
juristic)
would
seem
to
be
satisfactory
in
relation
to
the
material
discussed
in
this
study.
Therefore,
impossibility
in
this
study
will
encompass
logical,
practical,
and
juristic
impossibility.
However,
one
must
acknowledge
that
especially
practical
impossibility
is
a
concept
whose
scope
is
subject
to
discretion
and
seems
to
depend
on
what
is
considered
just,
reasonable
or
conscionable
in
each
case,
and
that
the
border
line
between
practical
impossibility
and
impracticability
is
negotiable.
2.2. Classifications of types of impossibility
Several
classifications
of
impossibility
have
been
introduced
in
the
literature.
Their
value
would
seem
to
be
in
distinguishing
different
kinds
of
situations
from
another
where
the
legal
consequences
of
impossibility
should
be
different.
Often
a
distinction
has
been
made
between
initial
(pre-existing,
original)
and
subsequent
(intervening)
impossibility.
Initial
impossibility
refers
to
a
situation
where
performance
has
been
impossible
already
at
the
moment the contract was concluded, whereas subsequent impossibility refers
to
situations
where
performance
was
initially
possible
but
became
impossible
after
the
conclusion
of
the
contract.[22]
As
mentioned
earlier,
this
study
concentrates
only
on
subsequent
impossibility.
Impossibility
is
therefore
seen
as
an
extreme
example
of
changed
circumstances.
The
division
of
impossibility
into
initial
and
subsequent
seems
to
be
useful
since
different
kinds
of
solutions
have
been
introduced
to
manage
some
of
these
situations.
Initial
impossibility
may, for example, lead to the use of rules related
to
mistake
or
perhaps
fraud
and
subsequent
impossibility
to
the
rules
on
frustration.[23]
Another
way
to
classify
cases
of
impossibility
is
to
divide
them
into
objective
and
subjective
impossibility.
In the first class, no
one
would
be
able
to
perform
as
required,
whereas
in
the
latter
someone
else
would
be
able
to
perform
but
not
the
party
that
has
committed
himself
to
performance.
A
division
into
final
and
temporary
(passing)
impossibility
has
also
been
made
on
the
basis
of
whether
the
impossibility
will
be
removed
in
some
future
time
or
not.
Furthermore,
impossibility
has
been
divided
into
total
and
partial
in
order
to
distinguish
whether
it
affects
the
whole
contract
or
just
some
part
of
it.
These
classifications
would
also
seem
to
lead
to
different
rules
and
rulings
in
some
cases
and
therefore
be
useful.[24]
A
division
into
absolute
and
relative
impossibility
has
also
been
made
but,
according
to
Vihma,
the
definitions
seem
to
be
unclear
and
the
usefulness
therefore
questionable.[25]
In
this
study,
however,
where
the
term
absolute
impossibility
is
used
it
refers
to
objective,
logical
impossibility.
The
above
classifications
do
not
refer
to
the
causes
of
impossibility.
However,
often
the
legal
consequences
of
impossibility
depend
on
the
cause.
Sometimes
authors
speak
of
economic
impossibility
as
a
subclass
of
subjective
impossibility.
Here
performance
becomes
impossible
due
to
a
lack
of
economic
resources.[26] Godenhielm
further
separates
economic
impossibility
from
commercial
impossibility.
Commercial
impossibility
occurs
when
the
value
of
what
is
to
be
received
in
return
for
performance
diminishes
fundamentally
(which
could
be
classified
as
a
case
of
hardship,
see
2.4.
below).[27]
Aurejärvi
does
not
seem
to
make
this
distinction.[28]
To him, economic
impossibility
is
not
real
impossibility and he, like
some
other
Finnish authors, sees
economic
impossibility
and
the
Finnish
term
liikavaikeus
as
synonyms.
It
is
submitted
that
liikavaikeus
has
been
used
in
relation
to
practical
economic
impossibility,
economic
force
majeure
or
hardship
and
the
term
lacks
distinctiveness.
Often
it
may
be
most
accurately
used
instead
of
hardship,
since
liikavaikeus
usually
does
not
exempt
from
liability
in
damages.[29]
Vihma,
in
turn,
ponders
whether
economic
impossibility
exists
or
not,
but
does
not
reach
a
conclusion.[30]
(See
also
2.3.
and
2.5.
below.)
Often
a
case
of
practical
impossibility
could
be
described
as
economic
impossibility,
consider
for
example
the
facts
in
Taylor
v.
Caldwell.
According
to
Treitel,
in
the
common
law
an
obligation
to
pay
money
is
never
considered
to
be
impossible.
[31]
It
should
be
noted
that
an
obligation
to
pay
money
might
still
be
impossible
in
fact,
though
the
law
does
not
acknowledge
this.
Different
rules
apply to
monetary
and
non-monetary
obligations
also
in
the
Principles
discussed
in
this
study
and in
the
Finnish
Sale
of
Goods
Act.
A
force
majeure
type
of
approach
would
not
categorically
rule
out
the
possibility
of
an
exemption
from
(damages
for
a
breach
of)
an
obligation
to
pay
money
but
would
rather
consider
the
causes
of
the
inability
to
perform.
We
may
also
make
the
division
into
self-caused
and
other
impossibility.
Moreover,
foreseeable
and
nonforeseeable
impossibility
can
be
distinguished
from
one
another.
These
kinds
of
qualifications
bring
us
closer
to
the
concept
of
force
majeure
(see
2.3.
below).
What
kind
of
impossibility
is
relevant
in
the
legal
sense
would
seem
to
differ
between
branches
of
law,
different
jurisdictions
and
so
forth.
2.3. Force majeure
The
roots
of
force
majeure
are
in
the
Roman
concept
of
vis
maior,
and
the
term
has
been
explicitly
used
in
the
French
Code
Civil.
In
Roman
law
as
well
as
in
French
law,
force
majeure
serves
as
a
limit
to
liability
not
based
on
fault.[32]
The
term
force
majeure
does
not
have
an
authoritative
definition,
although
Schmitthoff
does
state
that
the
term
has
a
clear
meaning
in
(English)
law,
namely
that
it
includes
every
event
beyond
the
control
of
the parties.[33]
Force
majeure
has
also
been
said
to
refer
to
an
event
that
the
performing
party
is
unable
to
overcome
(for
example
war,
natural
catastrophe
or
a
ban
by
a
legal
authority),
which
prevents
due
performance,
and
which
usually
releases
the
obligor
from
liability
in
damages.[34]
Sometimes
the
term
may
be
used
as
a
general
term
referring
to
any
event
that
serves
as
a
basis
for
an
exemption
from
liability.[35]
Force
majeure
type
of
regulations
can
be
found
in
national
laws
as
well
as
in
standard
terms
and
individual
contracts.
According
to
Mestad,
a
force
majeure
rule
must
have
at
least
the
four
following
elements:
(1) a definition of relevant events (causes),
(2) a requirement that performance be prevented,
(3) a requirement of a causal link between the events and the fact that performance is prevented, and
(4) consequences of the three prerequisites being fulfilled. In addition to these essential elements the rule may also include stipulations as to
(5) foreseeability,
(6) avoiding or overcoming the event, and
(7) procedural matters the party claiming force majeure should follow.[36]
The
elements
of
force
majeure
in
French
law
(Articles
1147
and
1148
in
the
Code
Civil)
have
been
said
to
be
(1) irresistibility: the event and its consequences could not have been avoided or overcome,
(2) unforeseeability: the event must have been unforeseeable to a reasonable person at the time and in the circumstances the contract was made,
(3) externality: the cause of the event is not the performing party or persons at his responsibility,
(4) impossibility: the event has to make performance impossible, not merely more onerous (Vihma's
definition of impossibility would seem to apply here also, see 2.1. above). In French law, force majeure
leads
to
a
release
from
liability
in
damages.[37]
Similarly,
in
the
new
Russian
Civil
Code
of
1994,
force
majeure
releases
the
obligor
from
liability
for
breach
of
his
obligations
and
refers
to
an
event
that
is
extraordinary
and
irresistible
in
the
given
circumstances.[38]
In
Article
7.1.7
of
the
UNIDROIT
Principles
for International Commercial Contracts (see 4.1. below), force majeure is in
question
when
non-performance
is
caused
by
an
impediment
beyond
the
performing
party's
control
which
he
cannot
reasonably
be
expected
to
have
taken
into
account
at
the
time
of
the
conclusion
of
the
contract
and
which
or
whose
consequences
he
cannot
reasonably
be
expected
to
have
avoided
or
overcome.[39]
Article
7.1.7
exempts
the
obligor
from
performance
or
damages.
Similarly, in the Principles
of
European
Contract
Law,
a
force
majeure
type
of
rule
releases
the
obligor
from
his
primary
and
secondary
obligations.
The
commentary
to
these
Principles
connects
force
majeure
with
impossibility
(see
4.2.
below).[40]
In
the
practice
of
the
European
Court
of
Justice, force
majeure
has
been
defined
to
be
an
event
unusual,
unforeseeable
and
beyond
the
trader's
control,
the
consequences
of
which
could
not
have
been
avoided
even
if
all
due
care
had
been
exercised.[41]
Furthermore,
in
some
cases
the
Court
has
stated
that
the
consequences
of
the
event
have
to
be
such
that
the
affected
party's
performance
becomes
objectively
impossible [42] and, in association with particular
regulations,
that
absolute
impossibility
is
required.[43]
In
some
other
cases
the
Court
has
maintained
that
absolute
impossibility
is
not
required
but
that
force
majeure
nevertheless
requires
abnormal
difficulties,
independent
of
the
will
of
the
person
concerned
and
apparently
inevitable
even
if
all
due
care
is
taken.[44]
The
Court
has
emphasised
that
the
concept
of
force
majeure
differs
in
content
in
different
areas
of
law
and
in
its
various
spheres
of
application
and
that
the
precise
meaning
of
the
concept
therefore
has
to
be
decided
by
reference
to
the
legal
context
in
which
it
is
intended
to
operate.[45]
In
conclusion
it
is
submitted
here
that
in
most
cases
the
term
force
majeure
refers
to
an
external
event
that
is
unforeseeable
and
irresistible
which
makes
the
performance
of
the
contract
at
least
practically
impossible.
If
we
accept
this
definition
we
can
also
say
that
the
relation
of
impossibility
to
force
majeure
is
that
force
majeure
can
be
defined
as
qualified
impossibility:
it
is
impossibility
restricted
by
the
type
of
cause
and
foreseeability.[46]
The
use
of
the
terms
is,
however,
inconsistent
in
literature.
For
example,
Nystén-Haarala
refers
to
economic
force
majeure
as
a
synonym
for
commercial
impracticability
and
a
translation
of
the
Finnish
liikavaikeus and states that it does
not
require
impossibility
of
performance
[47]
(see
also
2.2.
above
and
2.5.
below).
Adlercreutz
uses
the
terms
economic
impossibility
and
economic
force
majeure
as
synonyms.
[48]
According
to
our
definition,
economic
force
majeure
would
be
defined
as
qualified
economic
impossibility:
economic
impossibility
that
has
been
caused
by
an
irresistible,
unforeseeable
and
external event.
The
Finnish
law
does
not
refer
to
force
majeure
as
such.
The
term
is
mentioned
neither
in
the
Sale
of
Goods
Act
nor
the
CISG.
The
rules,
however, have force majeure-type of elements. English law does not have a general doctrine of force
majeure
but
(as
well
as
in
Finland)
the
term
can
often
be
found
in
contracts
and
the
courts
must
therefore
be
prepared
to
attribute
some
meaning
to
it.[49]
2.4. Hardship
Hardship
can
be
understood
as
a
situation,
which
does
not
quite
amount
to
being
a
force
majeure.
It
means
that
the
performance
of
a
contract
has
become
more
onerous
for
the
performing
party.[50]
A
typical
example
of
hardship
would
be
a
steep
rise
in
the
prices
of
raw
materials
after
the
conclusion
of
the
contract.[51]
According
to
Perillo,
hardship
recognised
by
Italian
law
(onerosità)
has
to
be
the
result
of
events
that
do
not
constitute
a
normal
risk
of
contracts
of
the
type
in
question
and
that
are
extraordinary
and
unforeseeable.[52]
According
to
Hellner,
hardship
clauses
in
contracts
usually
refer
to
a
fundamental
change
in
the
obligations
of
the
parties.
Furthermore,
in
his
analysis
hardship
(clauses)
differ
from
force
majeure
(clauses)
in
relation
to
the
demand
for
unforeseeability:
in
hardship
cases, it
may
have
been
foreseeable
that
circumstances
shall
change,
as
long
as
the
cause
of
the
changes
and
the
seriousness
of
them
have
not
been.[53]
In
the
UNIDROIT
Principles
for
International
Commercial
Contracts
(see
4.1.
below)
hardship
has
been
defined
as
follows:
"Article 6.2.2 Definition of hardship
There
is
hardship
where
the
occurrence
of
events
fundamentally
alters
the
equilibrium
of
the
contract
whether
because
the
cost
of
a
party's
performance
has
increased
or
because
the
value
of
the
performance
a
party
receives
has
diminished,
and
(a)
the
events
occur
or
become
known
to
the
disadvantaged
party
after
the
conclusion
of
the
contract;
(b)
the
events
could
not
reasonably
have
been
taken
into
account
by
the
disadvantaged
party
at
the
time
of
the
conclusion
of
the
contract;
(c)
the
events
are
beyond
the
control
of
the
disadvantaged
party;
and
(d)
the
risk
of
the
events
was
not
assumed
by
the
disadvantaged
party."
According
to
this
definition,
hardship
can
also
occur
in
situations
where
the
value
of
what
the
performing
party
is
to
receive
in
return
for
his
performance
has
diminished,
whether
or
not
this
has
affected
his
ability
to
perform.
This
definition
of
hardship
would
seem
to
include
force
majeure
(qualified
impossibility)
and
some
cases
of
impossibility
outside
force
majeure
as
well
as
other
types
of
events
that
fundamentally
affect
the
balance
of
the
contract.
Impossibility
of
performance
is
not
necessarily
required
and
there
is
no
reference
to
not
being
able
to
avoid
or
overcome
the
situation.
Tillotsson
states
that
the
difference
between
hardship
(clauses)
and
force
majeure
(clauses)
is
in
their
different
purposes
(functions).
According
to
him,
the
purpose
of
hardship
stipulations
is
to
provide
for
renegotiations
or
adjusting
the
contract
in
order
to
allow
the
contractual
relationship
to
continue,
while
force
majeure
provisions
in
turn
are
usually
called
for
at
the
termination
of
the
relationship.[54]
Also
according
to
Schmitthoff,
the
distinguishing
factor
is
the
purpose:
the
parties
do
not
wish
to
dissolve
the
contract
but
to
continue
it.[55]
These views seem to be supported by rules in some legislatory instruments as well. According to Perillo, under Italian law a contract can
be
terminated
or
equitably
modified
(adapted,
adjusted)
because
of
hardship.[56]
Hardship
in
the
UNIDROIT
Principles
leads
to
a
duty
to
renegotiate,
adaptation
or
termination
of
the
contract
(see
also
4.1.
below).
2.5. Conclusions
In conclusion, we
may
make
a
proposal
for
definitions
which
would
seem
to
serve
most
purposes:
The
concept
of
impossibility
of
performance
refers
to
a
situation
where
performance
required
by
the
contract
cannot
be
accomplished
either
because
it
is
not
possible
in
the
logical
(physical)
or
practical
sense,
or
because
it
is
not
allowed
by
the
legal
order.
The
term
force
majeure
refers
to
those
cases
of
impossibility
where
the
cause
or
source
of
impossibility
is
irresistible,
unforeseeable
and
external.
Hardship
does
not
presuppose
impossibility:
it
may
or
may
not
be
caused
by
it.
The
term
refers
to
cases
where
the
balance
of
the
contractual
obligations
by
the
parties
has
been
significantly
disturbed
and
which
often
are
subject
to
the
same
type
of
qualifications
of
unforeseeability,
irresistibility
and
externality
as
the
cases
of
force
majeure.
The
qualifications
for
hardship
may,
however,
be
less
stringent.
Furthermore,
another
dividing
factor
of
the
above
mentioned
concepts
can
be
found
in
the
function
the
rules
concerning
them
serve
(according
to
law
or
under
contract) [57]
or
in
the
consequences
they
lead
to.
This
division
may
in
fact
have
more
distinctiveness
than
the
definitions
given
above.
The
functions
are
not
overlapping
but
the
events
qualified
under
each
concept
may
be
(see
Picture
1
below).
Moreover,
it
is
submitted
that
the
event-based
definitions
of
the
concepts
discussed
depend
on
the
functions.
For
example,
the
preconditions
of
force
majeure
are
chosen
in
accordance
with
the
idea
of
what
kind
of
circumstances
should
lead
to
an
exemption
from
damages.
The
definitions
are
therefore
essentially
dependent
on
notions
of
justice
and
values.
As
has
become
apparent
in
chapters
2.2.
and
2.3.
above,
economic
difficulties
have
sometimes
inconsistently
and
interchangeably
been
referred
to
as
economic
impossibility,
economic
force
majeure
or
hardship.
The
source
of
this
unclarity
perhaps
is
that
economic
difficulties
are
usually
less
willingly
acknowledged
by
the
law.
The
parties
are
often
held
to
be
strictly
liable
for
having
sufficient
economic
resources
to
perform
their
contract.[58]
Therefore,
from
the
legal
point
of
view,
economic
difficulties
may
often
lead
to
the
same
conclusions.
The
terms
can,
however,
be
distinguished
according
to
the
criteria
presented
above
impossibility,
qualified
impossibility
and
disturbed
balance
together
with
the
consequences
in
law.
As
a
rule
of
thumb,
it
can
be
said
that
impossibility
frees
the
performing
party
from
specific
performance.
In
force
majeure
circumstances,
the
party
may
be
released
from
paying
damages
for
non-performance
as
well.
Hardship, on the other hand, in many jurisdictions does not affect
the
parties'
rights
or
duties
in
one
way
or
another,[59] but
where
it
does,
or
where
the
parties
have
so
provided,
its
primary
purpose
usually
is
to
try
to
preserve
the
contract.
It
may
lead
to,
for
example,
renegotiations,
adjustment
of
the
contract
or,
where
nothing
else
is
of
avail,
to
termination
and
excuse
from
obligations.
It is proposed that the definitions of the discussed legally relevant concepts should consist of both a description of the relevant circumstances and their consequences in law. Table 1 below provides a rough illustration of the discussed concepts. The table is to be read from left to right. In column two the table presents typical preconditions for the changed circumstances to be regarded as the phenomenon named in column four. Column three contains typical consequences in law that the events may have. These can also represent the functions of the concepts in column four. The category "mere inconvenience" refers to events that do not lead to any consequences and which the party facing them therefore has to suffer.
Table 1. Impossibility, force majeure and hardship
It should be noticed that the categories presented in Table 1 are not mutually exclusive. For example, the group of events classified as force majeure belong also to the category of impossibility. Impossibility, however, is a wider concept. Hardship could, depending on the exact definition, typically contain all the cases of force majeure and some of the cases of impossibility not qualified as force majeure plus a number of events not qualifying under these two categories. However, as has been stated above, the functions of the discussed terms in their pure form are mutually exclusive. Picture 1 illustrates the relations of the events that may classify under the different categories.
Picture 1. Events leading to impossibility, force majeure and hardship in relation. [Picture omitted. To view this picture, go to the presentation of this commentary on the CISG-Finland website <http://www.utu.fi/oik/tdk/xcisg/southerington.pdf> at page 23.]
3. IMPOSSIBILITY IN FINNISH LAW (Sale of Goods Act, CISG, Contracts Act)
3.1. Applicable law
3.1.1. Choice of law
In this study, we are interested in contracts for the sale of goods that posses international characteristics, more precisely contracts the parties to which are from different countries. The choice of law is governed by the Act on the Applicable Law for International Sales of Movable Goods (laki kansainvälisluonteiseen irtainten esineiden kauppaan sovellettavasta laista, 387/1964) as well as by the choice of law rules in CISG Article 1.
It
is
provided
in
3.1
§
of
the
above-mentioned
act
on
the
choice
of
law,
that
the
parties
to
a
contract
may
agree
on
the
applicable
law.
According
to
4
§,
if
there
is
no
agreement
on
the
applicable
law,
the
main
rule
is
that
the
sale
be
governed
by
the
law
of
the
country
where
the
seller
had
his
place
of
residence
at
the
time
he
received
the
order
for
the
goods.
However,
if
the
order
was
received
by
the
seller's
subsidiary,
the
law
of
the
country
where
the
subsidiary
is
located
is
to
be
applied.
Furthermore,
the
law
of
the
country
where
the
buyer
had
his
place
of
residence,
or
where
his
subsidiary,
which
received
the
order,
is
located,
is
to
be
applied
in
cases
where
the
seller
or
a
representative
to
him
has
received
the
order
for
the
goods
in
this
country
(4.2
§).
The
rules
are
limited
by
an
ordre
public
clause
in
6
§.
If
there
is,
for
instance,
a
contract
between
a
Finnish
buyer
and
an
English
seller,
the
governing
law
is
the
law
applicable
in
England,
unless
otherwise
agreed
and
unless
the
seller
received
the
order
in
Finland.
Were
the
roles
the
opposite,
Finnish
law
would
govern.
Then
the
question
of
whether
to
apply
the
Sale
of
Goods
Act
or
the
CISG
were
to
be
answered.
3.1.2. Sale of Goods Act or CISG?
The Sale of Goods Act entered into force on 1 January 1988 and the CISG in 1 January 1989. Pursuant to KL 5 §, the CISG prevails over the Sale of Goods Act where the CISG is applicable. CISG Article 1 provides:
(1) This
Convention
applies
to
contracts
of
sale
of
goods
between
parties
whose
places
of
business
are
in
different
States:
According
to
Article
1(1)(a),
whenever
the
parties'
places
of
business
are
in
different
countries
which
are
parties
to
the
CISG,
the
Convention
is
the
applicable
law.
Furthermore,
under
Article
1(1)(b),
the
CISG
is
the
applicable
law
even
in
cases
where
both
of
the
parties
do
not
have
their
places
of
business
in
a
CISG
country
if
the
rules
of
private
international
law
lead
to
the
application
of
the
law
of
a
CISG
country.
If
the
parties
are
from
China
(CISG)
and
Germany
(CISG),
for
example,
the
Convention
is
the
applicable
law.
If
the
buyer
is
from
England
(non-CISG)
and
the
seller
from
Finland
(CISG),
again
the
Convention
is
to
be
applied.
If
the
buyer
is
from
Finland
and
the
seller
from
England
and
they
have
agreed
that
their
contract
be
governed
by
the
"Finnish
law,"
again
the
law
is
the
CISG,
not
the
Sale
of
Goods
Act,[60]
though
this
may
be
subject
to
interpretation
or
construction
of
the
contract
by
the
court.[61]
Reservations
to
the
CISG
may
modify
the
choice
of
law
rules.
For
example,
China
and
the
United
States
have
excluded
the
application
of
Article
1(1)(b).[62]
Finland
has
made
a
declaration
under
CISG
Article
92
regarding
Part II: Formation of Contract.
Therefore,
Part
II
shall
not
be
applied
where
the
CISG
is
the
governing
Finnish
law.
Instead
the
provisions
in
the
Contracts
Act
govern
the
formation
of
contract.
However,
in
cases
where
the
rules
of
private
international
law
lead
to
the
application
of
a
CISG
country
other
than
Finland,
Part
II
is
to
be
applied
unless
the
said
country
has
made
a
similar
declaration.
Furthermore,
for
example,
Finland,
Sweden,
Norway,
Denmark
and
Iceland
have,
in
accordance
with
CISG
Article
94, declared
that
the
Convention
is
not
applicable
when
the
parties
have
their
places
of
business
in
these
countries.
Therefore
in
a
sale
between
a
Finnish
seller
and
a
Swedish
buyer, the
Finnish
Sale
of
Goods
Act
would
be
applicable.
Both
the
sale
of
Goods
Act
and
the
CISG
are
mainly
non-mandatory.
The
parties
may
exclude
them
by
agreement
and
trade
usages
may
replace
them.
It
should
also
be
remembered
that
a
sales
contract
is
governed
by
general
contract
law
as
well
as
by
sales
law.
If
Finnish
law
is
applicable
then
the
contract
is
also
governed
by,
for
example,
the
Contracts
Act,
which,
among
other
norms,
contains
rules
on
validity
of
the
contract
a
question
outside
the
scope
of
application
of
both
the
Sale
of
Goods
Act,
and
the
CISG.[63]
3.2. The Sale of Goods Act
3.2.1. Primary obligations: exemptions from performance
3.2.1.1. Seller's delay
The seller's primary obligation is to deliver goods as required by the
contract.
Delivery
has
to
be
made
in
the
time
provided
in
the
contract
and
the
goods
have
to
be
in
conformity
with
the
contract
terms
and
the
terms
implied
by
the
Sale
of
Goods
Act
(17,
18
and
19
§,
if
not
excluded
by
the
contract).
The
buyer's
right
to
require
performance
and
the
seller's
effective
excuses
in
situations
of
delay
of
delivery
(mora)
according
to
KL
23
§ are:
Performance impossible (logical, practical or juristic impossibility)
Cause irrelevant
®
Exemption from performance=
Impossibility
Cause
1. Irresistible
2. Unforeseeable
3. External®
Exemption from damages as well=
Force majeure
Balance of the contract disturbed, not necessarily an impediment to performance
A qualified change in contractual balance
®
Attempts to rebalance the contract + other consequences=
Hardship
Qualifications in the contract / rule not met
®
No effect=
Mere inconvenience
(b)
when
the
rules
of
private
international
law
lead
to
the
application
of
the
law
of
a
Contracting
State.
(3)
Neither
the
nationality
of
the
parties
nor
the
civil
or
commercial
character
of
the
parties
or
of
the
contract
is
to
be
taken
into
consideration
in
determining
the
application
of
this
Convention."
| 23 § | "The
buyer
has
the
right
to
keep
to
the
contract
and
to
require
its
performance.
However,
the
seller
is
not
under
obligation
to
fulfil
the
contract
if
there
is
an
impediment
to
such
fulfilment
which
the
seller
cannot
overcome,
or
if
fulfilling
the
contract
would
require
sacrifices
that
are
unreasonable
in
comparison
to
the
benefit
to
the
buyer
from
the
fulfilment
of
the
contract
by
the
seller.
If the impediment or imbalance is removed within a reasonable time the buyer is, however, entitled to require the seller to fulfil the contract. The buyer loses the right to require performance if he does not use the right within a reasonable time." |
The seller is released from the obligation to deliver the goods on two alternative grounds: (1) there is an impediment he cannot overcome, or (2) performing would require unreasonable sacrifices in comparison to the benefit the buyer would receive. Even if the seller is exempt under KL 23 § he is still in breach of the contract. The buyer may then avoid the contract and claim damages (KL 25-29 §). The requirements for an exemption from paying damages (KL 27 §) are stricter than the ones in KL 23 § and the remedies under KL 23 § and 27 § are not linked to one another.[64]
The first prerequisite under KL 23 § is that after the conclusion of the contract, circumstances have so changed that performance is prevented. Anything that in practice prevents performance is covered by KL 23 §. For example, unique goods that were to be delivered have been destroyed or the specified lot from which the goods were to be taken has been destroyed. Also an import or an export ban has been given as examples by the Government Bill.[65]
The second prerequisite is that the impediment to performance has been such that the seller cannot overcome it. Objective impossibility is, however, not required. The seller may invoke impediments that affect his performance only.[66] Neither is logical impossibility required.[67] Nevertheless, the seller is under obligation to try to overcome the difficulties caused by the changed circumstances. He may, for example, have to fulfil his obligations in some other manner than what he had in mind at the time the contract was concluded. The main rule is that the seller is under obligation to perform even though it may be significantly more costly and troublesome than what he had expected.[68] Wholly disproportionate financial sacrifices are not required. In this sense, the impediment may also be economic.[69]
For example, failure of a particular source is usually not sufficient to excuse the seller from performing if the goods can be obtained from another source. The same applies to the method of performance: if, for instance, the means or route of carriage that had been presupposed cannot be used, the seller is normally obliged to find other ways to deliver the goods.[70] However, the question of what constitutes an impediment beyond the seller's control has to be analysed taking into consideration the contract as a whole and the circumstances of the case. The parties may have agreed upon some restrictions to the seller's performance. The contract may, for instance, provide that the timber to be delivered is to be from a specified area (cf. 5.3.1.4. and 5.3.1.5.).[71]
In addition to the above mentioned rules, the seller can be exempted where performing the contract required sacrifices unreasonable in comparison to the benefit the buyer would receive should the seller fulfil the contract. The sacrifices referred to in the section can be either physical or economic. The reasons why performance has become more onerous than expected are not important as such.[72] This rule has a close connection to the requirement that the seller try to overcome impediments to performance: the seller is released from this duty if it required unreasonable sacrifices.[73]
KL 23 § applies in cases where the balance of the contract has been disturbed by changed circumstances. According to some commentators, it is not enough that the contract has become unprofitable to the seller. KL 23 § requires that the economic basis of the contract has been so radically disturbed that the seller's sacrifices would clearly exceed what the parties could reasonably expect with respect to the type of contract in question.[74] It is submitted that the focus under KL 23 § should not be on the fairness of the contract but rather on the fairness of the remedies: whether or not the buyer's rights and expectations can be protected through the seller's liability in damages. Where the cost of performance would exceed the amount of damages needed to compensate the buyer's losses, the seller could be exempted.
The existence of imbalance is to be analysed case by case. One factor to be taken into consideration is the goods in question. In the case of goods notoriously prone to price changes, for example, or in cases where the circumstances imply that the seller has assumed the risk of circumstances changing, the discussed rule can only be applied in extreme instances.[75] An example of a case where KL 23 § might apply is a situation where the production of certain goods has ended, and the goods in stock have been destroyed without the seller being aware of this. If the seller would have to resume production, this might cause sacrifices unreasonable in comparison to the buyer's benefits from this.[76]
The sacrifices have to be unreasonable in comparison to the benefits to the buyer. As stated above, the disturbance in the balance of the obligations has to be of exceptional proportions. A comparison of the parties' obligations is always required when applying the rule. For example, a rise in prices does not normally affect the balance since the benefit of the performance to the buyer often grows proportionally to the sacrifices of the seller. On the other hand, if the buyer would easily be able to obtain the goods from another source, the benefit he would receive from this particular sale should be deemed small, and the seller would therefore be more easily exempted from performing.[77]
KL 23 § certainly covers cases of impossibility of performance. Impossibility frees the seller from performing. However, the rule applies to other, less serious occurrences as well. Impediments that could be overcome but not without unreasonable sacrifices also release the seller from performing. In this aspect, the rule resembles hardship-type of situations. The key element is the emerged contractual imbalance. However, it is not enough that the seller's obligations become more onerous, or that the value of the performance the seller is to receive diminishes. If the buyer's benefits from the sale grow proportionally to the difficulties of the seller, KL 23 § does not usually apply. If, for example, the value of what the seller is to receive in the sale diminishes, this may make performance more burdensome to the seller, but it will usually also make it more beneficial to the buyer since it is unlikely that he would be able to negotiate another sale at the same low price.
Contracts Act 36 § may also apply in the same type of situations as the discussed KL 23 §. According to the Government Bill, the Sale of Goods Act is the primary source of law in questions of what kind of effects changed circumstances have on the contractual relations of the parties, and that adjustment under 36 § therefore comes into question in exceptional cases only. However, KL 23 § applies in cases of supervening events only. If the imbalance existed already at the time of the conclusion of the contract, the case is to be decided under Contracts Act 36 §.[78]
3.2.1.2. Seller's failure to cure non-conformity
If the seller has delivered non-conforming goods, the buyer may, subject to the preconditions laid down in Chapter 6 of the Sale of Goods Act, require the seller to cure the non-conformity by repair or by a substitute delivery of conforming goods, or to lower the price or he may terminate the sale (contract) and claim damages in addition. Furthermore, he may retain from making the payment (KL 30 §). For the purposes of this study, cure and liability in damages need to be discussed in more detail (on damages see 3.2.2. below).
The buyer's right to require repair or new delivery is stipulated in KL 34 §:
| 34 § | "The
buyer
has
the
right
to
require
that
the
seller
repair
the
non-conformity
without
causing
any
costs
to
the
buyer,
if
the
non-conformity
can
be
cured
without unreasonable costs or unreasonable trouble to
the
seller.
Subject
to
36
§,
the
seller
may
instead
of
repairing
the
non-conformity
make
a
new
delivery.
The buyer has the right to require new delivery if the breach of contract has fundamental significance to the buyer and the seller understood or he ought to have understood this. However, the buyer does not have this right, if an impediment or imbalance such as described in 23 § exists. Furthermore, the buyer does not have the right to require new delivery, if the sale is of goods that existed at the time of the conclusion of the contract and which, taking into consideration the qualities of the goods in question and what has to be assumed that the parties have presupposed, cannot be substituted by other goods. If the seller does not fulfil his obligation to repair the non-conformity, the buyer has a right to compensation for reasonable costs required for repairing the non-conformity." |
The buyer's right to require repair is subject to the unreasonableness of the costs or the trouble caused to the seller. The seller's obligation to cure non-conformity by repair depends, for example, on his technical and human resources. If he lacks the technology, skill, personnel or organisation or if procuring spare-parts and other equipment needed would become very expensive, the seller may be excused under KL 34.1 §. Also the fact that the goods are in a geographically remote place may lead to an exemption. The significance of the repair by the seller to the buyer has to be taken into consideration as well. It may in some instances be easier for the buyer to repair the goods or to have them repaired by a third party and then claim damages from the seller. Furthermore, where the seller is required to cure the non-conformity, the buyer has to contribute in a reasonable manner in order to allow the seller to perform, for example, send the goods to the seller (at the seller's expense).[79] As the above mentioned examples show, the seller may be excused on subjective causes, limited to his performance only.[80]
Under KL 34.2 §, the buyer may require new delivery if the breach has fundamental significance to him. Fundamentality is to be analysed case by case from an objective viewpoint. Logically, the seller is exempted from making a new delivery if the circumstances are such as described in KL 23 §. These have already been discussed above. The Government Bill gives a few additional examples. If, for instance, the non-conformity is caused by faulty design, it may be that all the goods produced are subject to the same non-conformity and conforming goods do not exist and therefore cannot be delivered. Also non-conformity which has been caused by a misrepresentation by the seller or someone else earlier in the supply chain can mean that conforming goods do not exist. An unreasonable imbalance under KL 23 § may also occur in a situation where the goods sold are of a type that is no longer in production and cannot be found on the market at the time non-conformity is discovered.[81] This could typically happen in a case of hidden defect that is discovered only a long time after the sale.[82]
KL 34.2 § further stipulates that the seller be excused from delivering conforming goods if the contract concerned existing goods that are unique, irreplaceable judging by their qualities and what the parties have presupposed (when the parties have intended that the subject of the sale is the object in question). If the seller is excused, the buyer may still use his right to require repair under subsection 1. The seller's excuse from new delivery applies, for example, in second hand sales and sales of unique pieces of art. If the question is of a used car, the buyer cannot normally require new performance. On the other hand, if a new car of a specified type is sold, the seller can seldom be exempt under KL 34 §. The discussed exemption does not cover sales of future goods, for example, goods that are to be manufactured especially for the buyer after his order. However, the seller may still be exempt if the circumstances amount to such as provided in the KL 23 § (impediment or imbalance).[83] KL 34.3 § will be discussed in 3.2.2.1. below.
3.2.1.3. Buyer's obligations
KL 50 § provides that firstly, the buyer is to contribute to the sale in a manner which can reasonably be expected from him in order to enable the seller to fulfil the contract and secondly, the buyer is to collect the goods or to take delivery of them. Naturally, the buyer also has to pay the price as agreed in the contract. Breach of these obligations may give rise to the seller's remedies under the Sale of Goods Act. KL 51 § provides that if the buyer does not pay the price timely or does not contribute to the sale as required by KL 50.1 § and this has not been caused by the seller or a factor within his control, the seller may require payment or other performance of the contract or terminate the contract and in addition claim damages. A breach of the buyer's duty to collect the goods or to take delivery of them can seldom lead to a breach of contract (KL 51.2 §), and can never be the subject of an order for specific performance.[84]
The obligation to contribute to the sale refers to the time before delivery. What kind of contribution is required has usually been agreed in the contract. It may consist of, for instance, a duty to deliver blueprints or other instructions, materials or personnel or perhaps of a preliminary inspection of the goods to be delivered. Whatever the precise obligations are, the buyer's contribution has to be a prerequisite for the seller being able to fulfil the contract. Otherwise, no remedies are available for the seller in cases where the buyer fails to contribute.[85]
3.2.1.4. Buyer's failure to perform
According to KL 52 §, the seller has the right to keep to the contract and to require payment. However, in cases where the buyer cancels an order concerning goods that have to be produced or procured especially for the buyer, the seller may not keep to the contract by continuing production or other preparations for the delivery of the goods and by requiring payment, unless terminating the preparations would cause him essential harm or danger that the damage caused by the cancellation will not be compensated (KL 52.2 §). It has been argued that essential harm may also refer to substantial effects on the seller's ability to employ workforce.[86]
The only exception that may in some situations release the buyer from paying the agreed price concerns cases of cancellation of an order. In these situations, the seller's right to require payment may turn into a right to claim damages instead. Cancellation is considered to be an intentional breach of contract, and the seller is therefore entitled to damages for indirect losses as well (on damages see 3.2.2.2. below). KL 52.2 § applies only where the goods are to be produced or procured especially for the buyer. If the goods have already been produced or procured, the excuse is unavailable. It has been contended that KL 52.2 § is an expression of the principle according to which the parties are under obligation to mitigate damages. Furthermore, if the buyer cancels his order, the seller is to take also the buyer's interests into consideration (this could be seen as an expression of the principle of good faith or loyalty). Also from an economic perspective, it would be senseless to produce goods for which there is no demand.[87]
KL 53 § reads as follows:
| 53 § | "The
seller
may
also
keep
to
the
contract
and
require
that
the
buyer
contribute
to
the
sale
as
required
by
51
§
subsection
1.
However,
the
buyer
is
not
under
obligation
to
fulfil
the
contract
if
there
is
an
impediment to such fulfilment which the buyer cannot overcome,
or
if
fulfilling the contract would require sacrifices that are unreasonable in comparison to the benefit to the seller from the fulfilment of the contract by the buyer.
If the impediment or imbalance is removed within a reasonable time the seller is, however, entitled to require the buyer to contribute to the contract. The seller loses the right to require performance if he hesitates unreasonably long in making the requirement." |
This section governing the seller's rights to require the buyer to contribute to the sale mirrors KL 23 § on the buyer's rights to require the seller to perform and reference can be made to the discussion in 3.2.1.1. above. In judging the imbalance between the buyer's troubles and the seller's benefits, one has to take into consideration, for example, how important it is to the seller that the contract is kept and how good the seller's possibilities to get compensation in damages from the buyer are.[88]
3.2.2. Secondary obligations: exemptions from damages
The Sale of Goods Act provides for three types of liability in damages. The main rule is the one adopted in KL 27.1-2 §, 40.1 § and 57.2 §, sometimes referred to as control liability, where intent or negligence are irrelevant.[89] KL 27.4 § is an example of culpa or fault liability, which only follows intent or negligence (dolus, culpa). According to the Sale of Goods Act, liability in damages for indirect losses is always culpa liability (direct and indirect losses are distinguished in KL 67 §), unlike in the CISG. The buyer's liability in damages for the unpaid price in KL 57.1 § represents strict liability.[90]
The Act also provides for adjustment of damages in KL 70.2 §. According to this section, damages may be adjusted if they are unconscionable taking into consideration the liable person's possibilities to take into account and prevent the losses as well as other circumstances. It may therefore happen that even though the performing party cannot efficiently invoke an exemption, he may still be relieved from paying part of the damages under 70.2 §. (See also 3.4. below.) The CISG does not contain a provision similar to KL 70 §, but Article 74 contains the requisite that the losses be foreseeable which may in some cases have a similar effect. Surprising losses on the other party's side may be left outside of liability in damages.[91]
3.2.2.1. Seller in breach
Delay. The seller's excuses from paying damages for delayed performance are regulated in KL 27 §. Liability in damages is stricter than liability for performance under KL 23 §. This is based on the notion that although it may not be possible or conscionable to make the seller fulfil his obligations specifically, it may still be justified to allocate him the risk of economic losses caused by his delay to the buyer.[92] KL 27 § reads as follows:
| 27 § | "(1) The buyer is entitled to a compensation for the loss he suffers as a consequence of the seller's delayed performance, unless the seller proves that the delay was caused by an
impediment
beyond
his
control,
which
he
could
not
reasonably
be
expected
to
have
taken
into
account at the time of the conclusion of the contract and whose consequences he could not reasonably have avoided or overcome. (2) If the delay is caused by a person whom the seller has used to assist him in fulfilling his contractual obligations or a part of them, the seller is exempted from the duty to pay damages only if the said person would be exempted under subsection 1. The same applies where the delay is caused by the seller's supplier or other parties on earlier marketing levels. (3) A loss described in 67 § will not be compensated under subsections 1 and 2 of this paragraph. The buyer is always entitled to compensation if the delay or loss is caused by negligence on the seller's side." |
There are four prerequisites the seller has to prove in order to be released from liability in damages: (1) the delay has been caused by an impediment that prevents performance, (2) the impediment has to be beyond the seller's control, (3) the seller could not reasonably be expected to have taken the impediment into consideration at the time of the conclusion of the contract, and (4) the seller could not reasonably have avoided or overcome the impediment or its consequences.[93] All of these facts have to be proven true before the seller can be excused from paying damages.
(1) Impediment. It is not sufficient that the seller's performance becomes more expensive or more difficult. There has to be an impediment that prevents the seller from performing at the right time. According to the Government Bill, objective impossibility is not necessarily required, an impediment preventing just the seller from performing may be enough. The impediment has to be such that, even though the circumstances would not amount to (logical) impossibility, they would make the performance exceptionally burdensome, so that from an objective viewpoint it would clearly be unreasonable to require the seller to suffer the sacrifices necessary to perform the contract. It is enough that the impediment in practice prevents timely performance.[94]
The Government Bill gives a few examples of the kind of impediments that may prevent performance. For instance, a natural catastrophe may prevent deliveries or cause a shortage of electricity that prevents production. An accident, like a fire or an explosion as well as industrial action may stall the seller's activities. Also governmental activities, such as export or import bans, can prevent performance. Whatever the cause is, it has to prevent performance in order to come under KL 27 §. For example, an import embargo is irrelevant in cases where the goods can be obtained from domestic sources as well. KL 27 § does not exclude financial difficulties; these are, however, usually within the seller's control (see below).[95]
In judging whether there has been an impediment to performance or not, time is often a crucial factor. If, for instance, the sale concerns standard type of goods, and the goods are destroyed in an accident on the way to the place of delivery (at the seller's risk), there is an impediment to performance if there is not enough time left for a new delivery. The contract is another important factor. If the goods to be delivered have to be from a designated bulk, lot or crop, or a certain ship, for example, there is an impediment to performance if the source is destroyed, or does not come into existence at all (like a crop of wheat from a specified field). The more restricted and specified the seller's duties are, the more likely it is that an impediment prevents performance.[96]
Though impossibility is not necessarily required according to the Government Bill, the section should be interpreted strictly. This argument is further strengthened by the notion that release from paying damages should be more difficult than being excused from specific performance. Taking into consideration also the precondition number four, the impediment in KL 27 § would be comparable to the insurmountable impediment in KL 23 §, whereas KL 27 § contains no basis for excuse due to unreasonable sacrifices.[97] At least it is clear that objective impossibility qualifies under KL 27 § while a mere rise in prices does not.[98] It should also be noted that commentators to CISG Article 79 often interpret the word impediment in terms of impossibility (see 3.3.2. below).
(2) Beyond control. The impediment that prevents performance has to lie beyond the seller's control. What kind of events are within the seller's control is to be judged on the basis of objective criteria. All events preventing performance that are within the seller's control lead to liability in damages. The seller is naturally responsible for the actions of his employees, subcontractors and so forth. Nevertheless, industrial action is usually beyond the seller's control. However, if a strike, for example, has been caused by the seller's breach of labour laws or other such condemnable conduct, the situation may be judged to be within his control.[99]
The seller is responsible for actions he may influence by planning, organising or supervising. If the seller runs his business in an improper way, this may lead to liability in damages. A raw material shortage is not an excuse, if it could have been prevented by more careful planning. However, it is not required that the seller has acted in an improper manner. For example, sudden technical problems in production are considered to be within his control and therefore cannot be used as an excuse for delayed performance. Such occurrences are at the seller's risk. Another example of events that are usually within the seller's control are financial difficulties. If the seller cannot perform due to insufficient financial resources, he cannot avoid liability in damages. If, however, the difficulties are caused by a strike that suspends payment transactions and financing activities, this may perhaps be used as an excuse.[100]
(3) Unforeseeable. The impediment has to be such that it could not reasonably be expected that the seller would have taken it into consideration at the time the contract was concluded. Not all events that can be envisioned beforehand are relevant, however. Typical risks that may affect the seller's performance are considered foreseeable, but more unusual and remote events should be taken into account only if there is an acute risk of such an event occurring and preventing performance. For example, normal bad weather is usually to be taken into consideration, whereas exceptionally bad weather conditions might come under KL 27 §.[101] The requirement that the impediment be unforeseen has been recognised already before the Sale of Goods Act. In the case KKO 1944 II 131, the seller claimed that his performance had been prevented by an insurmountable impediment and that he should therefore be exempted from paying damages. The court held that the seller had to have taken the impediment into account at the time of the conclusion of the contract and that therefore he could not be exempted.
It has been argued that the requirement of unforeseeability also means that the impediment has to have occurred only after the conclusion of the contract.[102] This argument does not seem to be directly supported by the wording of the section and also differs from the acknowledged interpretation of the almost identical CISG Article 79(1), discussed in 3.3.2. below. If a pre-existing impediment is considered to prevent applying KL 27 §, the case could be settled under the Contracts Act as the Government Bill proposes in relation to KL 23 § (see 3.2.1.1. above).
(4) Unavoidable. The impediment or its consequences have to be such that the seller cannot have avoided or overcome them. The seller has to take reasonable action to avoid events that are beyond his control and that have been unforeseeable at the time of the conclusion of the contract or to overcome the consequences of such an event. The seller has to react to events that were not foreseeable at the time of the contract but become foreseeable before delivery.[103]
As it was not required that the impediment render performance absolutely impossible, it is not required that the impediment is impossible to avoid or overcome. Only reasonable action has to be taken. An example of avoiding or overcoming the impediment could be keeping sufficient storage of raw material in order to secure production. In some instances, the seller may be required to use alternative ways to perform than what he originally had planned, for example, to procure goods from another source or to use an alternative method of carriage.[104]
Third persons. KL 27.2 § strictens the preconditions of subsection 1 in situations where the delay has been caused by a person whom the seller has used to assist him in fulfilling the contract or by a supplier or another earlier link in the supply chain. In such circumstances, the seller is exempt only if the said person would be exempt under subsection 1 as well. Subsection 2 lays down a requirement for a "double force majeure," as described by Koskelo.[105] This means that the third person in question has to have been prevented from performing by an impediment meeting the criteria of subsection 1 and that this has formed an impediment to the seller, that would exempt him under subsection 1. The onus is on the seller to prove that the preconditions for an exemption have been met with.[106]
In many cases the possibility of an exemption is excluded already by subsection 1, under which the seller has the duty to ensure that the third party fulfilling the contract or a part of it has been elected and supervised in a proper manner. The third party is normally within his sphere of control. Furthermore, subsection 2 does not apply if the third person has not been used by the seller to assist him or, if the supplier does not supply goods or raw material but, for example, electricity. Then the case is to be analysed solely on the basis of subsection 1. Subsection 2 may be excluded, for instance, in situations where it can be inferred from the contract and other circumstances that the third party has not been chosen by the seller. This may typically happen when the buyer has demanded that a certain person or company be used and this party has in fact been assisting the buyer, not the seller. The fact that due to the structure of the market the seller has had no actual choice in electing the third party does not lead to the exclusion of subsection 2.[107]
It should be noted that the scope of application of KL 27.2 § is wider than that of CISG Article 79(2) (see 3.3.2. below). The rule is therefore stricter since the criteria of "double force majeure" are to be applied more widely. The CISG does not refer to suppliers or other parties on earlier marketing levels, although Article 79(2) does apply to such suppliers that are directly linked to the specific contract in question.[108]
Time factor. In addition to the above-presented prerequisites the time the impediment arose and its duration have also to be considered. If the impediment arises after the seller is already in breach of his contract, he will not be exempted from damages if the impediment would not have affected the fulfilment of the contract had the contract been performed at the right time. If the impediment described in KL 27 § is only temporary, the seller is exempted from liability for only such losses as the buyer has suffered during the time the circumstances described in KL 27 § lasts.[109] This follows from the requirement for causality between the impediment and the performance, though there is no express provision such as in CISG Article 79(3).[110]
It should also be noted that the seller cannot be exempted from compensating losses that have occurred because he has not informed the buyer of the impediment. According to KL 28 §, if the seller cannot perform in time, he is to give notice to the buyer of the impediment and its consequences on the possibility to fulfil the contract. Unless the buyer receives such notice within a reasonable time after the seller became or should have become aware of the impediment, the buyer is entitled to compensation for loss that could have been avoided had he received the notice in time.
Non-conformity. The seller's excuses from paying damages for losses caused by non-conformity of goods delivered are regulated in KL 40 §. This section refers to KL 27.1-2 §. A reference can therefore be made to the discussion above. It should be noted that the prerequisites laid down in KL 27 § are seldom met in cases of non-conforming goods. In most situations non-conformity is within the seller's control. Defects caused by production, storage, materials, construction or design are always within the seller's control. However, if the delivered goods have a hidden defect that can be found in all the same kind of products and the defect has been caused by a factor beyond the seller's control, the seller may be exempted. This is more likely to happen in cases of natural products: for example, a nightly interruption in the supply of electricity affects goods in a cooled storage. Likewise, if the question is of second hand goods or other existing specific goods, the seller may be excused more easily. A hidden defect in goods of a unique character may mean that conforming goods do not exist and the seller may be excused if he can show that the cause of the defect has been beyond his control.[111]
Apart from KL 40 §, also KL 34 § contains a provision on damages in cases of non-conformity. According to KL 34.3 §, if the seller is not excused from his obligations to repair the non-conformity and he does not fulfil this obligation at all or within a reasonable time (see KL 37.1), the buyer is entitled to compensation for the costs needed to repair the non-conformity to an amount that is reasonable (necessary and justifiable). This provision does not restrict the buyer's right to damages for non-conformity under 40 §. It is aimed at securing the buyer's rights to compensation in cases where he cannot recover damages under KL 40 § (see also 3.2.1.2. above). Therefore, if the buyer has the right to require repair in accordance with KL 34.1 § (does not cause unreasonable costs or unreasonable trouble to the seller) and the seller does not perform, he cannot be excused from paying damages for reasonable costs to repair the non-conformity.[112] It has been argued that the strictness of KL 34.3 § was adopted into the Sale of Goods following the model of CISG Article 46(1).[113] However, it should be noted that a possible exemption under CISG Article 79 applies to damages for all types of losses; there is no separate article for losses caused by a failure to repair non-conformity. Furthermore, the CISG contains the anomaly that the seller may be exempted from damages even though he would not be exempted from specific performance.
3.2.2.2. Buyer in breach
The seller's right to claim damages for losses suffered as a consequence of delayed payment or a breach of the buyer's other obligations is governed by KL 57 §, which reads as follows:
| 57 § | "The seller is entitled to a compensation for the loss he suffers as a consequence of the buyer's delayed payment, unless the buyer shows that the delay is caused by a provision of law, an interruption in public traffic or payment transactions or other similar impediment, which he could not reasonably be expected to have taken into account at the time of the conclusion of the sale and whose consequences he could not reasonably have avoided or overcome.
The seller has also on similar grounds as are laid down in 27 § a right to compensation for loss which he suffers because the buyer fails to contribute to the sale as required by 50 § subsection 1, or because the buyer fails to collect or take delivery of the goods in time where it can be inferred from the contract or the circumstances that the disposal of the goods is especially significant to the seller." |
The buyer's excuses for not performing in time are stricter than the seller's. The types of impediments that may qualify as an excuse have been restricted by the examples given in the section. Furthermore, the impediment that prevents timely payment has to be objective in the sense that it affects all payments, not just the buyer's. Also the scope of liability is broader. The buyer is strictly liable for both direct and indirect losses caused by the late payment. As has been discussed above, the seller's liability is restricted to damages for direct losses except for cases of intent or negligence (fault).[114]
KL 57 § does not contain an express requirement that the impediment to timely payment be beyond the buyer's control. The section, however, does contain this requirement as can be inferred from the examples. The examples also show that the buyer's financial difficulties do not excuse him from damages for late payment.[115] The section refers to force majeure type of events.[116] However, impossibility as such does not seem to be required. The scope of application of the section is largely subject to interpretations of what would be reasonable in relation to avoiding or overcoming the consequences in each case.
The buyer is also liable for the loss the seller suffers as a consequence of the buyer's failure to contribute to the sale as required or to collect or take delivery of the goods if it is especially important for the seller to dispose of the goods. This liability is similar to the seller's liability governed by KL 27 § and a reference can be made to the discussion above in 3.2.1.1. It should also be noted that KL 57 § does not govern the buyer's obligation to pay damages for the costs incurred in taking care of and storing the goods in the case the buyer has not collected or taken delivery of them. This obligation is governed by KL 75 §, according to which the buyer is liable for such costs. The causes of why he has not collected or taken delivery of the goods are of no relevance.[117]
3.3. CISG
3.3.1. Primary obligations: exemptions from performance
3.3.1.1. Seller in breach
The seller's obligations have been laid down in Article 30. According to this Article, the seller must deliver the goods, hand over any documents relating to them and transfer the property in the goods, as required by the contract and by the CISG. Pursuant to Article 35, the seller is to deliver goods which are in conformity with the contract. The principal rule concerning the buyer's right to require the seller to fulfil his obligations is to be found in Article 46, which reads:
"Article 46
(1) The buyer may require performance by the seller of his obligations unless the buyer has resorted to a remedy which is inconsistent with this requirement.
(2) If the goods do not conform with the contract, the buyer may require delivery of substitute goods only if the lack of conformity constitutes a fundamental breach of contract and a request for substitute goods is made either in conjunction with notice given under Article 39 or within a reasonable time thereafter.
(3) If the goods do not conform with the contract, the buyer may require the seller to remedy the lack of conformity by repair, unless this is unreasonable having regard to all the circumstances. A request for repair must be made either in conjunction with notice given under Article 39 or within a reasonable time thereafter."
Article 46 provides that the buyer has the right to require the seller to specifically perform the contract. Specific performance here refers to cure (new delivery or repair) as well. The Article also applies to partial non-performance. The buyer loses his right if he has resorted to a remedy that is inconsistent with the demand for specific performance. Such remedies include avoidance and reduction of price. Claiming damages for late performance does not prevent the buyer from requiring specific performance.[118]
It would seem that the seller would have no excuses for non-performance. However, Article 28 mitigates the strictness of Article 46:
"Article 28
If, in accordance with the provisions of this Convention, one party is entitled to require performance of any obligation by the other party, a court is not bound to enter a judgement for specific performance unless the court would do so under its own law in respect of similar contracts of sale not governed by this Convention."
The effect of Article 28 according to the Government Bill, is that the party requiring performance can only be entitled to it in the extent that the municipal laws [119] of the country where the court resides governing similar contracts of sale as the CISG will grant. This also means that, in cases where the municipal laws would grant specific performance, the court must grant it (if the party has the right to it under CISG, see 3.3.3. below). If a case is brought before a Finnish court, the right to performance can be settled in accordance with both CISG Article 46 and the relevant sections of the Sale of Goods Act.[120] However, Article 28 does leave the court wider discretion than it would have under its own law,[121] so at least in theory it would be possible to grant specific performance even in cases where the Sale of Goods Act would not allow it. It is submitted that in practice the courts will probably follow the rules they are more familiar with, and will not grant specific performance unless their domestic rules would lead to such a decision. The procedure, therefore, is first to analyse whether the party has the right to require performance under the CISG and then, if the answer were yes, to analyse whether the domestic rules would lead to a different result.
In cases of late performance, specific performance may be granted in accordance with Article 46(1) and KL 23 §. The seller does not have to perform if there is an impediment to such fulfilment which the seller cannot overcome, or if fulfilling the contract would require sacrifices that are unreasonable in comparison to the benefit to the buyer from the fulfilment of the contract by the seller (see 3.2.1.1. above).
If the seller has delivered non-conforming goods, the buyer may require delivery of substitute goods in accordance with Article 46(2) and KL 34.2 §. Firstly, the lack of conformity has to constitute a fundamental breach of contract. According to Article 25, a breach is fundamental if it results in such detriment to the other party as substantially to deprive him of what he is entitled to expect under the contract, unless the party in breach did not foresee and a reasonable person of the same kind in the same circumstances would not have foreseen such a result. Therefore the seller may be excused from a new delivery if the results of him delivering non-conforming goods have been unforeseeable as described in Article 25. Secondly, under KL 34.2 §, the seller is excused if the breach of contract did not have significant importance to the buyer or when it did but the seller did not understand this and he ought not to have understood this. Thirdly, under KL 34.2 §, the seller is excused in cases of an impediment or imbalance such as described in KL 23 § (see 3.2.1.1. above). Finally, the seller does not have to perform if the contract was of existing goods with unique characters as described in KL 34.2 §.
The question of repair is subject to Article 46(3) and KL 34 § subsection 1. According to Article 46(3), the buyer may require the seller to remedy the lack of conformity by repair, unless this is unreasonable having regard to all the circumstances. Under KL 34.1 § the seller is excused if the non-conformity cannot be cured without unreasonable costs or unreasonable trouble to the seller.
3.3.1.2. Buyer in breach
According to CISG Article 53, the buyer must pay the price for the goods and take delivery of them as required by the contract and the CISG. Article 60 provides that the buyer's obligation to take delivery consists of doing all the acts which could reasonably be expected of him in order to enable the seller to make delivery and of taking over the goods. According to Article 62, the seller may require the buyer to pay the price, take delivery or perform his other obligations, unless the seller has resorted to a remedy which is inconsistent with this requirement (such a remedy can mainly be avoidance).[122]
These obligations are also subject to Article 28: a court is not bound to enter a judgement for specific performance unless the court would do so under its own law in respect of similar contracts of sale not governed by the CISG (see above 3.3.1.1. and 3.3.3. below). Both the CISG and the Sale of Goods Act are therefore relevant if the case is decided in Finland.
Article 62 does not provide for any excuses for the buyer to be exempted from his obligations. This is also the case in KL 52 § concerning the seller's right to require payment (except for cases of cancellation, see 3.2.1.4.). KL 51.2 § provides for the situation where the buyer does not fulfil his obligation to collect or take delivery of the goods. According to it, the seller may declare avoidance or claim damages. Therefore, specific performance regarding the obligation to collect or take delivery of the goods cannot be granted. The buyer's duty under Article 60(a) is at least in part overlapping with the buyer's obligation to contribute to the sale under KL 50.1 §. Therefore, KL 53.1 § also has to be taken into account. As has been noted above in 3.2.1.2., under KL 53.1 § the buyer is excused from contributing if there is an impediment to such fulfilment which the buyer cannot overcome, or if fulfilling the contract would require sacrifices that are unreasonable in comparison to the benefit to the seller from the fulfilment of the contract by the buyer.
3.3.2. Secondary obligations: exemptions from damages
Article 79 governs both the seller's and the buyer's chances of being exempted from paying damages for breach of any of their obligations. The Article closely resembles KL 27 §, which is no accident since paragraphs (1) and (2) of Article 79 have served as a model for KL 27 §.[123] According to Articles 45 and 61, liability in damages does not depend on questions concerning fault (intent or negligence). This applies also to indirect losses since the CISG does not distinguish them from direct losses (see Article 74). Anglo-American influence can be detected behind these provisions.[124] Under the CISG, liability in damages is always control liability. Article 79 provides:
"Article 79
(1) A party is not liable for a failure to perform any of his obligations if he proves that the failure was due to an impediment beyond his control and that he could not reasonably be expected to have taken the impediment into account at the time of the conclusion of the contract or to have avoided or overcome it or its consequences.
(2) If the party's failure is due to the failure by a third person whom he has engaged to perform the whole or a part of the contract, that party is exempt from liability only if: (a) he is exempt under the preceding paragraph; and (b) the person whom he has so engaged would be so exempt if the provisions of that paragraph were applied to him.
(3) The exemption provided by this Article has effect for the period during which the impediment exists.
(4) The party who fails to perform must give notice to the other party of the impediment and its effect on his ability to perform. If the notice is not received by the other party within a reasonable time after the party who fails to perform knew or ought to have known of the impediment, he is liable for damages resulting from such non-receipt.
(5) Nothing in this Article prevents either party from exercising any right other than to claim damages under this Convention."
The four prerequisites the seller has to prove in order to be released from liability in damages are the same as discussed above in 3.2.2.1: (1) the delay has been caused by an impediment that prevents performance, (2) the impediment has to be beyond the seller's control, (3) the seller could not reasonably be expected to have taken the impediment into consideration at the time of the conclusion of the contract, and (4) the seller could not reasonably have avoided or overcome the impediment or its consequences.[125] All of these conditions have to be proven true before the seller can be excused from paying damages. The examples of the situations where exemption can be granted given in the Government Bill are similar to those given in the bill concerning the Sale of Goods Act.[126] The Article should, however, not be applied on the basis of domestic laws, but one should keep in mind Article 7, which provides, among other things, that the Convention's international character is to be appreciated as well as the need to promote uniformity in its application.[127]
(1) Impediment. There has to be an impediment to due performance. According to Honnold, the word impediment "implies a barrier to performance, such as delivery of the goods or transmission of the price rather than an aspect personal to the seller's performance." Furthermore, performance has to be prevented by the impediment.[128] According to Stoll, who sees Honnold's definition of impediment as too narrow, the term refers to events external to the party in breach which may be "natural, social, or political events or physical or legal difficulties." Purely personal circumstances, such as personal inadequacy or a mistake of law could not amount to an impediment within the meaning of Article 79.[129]
Article 79 does not use the term impossibility. The requirement that performance be prevented does, however, seem to refer to impossibility instead of impracticability or other less forceful event. Tallon, for example, states that the Article deals with "one of the most delicate questions in contract law [:] the effects of the impossibility to perform one of the obligations of the contract."[130] In the case Nuova Fucinati S.p.A. v. Fondametall International A.B.[131] the tribunal of Monza found that Article 79 would not excuse a party unless performance had become impossible.[132] It is noticeable that the authorities seem to be of the mind that the impediment or impossibility should be objective. As has been discussed in 3.2.2.1. above this was not required under KL 27 §.
The impediment may have existed already at the time of the conclusion of the contract (as in cases of initial impossibility),[133] unlike under KL 27 § according to some commentators (see 3.2.2.1. above). It may also be economic, as long as it fulfils the requirements provided by Article 79.[134] For example, increased procurement and production costs as a rule do not constitute an exempting impediment since the performing party is usually understood to have guaranteed his financial capability to fulfil the contract.[135] On the other hand, at least according to Huber, a party might be exempted when war, blockade or other such event does not make performance impossible, but makes it possible only with unforeseeable expenses clearly out of proportion to the price agreed.[136]
(2) Beyond control. The impediment must be beyond the promisor's control. According to Stoll, this requirement is based on the assumption that there is a typical sphere of control: a sphere within which it is objectively possible for, and can be expected of, the promisor to be in control. For example, manufacturing defects fall within the manufacturer's sphere of control even if reasonable measures had been taken to prevent them, whereas disadvantageous qualities of goods (cf. tobacco) discovered at some later date do not, provided that they were manufactured in accordance with the relevant technical rules and existing scientific knowledge.[137] According to Schlechtriem, the obligor is always responsible for impediments that he could have prevented but, despite his control over preparation, organisation, and execution, failed to do so. Negligence, however, is not required.[138] For example, in a case decided by the High Arbitration Court of Russia, the buyer had paid the price, but the money was stolen from the foreign bank before the seller had obtained it. The Court held that the failure of the buyer was not due to an impediment beyond his control.[139]
(3) Unforeseeable. The impediment has to be reasonably unforeseeable. If there is a realistic risk of an impediment to performance and the contract is nevertheless unconditionally entered into, the risk of the impediment has been assumed and exemption cannot be successfully claimed.[140] Where neither the explicit or implicit terms of the contract show that the impediment was in fact foreseen, it has to be determined whether the nonperforming party could reasonably have been expected to take it into account at the time of the conclusion of the contract. This can only be made on a case by case basis.[141] In a Russian arbitral award of 17 October 1995, the buyer requested discharge from liability on the basis that he did not have the foreign currency necessary for the payment. The tribunal firstly held that the lack of foreign currency did not qualify under the force majeure clause in the contract and went on to state that the buyer had not taken any measures to ensure that the payment could actually be made.[142]
(4) Unavoidable. The impediment and its consequences must have been unavoidable. An impediment may be avoided or overcome, for example, by choosing another form of transport or another route (like shipping the goods via the Cape of Good Hope instead of the Suez Canal) or even by delivering a commercially reasonable substitute for the performance which was required by the contract. However, the promisor should not be expected to risk his own existence by performing his obligations at all costs,[143] even though the Secretariat Commentary does state that the obligor must do all in his power to carry out his obligation.[144]
Third persons. Article 79(2) represents the same kind of "double force majeure" regulation as does KL 27 § (see 3.2.2.1. above). According to Article 79(2), if the promisor's failure to perform is due to a third person whom he has engaged to perform the contract or a part of it, the promisor can only be exempt from liability in damages if he is exempt under Article 79(1) and the third person would be exempt as well if 79(1) would be applied to him. 79(2) requires that there be a sub-contract with an organic link to the main contract. Furthermore, the subcontractor must be legally independent of the party to the main contract. Also, the sub-contractor must at least have been accepted by the promisor, and act under his control.[145]
Article 79(2) applies to such third persons only that directly fulfil the contract or a part of it. If the question is. for example, of an energy supplier whose performance may be a precondition for the performance of the main contract, but not part of it, the liability is settled under 79(1) only.[146] According to Schlechtriem, the seller is not liable for secondary suppliers when they are beyond his control and their failure could neither be taken into account nor cured (the normal requirements under 79(1)). This would apply in cases where the seller could not choose nor control his suppliers and it was not possible to procure, produce or repair the goods in any other manner.[147]
Onus. It should be noted that the burden of proof concerning the preconditions laid down in 79(1) as well as those in 79(2) is on the party seeking exemption. The Russian arbitral award of 16 March 1995 illustrates the difficulties facing the party in breach: Chemical products were to be delivered by a Russian supplier to a German buyer within the fourth quarter of 1992. The seller did not perform and the buyer sued and claimed damages. The seller maintained that he should be exempted since he had been unable to deliver the goods for reasons beyond his control. According to him, the delivery had been prevented by an emergency production stoppage at the plant manufacturing the goods specified in the contract. The Tribunal of International Commercial Arbitration at the Russian Federation Chamber of Commerce and Industry held that the seller had been unable to prove the facts that would have discharged him from liability. The manufacturer's refusal to supply the seller with the goods could not be deemed sufficient grounds for such discharge. In addition, the court stated that the seller had been unable to establish that it could not reasonably be expected to have taken the obstacle preventing performance into account or to have avoided the obstacle or its consequences.[148] The tribunal seems to have concluded that the seller could prove none of the preconditions under Article 79.
Time factor. According to Article 79(3) the exemption under 79(1) and 79(2) starts when the impediment occurs and lasts as long as the impediment exists. Article 79(3) does not provide whether or not the performing party is under obligation to perform after the impediment has ceased to exist.[149] This should be clear since 79(5) explicitly limits the application of Article 79 to damages and the promisee's duty to perform remains unchanged in the event of exempting impediments.[150] Under 79(4), a party is liable for damages caused by his failure to notify the other party of the impediment and its effects even if he would otherwise be exempt.[151]
Partial non-performance. Article 79 does not provide for the situation where only part of the performance is prevented. It refers to a failure of any obligation, but does not lay down the consequences of the non-performance of the contract as a whole.[152] Honnold notes that the language of the provision permits exemption to the extent that the impediment applies. This can be supported by Article 51(1) allowing remedies to apply in respect of partial breach. The promisee's rights to other remedies would not be impaired.[153]
3.3.3. Problem of specific performance
The question of impossibility of performance raises three specific problems relating to specific performance that should be discussed. These are, firstly, what is the effect of Article 79 on specific performance, secondly, can the court grant specific performance where it would not do so under its own law, and thirdly, on what grounds can the court deny specific performance in situations where domestic law would grant it.
Article 79 and specific performance. As stated in 79(5), the Article does not prevent the parties from requiring other remedies provided by the Convention. According to the Secretariat Commentary, the obligee may demand performance, reduction of price or avoidance of the contract. In cases where the obligor has attempted to overcome an impediment by furnishing a substitute performance, the obligee may avoid the contract and reject the performance only if the performance was so deficient in comparison to the agreed performance that it constitutes a fundamental breach of contract. Even in cases of impossibility of performance, the receiving party would have the right to require that performance under Articles 46 or 62. The CISG seems to leave this question to be solved by the domestic laws of the court deciding the case (see Article 28).[154] According to Schlechtriem, "it may be hoped that the general belief expressed in Vienna that a judgment for a physically impossible performance would be neither sought nor obtained should lead to a reasonable limitation o[f] Article 79(5)."[155]
Among others, Tallon has expressed discontent with Article 79(5). According to him, the Article leads to unrealistic results, especially in cases of impossibility of performance.[156] Huber seems to have adopted a rather unconventional view. He refers to the spirit of Article 46(1) and states that it would be inconsistent to allow a buyer to require performance in cases where performance is prevented by an impediment that the seller is not required to overcome under Article 79. Huber would apply the criteria laid down in Article 79 to release the party from performing.[157] Stoll, in turn, states that upholding the right to require performance is sensible as a basic rule and acknowledges the fact that the right to require performance is not settled by Article 79. He adds, however, that in a case of impossibility of performance the right to claim performance would be absurd.[158] Honnold notes that the legislators did not intend to allow this kind of absurdity, but most likely dismissed further discussion about the breadth of 79(5) in order to avoid the complications of producing a revised text.[159] It would seem to be clear that Article 79 only concerns exemptions from damages. It has no direct significance in relation to the right to require performance.
Court's power to order specific performance. Under Articles 46(1) and 62 the main rule is that the receiving party has the right to require performance. This right is subject to the limitations in Article 46(2) and 46(3) as well as those of domestic laws in accordance with Article 28. Where the domestic law of the court would not allow or require specific performance the court does not have to allow it either, though it may.[160] E contrario, it would seem that, where the domestic law required specific performance, the court must order it in cases where the party has a right to it under the Convention. The wording "unless the court would do so" would seem to infer this too.[161]
Article 28 was taken into the Convention, on the one hand, because the courts in some countries do not have the authority or the procedural mechanisms to order specific performance, and on the other, to satisfy the common law countries, where the criteria for granting specific performance is very strict. The purpose therefore was to allow, not to compel, the court to follow its own law where specific performance would not be granted by it. The argument that the court is not bound to reject a request to specific performance in cases where it would do so under its own law [162] seems therefore reasonable.
Court's power to deny specific performance. The court has to order specific performance only if, firstly, the CISG and secondly, the domestic law requires it. As noted in 3.3.1.1., the procedure therefore should be first to examine whether the party has the right to require specific performance under the CISG. If the answer to this question were positive, but the court would not be happy with this decision, then the court would have the possibility to examine whether it could reject the requirement under the safety valve of its own law.[163] The important question in cases where the domestic law does not provide for limitations for ordering specific performance or where the court does not even look into its domestic rules is, does the CISG provide for any limitations on or exemptions from specific performance,[164 for example, in cases of impossibility of performance?
Mitigation of damages. Articles 46(2) and (3) have already been mentioned as directly limiting the right to cure in the form of new delivery or repair. A more difficult question is delay of performance. It has been suggested that Article 77 on the duty to mitigate damages would limit the rights to performance under Articles 46 and 62.[165] Opinions on this question vary, however. Kastely, for instance, notes that the language of Article 77, the construction of the Convention and its legislative history prove otherwise.[166] Demands by third parties have also been stated to form a limitation to specific performance.[167] If, however, not even (logical) impossibility is recognised as a limitation, why then would any third party claims be? Anyhow, this is a question of domestic laws and not a question of whether any exemptions could be granted under the Convention.
Interpretation of the Convention. According to Article 7(1), when interpreting the Convention regard should be had to its international character, the need to promote uniformity in its application and the observance of good faith in international trade. It has been argued that the observance of good faith would restrict the parties' rights to require specific performance at least in cases where a party seeks this remedy after a delay that permits him to speculate at the expense of the other party (e.g. after a rise in market prices).[168] Kastely notes that a good faith limitation to Articles 46 and 62 may be especially important in cases of impossibility or impracticability of performance. According to her, it is appropriate to interpret Articles 46 and 62 consistently with a general obligation of good faith. In her opinion, where a party would inflict "undue pain or punishment" to the other party, the court can prevent this under Article 7.[169]
However, Article 7(1) is directed towards the courts interpreting the Convention. Therefore, it does not directly oblige the parties to the contract, although it has been argued that it lays down a principle of good faith that the parties should obey.[170] The wording of Articles 46 and 62 is very precise and leaves little room for interpretation. It is submitted that these Articles cannot be interpreted in such a manner that would allow the court to refrain from ordering specific performance merely on the basis that requiring performance would be a violation of good faith. This would be equivalent to introducing a new rule allowing for exemption, which Article 7(1) would not seem to allow. This brings us to the question of Article 7(2).
Supplementing the Convention. Article 7(2) provides that questions concerning matters governed by the CISG which are not expressly settled by it are to be settled in conformity with the principles on which it is based or, in the absence of such principles, in conformity with the law applicable by virtue of the rules of private international law. This provides for means of gap filling in cases of lacuna. It could be argued that the question of, for example, the influence of impossibility of performance is a question not expressly settled by the Convention. On the other hand, both the right to require performance and exemptions have been dealt with in the CISG and it could be thought that the non-existence of the question means that impossibility should not be taken into consideration.[171] However, the Convention is a result of numerous compromises between different legal systems. The question of specific performance resulted to the less-than-perfect results apparent in Articles 79(5) and 28 (see above). It may be that the issue was left open, not intentionally, but perhaps due to practical difficulties in the legislatory process.[172] This would leave open the possibility to supplement the rules of the Convention in accordance with Article 7(2).
The first source of gap-filling rules would be the principles on which the Convention is based. It might be difficult to establish that the Convention is based on "impossibilium nulla est obligatio" or other such principle.[173] However, at least the principle of good faith has been argued to be a principle on which the Convention is based on (as perhaps also Article 7(1) implies), and could be used to limit ordering specific performance in some cases pursuant to Article 7(2). Furthermore, Article 7 promotes an international approach, domestic laws should only be applied as a last resort [174] Municipal laws should be avoided to promote uniformity in application.[175] The fact that many jurisdictions as well as usages in international trade and international legal instruments, such as the UNIDROIT Principles [176] or the Principles of European Contract Law, contain rules that excuse the party from performance in cases of impossibility, force majeure or the like makes it reasonable to assume that the Convention would be based on such ideas as well.
Trade usage. Article 9(1) provides that the parties are bound by any usage to which they have agreed to or which they have established by themselves. Though it has been stated that a usage adopted by the parties could lead to an exemption from specific performance,[177] it may be that such usages seldom occur. According to Article 9(2), unless otherwise agreed, the parties are bound by a trade usage of which they knew or ought to have known and which in international trade is widely known to, and regularly observed by, parties to contracts of the type involved in the particular trade concerned. It is submitted that judging by, for example, contract practices, taking into consideration especially standard terms prepared through collaboration of representatives of both sellers and buyers, it could in some cases be established that an international trade usage providing for release from the duty to perform exists.
On the basis of the arguments presented above, it is submitted that a party should be able to successfully reject a demand for specific performance in accordance with the CISG at least in cases of impossibility of performance even in countries that do not give effect to such events. The risk of the court interpreting the Convention in another manner, however, remains.
3.4. Contracts Act
It has been stated that the majority of the countries in the European Community have introduced into their law some mechanism to correct injustices resulting from an imbalance in the contract caused by supervening events, that is, situations of the type of hardship.[178] The Sale of Goods Act or the CISG do not contain such provisions. However, though the described sales laws applicable in Finland are silent on the matter, a rule that encompasses also situations of changed circumstances of the said type can be found in the Contracts Act 36 §, sometimes called the big general clause.[179] Contracts Act 36 § came into force 1 January 1983 and it is applicable retrospectively.
However, according to the Government Bill on the Sale of Goods Act, it is this act that sets the primary criteria for the analysis of what kind of effects changed circumstances may have on the contractual relationship, and that adjustment of the contract under Contracts Act 36 § should only come into question if there are special reasons for it.[180] Though this was stated in relation to the Sale of Goods Act, it should apply in relation to the CISG as well. Because of this and in attempt to restrict the scope of this study, 36 § shall be introduced only briefly.
According to 36 § subsections (1), (2) and (3):
| 36 § | "(1) If a term of a contract [181] is unconscionable or its application would lead to unconscionability, the term may be adjusted or it may be set aside. In determining unconscionability one must take into consideration the contents of the contract as a whole, the position of the parties, circumstances prevailing at the time of the conclusion of the contract and after it, as well as other relevant facts. (2) If the term described in subsection (1) is such that because of the adjustment of the said term it would be unconscionable if the rest of the contract stayed in force unchanged, other parts of the contract may be adjusted as well or the contract may be declared discharged. (3) A commitment concerning the price is also considered to be a term of the contract." |
Under Contracts Act 36 §, a contract term or even the whole contract may be adjusted if it is considered to be unconscionable, either originally or due to supervening circumstances.[182] Adjustment is only possible where a valid contract has been concluded. Even though it may lead to the whole contract being declared discharged (frustrated), the contract has been in force and binding for some time before the adjustment. 36 § cannot lead to nullity ab initio.[183] In this sense, the effect is similar to that of the doctrine of frustration (see 5. below).
For example, in the case KKO 1990:138, the question was of a contract for the supply of electricity. The contract was concluded in 1963 for 99 years providing that the company would continue to produce electricity. The contract stipulated that for electricity in excess of 5000 kWh/year (up to which amount the buyer would receive free in exchange for real property sold) the buyer was to pay according to the tariffs for occasional users, a tariff higher than that for regular users. In short, a considerable time after the conclusion of the contract increased consumption led to a situation where electricity became more expensive to the buyer than it would have been if the tariff for regular users had been applied to the whole amount consumed. The Supreme Court adjusted the price term by replacing the tariff on electricity in excess of 5000 kWh per year with the tariff for regular users. Lower instances would not have adjusted the contract. The case is actually less dramatic than it seems since the reduction made by the court was equal to what the supplier had already offered to the buyer. However, the buyer had rejected the offer and thus this was not a case of the court confirming a settlement by the parties.[184]
Another example of a hardship type of situation is the case KKO 1991:182, which concerned a contract for supplying energy. The contract was concluded for five years at a time, and could be terminated by a year's notice before the said five years. During the contract period, the law on value added tax changed and made the contract more onerous for the supplier who then informed the buyer of a 9.6% rise in prices. The buyer sued the supplier requiring it to keep to the original contract. The Court of Appeal (HHO 13.1.1990) stated that, on the one hand, the costs of the supplier had increased and this had occurred unexpectedly and concerned only a specific branch of industry. On the other hand, the contract was for a fixed time and it had not been shown that the change in the tax laws had led to higher total costs and thus disturbed the balance of the obligations of the parties to such a significant extent that applying the agreed term on the price would have led to apparent unconsionability. Contracts Act 36 § was therefore not applied. The rise in prices was declared ineffective and the supplier was ordered to return the amounts received in excess of the contract price. The Supreme Court upheld the decision.
It should be noted that the court may also adjust the damages, not only the primary obligations under the contract. As has been noted above in 3.2.2., the Sale of Goods Act 70.2 § provides for this explicitly in cases of sales contracts. In the case KKO 1982 II 141, which was decided before the (new) Contracts Act 36 § or the Sale of Goods Act had entered into force, the seller was to supply milk powder for the price of 3.50 marks per kilogram. Unexpectedly, due to governmental activities, the production costs of milk powder rose from 1.81 to 4.17 marks. The seller refused to deliver part of the agreed quantity. The Court held that applying the price term in the contract would have led to apparent unconscionability, and the buyer's claim for damages for losses caused by a substitute purchase was therefore adjusted by decreasing the sum by one third.
3.5. Conclusions
Both of the discussed sales laws applicable in Finland contain provisions on exemptions from contractual obligations in situations where the circumstances have so changed as to make performance more difficult. Specific performance rules under the CISG refer to the domestic laws of the deciding court as a limiting factor. Therefore the decisions may differ considerably from country to country. The risks attached to this feature of the CISG can be controlled by choice of law clauses as well as clauses providing for the effects of changed circumstances in the contract.
The CISG does not distinguish between monetary and non-monetary obligations in relation to exemptions from damages. When the question is of non-monetary obligations, the CISG may be stricter than the Sale of Goods Act. According to many commentators, impossibility of performance is required, whereas under the Sale of Goods Act this would not appear to be the case. This is, however, a question to be settled in the courts, and the differences may be only superficial. The "double force majeure" rule is stricter in the Sale of Goods Act. Also in relation to monetary obligations, the Sale of Goods Act would seem to be stricter. To make comparing the individual rules easier, the main exempting rules in the Sale of Goods Act and the CISG are presented in Appendix 1. Where the appendix refers to the court's own law, the exempting event in the column for the Sale of Goods Act applies as well.
Neither the Sale of Goods Act nor the CISG contain express rules on hardship. The kind of events usually associated with the term hardship, for example, an increase in prices, would not normally exempt the obligor under these rules. However, in exceptional cases the obligor might be entitled to adjustment of an unconscionable contract term or the whole contract under Contracts Act 36 § and thereby to an exemption from liability. Applying this section may also lead to discharge (frustration) of the contract. Also KL 23 § may apply in some hardship type of circumstances ("sacrifices that are unreasonable in comparison to the benefit to the buyer from the fulfilment of the contract by the seller"). However, the aim of this section is in releasing the obligor from performance, not in preserving the contract. Rather than referring to hardship, KL 23 § seems to refer to unconscionability as does Contracts Act 36 §. On the basis of the discussion in this chapter, it is submitted that the law applicable in Finland provides for exemptions from obligations in three types of changed circumstances: impossibility, force majeure, and unconscionability.
Table 2 presents a rough illustration of the rules leading to a possible exemption from liability under the law applicable in Finland. If we compare these rules
with the definitions proposed in chapter 2, it can be said that the concepts of impossibility, force majeure or hardship do not appear as such in them. As stated
above, hardship as defined in chapter 2 does not appear to be a relevant factor in the Finnish law though some of the hardship-type of circumstances may be. There
are no stipulations whose aim could be said to be saving the contractual relationship. Impossibility and force majeure in turn do have significance but it is
submitted that the law provides for more room for consideration of fairness or unconscionability. From the viewpoint of the definitions proposed in chapter 2,
these have been modified to allow exemption more often than in the pure cases of impossibility or force majeure as described.
Table 2. Exemptions under the law applicable in Finland
4. IMPOSSIBILITY IN INTERNATIONAL INSTRUMENTS
4.1. UNIDROIT Principles of International Commercial Contracts
The UNIDROIT Principles were published in 1994. The Principles were drafted taking into consideration a number of different national legal systems as well as the CISG and other international instruments prepared by UNCITRAL.[185] According to the preamble to the UNIDROIT Principles, the Principles shall be applied when the parties have agreed that their contract be governed by them and they may also be applied when the parties have agreed that their contract be governed by "general principles of law," the "lex mercatoria" or the like. Furthermore, they may (among others) provide a solution to an issue raised when it proves impossible to establish the relevant rule of the applicable law. In addition, they may be used to interpret or supplement international uniform law and they may serve as a model for national and international legislators. It has been discussed in the literature whether UNIDROIT Principles could be used to supplement the CISG, for example, whether the hardship provisions could be applied when the CISG is the governing law. The answer in most cases would appear to be negative.[186]
Article 6.2.1 establishes the principle of pacta sunt servanda as the main rule to be followed. This Article provides that if the performance of a contract becomes more onerous for one of the parties, he is nevertheless bound to perform his obligations
subject
to
the
following
provisions
on
hardship.
Article
6.2.2
then
defines
hardship
and
6.2.3
provides
for
the
effects
of
it
as
has
been
discussed
above
in
2.4.
Where
the
equilibrium
of
the
contract
has
been
fundamentally
[187]
altered,
the
disadvantaged
party
is
entitled
to
request
renegotiations.[188]
Where
such
negotiations
fail
to
lead
to
an
agreement
within
a
reasonable
time
either
party
may
resort
to
the
court,
which
may,
if
reasonable,
terminate
the
contract
or
adapt
it
with
a
view
to
restoring
its
equilibrium.
It
should
be
noted
that
hardship
does
not
automatically
lead
to
an
exemption
from
performance.
The
disadvantaged
party
is
still
under
obligation
to
perform
even
if
renegotiations
have
commenced.
Only
an
agreement
or
a
court
order
may
release
the
party
from
this
obligation
(Article
6.2.3(2)).
Sometimes
a
situation
may
qualify
as
both
hardship
and
force
majeure
(see
below).
In
such
occasions
the
party
affected
by
these
events
may
decide
which
remedy
to pursue.[189]
Article 7.1.7 concerns force majeure situations. It reads as follows:
"Article 7.1.7 Force majeure
(1)
A
party's
non-performance
is
excused
if
that
party
proves
that
the
non-performance
was
due
to
an
impediment
beyond
its
control
and
that
it
could
not
reasonably
be
expected
to
have
taken
the
impediment
into
account
at
the
time
of
the
conclusion
of
the
contract
or
to
have
avoided
or
overcome
it
or
its
consequences.
(2)
When
the
impediment
is
only
temporary,
the
excuse
shall
have
effect
for
such
period
as
is
reasonable
taking
into
account
the
effect
of
the
impediment
on
performance
of
the
contract.
(3)
The
party
who
fails
to
perform
must
give
notice
to
the
other
party
of
the
impediment
and
its
effect
on
its
ability
to
perform.
If
the
notice
is
not
received
by
the
other
party
within
a
reasonable
time
the
party
who
fails
to
perform
knew
or
ought
to
have
known
of
the
impediment,
it
is
liable
for
damages
resulting
from
such
non-receipt;
(4)
Nothing
in
this
article
prevents
a
party
from
exercising
a
right
to
terminate
the
contract
or
withhold
performance
or
request
interest
on
money
due."
According
to
Article
7.1.1,
the
term
non-performance
refers
to
a
failure
by
a
party
to
perform
any
of
its
obligations
under
the
contract,
including
defective
performance
or
late
performance.
Article
7.1.7
thereby
applies
to
all
such
events.
According
to
the
commentary,
this
Article
concerns
the
area
covered
in
common
law
systems
by
doctrines
of
frustration
or
impossibility
and
in
civil
law
systems
by
doctrines
such
as
force
majeure, Unmöglichkeit, and the like.[190]
The
prerequisites
for
an
exemption
in
paragraph
(1)
are
almost
identical
to
those
in
KL
27.1
§
and
CISG
Article
79(1).
However,
Article
7.1.7
contains
no
provisions
on
third
persons
such
as
the
"double
force
majeure"
rules
in
KL
27.2
§
and
CISG
Article
79(2),
and
is
therefore
more
lenient
than
these.
Unlike
in
CISG
Article
79(5),
Article
7.1.7(4)
does
not
limit
the
scope
of
the
Article
to
damages
only.
Article
7.1.7
exempts
the
non-performing
party
both
from
performance
and
damages
(at
least
for
the
time
performance
is
affected
by
the
impediment),
though
its
primary
aim
is
in
releasing
the
obligor
from
liability
in
damages.[191]
Article
7.2.2
provides
for
grounds
of
exemption
in
cases
of
non-performance
of
non-monetary
obligations.
Article
7.2.1,
which
gives
the
obligee
the
right
to
require
payment,
does
not
contain
any
such
grounds,
so
the
party
may
only
be
exempted
under
the
force
majeure
rule.
If
the
less
strict
criteria
of
Article
7.2.2
are
met,
the
obligor
is
exempt
from
performing
specifically,
but
he
may
still
be
liable
in
damages
if
he
cannot
prove
an
impediment
in
accordance
with
7.1.7.
Article
7.2.2
reads
as
follows:
"Article 7.2.2 Performance of a non-monetary obligation
If a party who owes
an
obligation
other
than
one
to
pay
money
does
not
do
so,
the
other
party
may
require
performance,
unless
(a)
performance
is
impossible
in
law
or
in
fact;
(b)
performance
or,
when
relevant,
enforcement
is
unreasonably
burdensome
or
expensive;
(c)
the
party
entitled
to
performance
may
reasonably
obtain
performance
from
another
source;
(d)
performance
is
of
an
exclusively
personal
character;
or
(e)
the
party
entitled
to
performance
does
not
require
performance
within
a
reasonable
time
after
he
has,
or
ought
to
have,
become
aware
of
the
non-performance." According
to
Article
7.2.3,
the
right
to
performance
includes
the
right
to
repair
or
replacement
of
non-conforming
goods.
The
exemptions
under
Article
7.1.7
are
fairly
numerous.
Precondition
(c)
requires
that
the
obligee
has
a
legitimate
interest
to
demand
performance.
This
rule
could
be
seen
as
an
expression
of
the
principle
of
good
faith
or
loyalty.
It
can
also
be
seen
to
be
directed
towards
a
fair
choice
of
remedies:
where
performance
may
reasonably
be
obtained
elsewhere,
the
obligor's
liability
in
damages
is
adequate
to
protect
the
obligee's
interests.
Precondition
(d)
can
be
understood
in
conjunction
with
the
laws,
principles
and
international
treaties
on
human
rights:
in
many
countries
a
person
cannot
be
forced
to
work
involuntarily
(cf.
slavery).
It
should
also
be
noted
that
this
rule
concerns
other
contracts
than
contracts
for
the
sale
of
goods.
The
UNIDROIT
Principles
do
not
contain
any
references
to
municipal
laws
such
as
in
CISG
Article
28.
Where
the
contract
is
governed
by
the
Principles,
the
court
is
bound
to
order
specific
performance
if
the
preconditions
for
an
exemption
have
not
been
met
with.
4.2. Principles of European Contract Law
The
Principles
of
European
Contract
Law
were
drafted
by
the
Commission
on
European
Contract
Law
(the
"Lando
Commission")
with
financial
support
mainly
from
the
EEC.
Both
European
and
other
legal
systems
were
considered
in
the
drafting
process.
The
EU
Principles
were
also
influenced
by
the
UNIDROIT
Principles
and
vice-versa.[192]
The
complete
and
final
version
of
the
EU
Principles
was
concluded
in
1998.[193]
According
to
Article
1.101,
the
Principles
are
intended
for
use
in
the
European
Communities
only.
They
are
applicable
in
similar
types
of
situations
as
the
UNIDROIT
Principles.
Article
6.111
(2.117
in
the
previous
version)
addresses
the
issue
of
a
change
of
circumstances:
"Article 6.111 Change of Circumstances
(1)
A
party
is
bound
to
fulfil
his
obligations
even
if
performance
has
become
more
onerous,
whether
because
of
the
cost
of
performance
has
increased
or
because
the
value
of
the
performance
he
receives
has
diminished.
(2)
If,
however,
performance
of
the
contract
becomes
excessively
onerous
because
of
a
change
of
circumstances,
the
parties
are
bound
to
enter
into
negotiations
with
a
view
to
adapting
the
contract
or
terminating
it,
provided
that:
(3)
If
the
parties
fail
to
reach
agreement
within
a
reasonable
period,
the
court
may:
Article
6.111
can
clearly
be
classified
as
a
hardship
type
of
rule.
It
bears
resemblance
to
the
Article
6.2.2
of
the
UNIDROIT
Principles.
There
is
no
express
requirement
for
a
fundamental
disturbance
of
balance
though,
but
a
reference
to
excessive
onerousness.
However,
this
difference
may
be
superficial.
The
commentary
to
this
Article
explains
that
the
contract
has
to
be
completely
overturned
by
events.[194]
Another
difference
is
that
the
change
of
circumstances
has
to
have
occurred
after
the
conclusion
of
the
contract.
Furthermore,
6.111
does
not
state
whether
or
not
the
obligor
is
still
under
a
duty
to
perform.
The
most
interesting
difference
perhaps
is
the
rule
in
6.111(3)(c)
which
gives
the
court
the
power
to
award
damages
to
compensate
losses
caused
by
the
other
party's
refusal
to
negotiate
or
his
breaking
off
negotiations
contrary
to
good
faith
and
fair
dealing.
It
should
be
noted
that
both
of
the
parties
are
under
the
duty
to
negotiate
in
good
faith,
the
purpose
of
the
provision
is
to
allow
the
contractual
relationship
to
continue,
not
for
example
to
give
the
party
suffering
hardship
time
to
resist
the
other
party's
demands.[195]
Article
8.108
(ex
3.108)
provides
for
an
excuse
due
to
an
impediment:
"Article 8.108 Excuse Due to an Impediment
(1)
A
party's
performance
is
excused
if
he
proves
that
it
is
due
to
an
impediment
beyond
his
control
and
that
he
could
not
reasonably
have
been
expected
to
take
the
impediment
into
account
at
the
time
of
the
conclusion
of
the
contract,
or
to
have
avoided
or
overcome
the
impediment
or
its
consequences.
(2)
Where
the
impediment
is
only
temporary
the
excuse
provided
by
this
article
has
effect
for
the
period
during
which
the
impediment
exists.
However,
if
the
delay
amounts
to
a
fundamental
non-performance,
the
obligee
may
treat
it
as
such.
(3)
The
non-performing
party
must
ensure
that
notice
of
the
impediment
and
of
its
effect
on
his
ability
to
perform
is
received
by
the
other
party
within
a
reasonable
time
after
the
non-performing
party
knew
or
ought
to
have
known
of
these
circumstances.
The
other
party
is
entitled
to
damages
for
any
loss
resulting
from
the
non-receipt
of
such
notice." Article
8.101(2)
(ex
3.101(2))
states
that
where
a
party's
non-performance
is
excused
under
Article
8.108,
the
aggrieved
party
may
resort
to
any
of
the
remedies
set
out
in
Chapter
4
except
claiming
performance
and
damages.
According
to
the
commentary
on
the
EU
Principles,
under
8.108
the
performance
has
to
have
become
totally
impossible,[196]
and
furthermore,
that
the
preconditions
are
those
traditionally
required
for
force
majeure.
The
Article
applies
to
any
obligation,
including
monetary.[197]
The
Article
has
been
modelled
after
CISG
Article
79(1),
but
according
to
some
commentators
resembles
also
the
common
law
frustration
in
that
both
parties
are
automatically
discharged.[198]
Article
8.108
read
in
conjunction
with
8.101(2)
is
almost
identical
to
the
UNIDROIT
Principles
Article
7.1.7,
and
reference
can
be
made
to
the
discussion
above
in
4.1.
Articles
9.101
(ex
4.101)
and
9.102
(ex
4.102)
refer
to
monetary
and
non-monetary
obligations.
Once
again,
it
is
more
difficult
for
the
obligor
to
be
released
from
non-monetary
than
monetary
obligations.
However,
an
exception
is
provided
for
cases
where
the
creditor
is
yet
to
perform
and
it
is
clear
that
the
debtor
is
unwilling
to
receive
performance.
In
such
circumstances,
the
creditor
may
not
proceed
with
his
performance
and
recover
the
payments
due
if
he
could
have
made
a
reasonable
cover
transaction
without
significant
effort
or
expense,
or
if
performance
would
be
unreasonable
in
the
circumstances.
In
other
words,
the
creditor
must
have
a
legitimate
interest
in
the
performance
in
cases
where
the
debtor
no
longer
is
willing
to
accept
the
performance.[199]
This
Article
bears
a
resemblance
with
KL
52.2
§
which
concerns
performance
of
an
order
the
buyer
has
cancelled
(see
3.2.1.4.
above).
Article
9.102
in
turn
reads: "Article 9.102 Non-monetary obligations
(1)
The
aggrieved
party
is
entitled
to
specific
performance
of
an
obligation
other
than
one
to
pay
money,
including
the
remedying
of
a
defective
performance.
(2)
Specific
performance
cannot,
however,
be
obtained
where:
(3)
The
aggrieved
party
will
lose
the
right
to
specific
performance
if
he
fails
to
seek
it
within
a
reasonable
time
after
he
has
or
ought
to
have
become
aware
of
non-performance."
Again,
Article
9.102
is
very
similar
to
7.2.2
of
the
UNIDROIT
Principles.
Article
9.103
explicitly
states
that
an
exemption
from
performing
under
9.102
does
not
lead
to
an
exemption
from
damages.
This
question
is
to
be
decided
under
8.108.
4.3. Conclusions
Both
the
UNIDROIT
and
the
EU
Principles
apply
the
same
structure.
Hardship
may
be
invoked
in
cases
of
serious
contractual
imbalance.
There
are
separate
rules
concerning
monetary
and
non-monetary
obligations.
It
is
easier
to
be
exempted
from
performing
specifically
a
non-monetary
obligation
than
from
performing
a
monetary
one.
Furthermore,
it
is
easier
to
get
an
exemption
from
specific
performance
of
a
non-monetary
obligation
than
from
liability
in
damages.
The
discussed
Principles
contain
what
we
could
call
the
"full
set"
of
juristic
tools
for
coping
with
changed
circumstances.
They
encompass
rules
exempting
from
specific
performance
and
from
liability
in
damages
and
they
provide
for
renegotiations
and
adjustment.
Events
of
impossibility,
force
majeure,
and
hardship
have
been
taken
into
consideration.
Furthermore,
the
Principles
widen
the
applicability
of
the
exemptions
outside
pure
instances
of
impossibility
or
force
majeure
by
references
to
unreasonableness
or
unconscionability
as
well
as
to
loyalty
or
the
observance
of
good
faith
(cf.
Articles
7.2.2(c)
and
9.102(d)
which
require
that
the
seller
have
a
legitimate
interest
to
demand
performance
this
might
also
be
seen
as
a
sign
of
Anglo-American
influence
in
the
Principles).
Table
3
presents
a
rough
illustration
of
the
structure
of
exemption
under
the
studied
Principles.
Table 3. Exemptions under the UNIDROIT and EU Principles
Both the examined instruments differ from the Finnish Sale of Goods Act, the CISG and the English frustration as well. They seem to be based on a slightly
different conception of contract. Though pacta sunt servanda still is the main rule, exemptions from obligations are granted on a more lenient basis and the
contract can be more freely modified by the court. Furthermore, both instruments contain express references to the obligation of observing good faith (Articles
1.7 and 1.201 most importantly) and for example the hardship provisions seem to promote a more co-operative, loyalty based notion of contract.
It should also be noted that both sets of principles were completed in the 1990's. Therefore they represent the modem developments in the field of contract law.
There can, however be many views on, for example, EU Principles Article 6.1 11(3)(c). It is submitted that it may in many situations be artificial to require
renegotiations from the parties. This may also cause unnecessary uncertainty. Furthermore, this may cause additional costs and take time, which may be against
both of the parties' interests. Moreover, the possibility to compel a party to negotiate by the risk of liability in damages might easily be abused despite of the
obligations of good faith and co-operation. On the other hand, the provision may have positive effects as well. When the parties know from the beginning of their
contractual relationship that changed circumstances may lead to renegotiations they may, for example, assume an attitude towards their relationship that emphasizes co-operation which may in turn make it easier to cope with changed circumstances and other such problems.
5. IMPOSSIBILITY IN ENGLISH LAW
5.1. Introduction
The doctrine of frustration may be applied in cases where the circumstances have significantly changed after the conclusion of the contract. When a contract is frustrated it becomes void and the parties to it are released from their obligations. Not only does the contract become
avoided, but also the parties are released from any liability in damages for non-performance. The first and most obvious cause of frustration is impossibility of
performance. When performance has been impossible already at the time the contract was concluded, frustration is not applicable but instead the doctrine of
mistake comes into question.[200] From impossibility, the law has evolved to
the
direction
that
any
event
that
would
make
the
performance
of
the
contract
a
significantly
different
thing
from
that
contracted
for
causes
frustration.[201]
The
doctrine
of
frustration
provides
a
different
kind
of
solution
to
the
problem
of
impossibility
of
performance
and
changed
circumstances
than
has
been
discussed
above.
Frustration
affects
the
contract
as
a
whole,
rendering
it
discharged,
whereas
the
force
majeure
types
of
solutions
only
affect
the
obligations
of
the
parties
under
the
contract,
but
leave
the
contract
itself
intact.
Solutions
of
the
kind
of
frustration
are
not,
however,
the
sole
property
of
common
law
systems.
For
example
in
German
law
both
impossibility
(Unmöglichkeit)
and
the
destruction
of
the
basis
of
the
contract
(Wegfall der Geschäftsgrundlage),
which
would
seem
to
be
typical
cases
frustration,
have
their
places
in
contract
law
(see
1.2.
above).[202]
However,
on
the
whole,
the
two
systems
differ
considerably.
Nevertheless,
there
seem
to
be
analogies
in
the
historical
development
of
law
in
the
continental
Europe
in
comparison
to
that
in
England.[203]
These
issues,
however,
are
beyond
the
scope
of
this
study.
It
should
also
be
noted
that
the
doctrine
of
frustration
applies
to
all
kinds
of
contracts
and
the
cases
discussed
mostly
are
other
than
sales
contracts.
The
cases
are,
however,
essential
for
understanding
the
doctrine
even
though
they
may
not
represent
the
focus
area
of
this
study:
international
sales.
Special
legislation
on
sales
contracts
will
be
discussed
in
5.3.1.1.
5.2. Development of the doctrine of frustration
The
doctrine
of
frustration
started
to
develop
as
late
as
in
the
nineteenth
century.
Before
this
most
contractual
obligations
were
regarded
as
absolute.
Supervening
events
were
not
regarded
as
excuses
for
non-performance.
This
rule
was
laid
down
in
the
seventeenth
century
in
Paradine
v.
Jane,
where
a
tenant
was
sued
for
rent
and
pleaded
that
the
King's
enemies
had
possessed
the
land
for
about
two
years
and
that
he
therefore
could
not
be
liable
for
the
rent.[204]
The
court
held
him
liable,
and
stated:
"When
the
party
by
his
own
contract
creates
a
duty
or
charge
upon
himself,
he
is
bound
to
make
it
good,
if
he
may,
notwithstanding
any
accident
by
inevitable
necessity,
because
he
might
have
provided
against
it
by
his
contract."[205]
The
rule
or
doctrine
of
absolute
contracts
did
provide
that
if
performance
were
or
had
become
illegal,
the
performing
party
was
relieved
from
his
obligations
(cf.
"bound
to
make
it
good,
if
he
may").[206]
Another
exception
to
the
rule
probably
were
contracts
for
personal
performance
in
cases
where
the
performing
party
died
or
became
permanently
incapacitated.[207]
Otherwise,
a
party
who
was
bound
by
a
contract
to
perform
did
not
become
free
of
his
obligation
even
if
performance
was
impossible
or
futile
and
he
himself
was
not
the
cause
of
this.
He
would
still
be
under
obligation
to
perform
or
to
pay
damages
for
non-performance.
The
alleged
justification
for
this
rule
was
that
the
parties
could
always
guard
themselves
against
unforeseen
events
by
express
stipulations
in
the
contract.[208]
In
modern
times,
however,
this
approach
seems
unsatisfactory
whenever
it
would
seem
unreasonable,
regarding
the
contract
and
the
circumstances
in
which
it
was
made,
to
expect
the
parties
to
have
provided
for
such
events.[209]
The
law
gradually
changed,
starting
from
the
already
mentioned
case
Taylor v. Caldwell in
1863
and
the
doctrine
of
frustration
evolved.
In
the
said
case
the
defendants
had
contracted
to
allow
the
plaintiffs
to
use
the
Surrey
Gardens
and
Music
Hall
for
four
concerts
on
four
designated
days
in
the
summer
of
1861,
and
to
provide
various
side-shows
and
other
entertainment
in
the
gardens.
Only
six
days
before
the
first
concerts
the
hall
was destroyed
in
an
accidental
fire.
The
court
held
that
the
defendants
were
not
liable
for
damages
for
the
plaintiff's
wasted
expenses
because
the
contract
had
been
discharged.
The
reasoning
was
that
the
parties
must
have
known
that
the
contract
could
not
be
fulfilled
unless
a
certain
thing
(the
hall)
continued
to
exist
and
that
the
contract
"was
not
to
be
construed
as
a
positive
contract,
but
as
subject
to
an
implied
condition
that
the
parties
shall
be
excused
in
case,
before
breach,
performance
becomes
impossible
from
the
perishing
of
the
thing
without
the
fault
of
the
contractor."[210]
After Taylor v. Caldwell the doctrine
of
frustration
was
extended
to
cases
in
which
performance
became
impossible
in
some
other
manner
than
through
the
perishing
of
a
particular
thing.
Finally
its
applicability
reached
cases
where
performance
did
not
become
impossible
but
the
commercial
object
or
purpose
of
the
contract
was
frustrated
(frustration
of
the
common
venture).
In Krell v. Henry in
1903
the
defendant
had
hired
a
flat
for
the
days
on
which
the
coronation
of
King
Edward
VII
was
to
take
place
in
the
purpose
of
watching
the
proceedings.
This
purpose
was
not,
however,
stated
in
the
contract.
The
court
held
the
contract
frustrated
when
the
proceedings
were
postponed
due
to
the
illness
of
the
King.[211]
In
this
case,
the
owner
of
the
flat
most
probably
knew
of
the
reasons
why
the
defendant
needed
the
flat
and
the
price
was
substantially
higher
than
the
normal
rent
would
have
been.
According
to
Atiyah,[212]
the
fact
that
the
owner
is
aware
of
the
hirer's
motives
does
not
necessarily
lead
to
the
frustration
of
the
contract.
Neither
is
the
fact
that
the
contract
suddenly
becomes
more
disadvantageous
to
one
of
the
parties,
due
to, for example, a
heavy
change
in
prices,
enough
to
frustrate
the
contract.[213]
One
could
interpret
Krell v. Henry so
that
the
subject
matter
of
the
contract
in
fact
was
to
provide
the
hirer
a
place
where
he
could
observe
the
coronation
proceedings
from
on
a
given
date.
This
has
also
been
the
view
of
some
authors.[214]
When
the
coronation
did
not
take
place
it
was
actually
impossible
for
the
flat
owner
to
perform
the
contract.
He
was
not
in
possession
of
a
flat
where
the
coronation
could
be
observed
from.
No
one
was.
The
subject
matter
of
the
contract
did
not
exist
at
the
time
the
contract
was
to
be
executed
and
the
contract
could
have
been
frustrated
because
of
impossibility
to
perform.
The
authors,
however,
speak
of
frustration
of
the
common
venture
and
not
of
impossibility.
5.3. Operation of the doctrine
Events
that
may
lead
to
frustration
can
be
divided
into
groups,
for
example, into
impossibility
and
frustration
of
a
common
venture
[215]
(or
purpose).
Some
authors
see
illegality
as
an
independent
category
separate
from
other causes.[216]
These
categories
can
be
further
divided
into
subcategories.
For
example
Treitel
[217]
separates
impossibility
from
frustration
of
purpose
and
illegality
and
describes
six
sources
of
impossibility:
(1)
destruction
of
a
particular
thing,
(2)
death
or
incapacity,
(3)
unavailability,
(4)
failure
of
a
particular
source,
(5)
method
of
performance
and
(6)
statute.
In
the
following
text
this
structure
is
loosely
followed,
except
that
the
last
source
of
impossibility,
statute,
[218]
is
omitted
altogether.
Bayles
distinguishes
impossibility
from
frustration.[219]
He
even
refers
to
a
separate
doctrine
of
impossibility,[220]
but
does
not
reveal
how
it
functions.
According
to
Bayles,
in
cases
of
frustration
performance
is
in
fact
possible.[221]
By
the
doctrine
of
impossibility,
he
seems
to
be
referring
to
discharge
of
the
contract
because
of
impossibility
of
performance,
while
the
doctrine
of
frustration
would
cover
the
frustration
of
purpose
(or
common
venture).[222]
Other
authors
do
not
seem
to
make
such
distinction.
For
them
impossibility
forms
a
part
of
the
doctrine
of
frustration,
not
a
separate
doctrine.
Impossibility
was
the
first
cause
acknowledged
to
frustrate
a
contract
in
Taylor
v.
Caldwell
as
discussed
above.[223]
For
example
Atiyah
writes:
"
there
has
been
a
tendency
to
separate
off
questions
of
subsequent
impossibility
and
to
put
them
in
a
doctrine
of
their
own,
called
the
doctrine
of
'frustration'"
(as
opposed
to
other
changes
in
circumstances).[224]
5.3.1. Frustration by impossibility
Impossibility
of
performance
was
the
first
acknowledged
cause
of
frustration.
If
the
performance
of
a
contract
becomes
substantially
impossible
without
any
fault
on
either
side,
the
contract
is
prima
facie
frustrated.[225]
Like
in
the
first
frustration
case, Taylor v. Caldwell,
a
clear
application
of
the
doctrine
is
when
a
particular
thing
(which
forms
the
subject
matter
of
the
contract)
is
destroyed.
Similarly, in
a
sale
of
specific
goods,
if
the
goods
perish,
the
sales
contract
might
become
frustrated.[226]
The
destruction
does
not
have
to
be
complete.
For
example
in
Asfar
&
Co.
v.
Blundell
(1896) [227]
a
cargo
of
dates
became
exposed
to
seawater
and
was
therefore
considered
by
the
court
to
be
"for
business
purposes
something
else."[228]
5.3.1.1. Sale of goods
The
remedies
of
the
buyer
under
the
Sale
of
Goods
Act
1979
are
damages
for
non-delivery
(s.
51),
damages
for
breach
of
condition
or
warranty
(s.
53),
which
refers
to,
for
example,
late
delivery
or
defective
quality
of
the
goods,
and
specific
performance
(s.
52).
Section
52
allows
the
court
considerable
powers
of
discretion;
under
no
circumstances
is
the
court
under
an
obligation
to
order
the
contract
to
be
performed
specifically.[229]
There
are
no
express
excuses
from
specific
performance,
nor
are
they
needed
since
specific
performance
of
a
non-monetary
obligation
in
the
common
law
traditionally
is
an
exception,
not
the
main
rule
as
it
is, for example, in
the
CISG.[230] Section 52 reads as follows:
Impediment to performance or unreasonableness
Cause irrelevant
®
Exemption from performance=
Impossibility amended by reasonableness
Impediment to performance
Cause
1. Reasonably irresistible
2. Reasonably unforeseeable
3. Beyond control (external)®
Exemption from damages as well=
Force majeure amended by reasonableness
Any change that affects the contract
All the relevant factors considering unconscionable
®
Adjustment or termination=
Unconscionability
Situation not unconscionable
®
No effect=
Mere inconvenience
(a)
the
change
of
circumstances
occurred
after
the
time
of
conclusion
of
the
contract,
and
(b)
the
possibility
of
a
change
of
circumstances
is
not
one
which
could
reasonably
have
been
taken
into
account
at
the
time
of
conclusion
of
the
contract,
and
(c)
the
risk
of
the
change
of
circumstances
is
not
one
which,
according
to
the
contract,
the
party
affected
should
be
required
to
bear.
(a)
terminate
the
contract
at
a
date
and
on
terms
to
be
determined
by
the
court;
or
(b)
adapt
the
contract
in
order
to
distribute
between
the
parties
in
a
just
and
equitable
manner
the
losses
and
gains
resulting
from
the
change
of
circumstances;
and
(c)
in
either
case,
award
damages
for
the
loss
suffered
through
the
other
party
refusing
to
negotiate
or
breaking
off
negotiations
contrary
to
good
faith
and
fair
dealing."
(a)
performance
would
be
unlawful
or
impossible;
or
(b)
performance
would
cause
the
obligor
unreasonable
effort
or
expense;
or
(c)
the
performance
consists
of
services
or
work
of
a
personal
character
or
depends
upon
a
personal
relationship,
or
(d)
the
aggrieved
party
may
reasonably
obtain
performance
from
another
source.
Performance or unreasonableness
Cause irrelevant
®
Exemption from performance of non-monetary obligation=
Impossibility amended by reasonableness and loyalty
Impediment to performance
Cause
1. Reasonably irresistible
2. Reasonably unforeseeable
3. Beyond control (external)®
Exemption from performance of any obligation and damages=
Force majeure amended by reasonableness
Balance of the contract disturbed, not necessarily an impediment to performance
A qualified change in contractual balance
®
Renegotiations, adjustment or termination=
Hardship
Qualifications in the contract / rule not met
®
No effect=
Mere inconvenience
| S. 52 | "(1) In any action for breach of contract to deliver specific goods or ascertained goods the court may, if it thinks fit, on the plaintiff's application, by its judgement or decree direct that the contract shall be performed specifically, without giving the defendant the option of retaining the goods on payment of damages. (2) The plaintiff's application may be made at any time before judgement or decree. (3) The judgement or decree may be unconditional, or on such terms and conditions as to damages, payment of the price, and otherwise, as seems just to the court." |
The principal remedies of the seller are an action for the price (s. 49(1)) and an action for damages for non-acceptance (s. 50(1)). The Sale of Goods Act 1979 does not provide for any force majeure type of exemptions as do the Finnish Sale of Goods Act and the CISG. The only section having a similar effect is section 7, which provides for frustration in the case of destruction of the goods. Section 7 reads:
| S. 7 | "Where there is an agreement to sell specific goods, and subsequently the goods, without any fault on the part of the seller or buyer, perish before the risk passes to the buyer, the agreement is thereby avoided." |
According to Atiyah, s. 7 only applies to a contract for the sale of specific goods [231] in which neither the property nor the risk has passed.[232] If only a part of the goods perish, then the law may be that if the contract is unseverable, it is frustrated, whereas if it is severable it is frustrated only as to the part which has perished. There is, however, a case (H R & Sainsbury v. Street (1972) W.L.R. 834) suggesting that even if the contract were unseverable the seller might be obliged to offer the remaining goods to the buyer, but the buyer might have the option whether or not to accept the goods.[233]
S. 7 of the Sale of Goods Act 1979 does not automatically apply in all situations that would seem to come within its wording. According to Atiyah there may be at least three possibilities that will have to be taken into consideration: (1) the contract may be frustrated because of an implied condition that if the goods perish the contract will be discharged and neither party shall be held liable; (2) the seller may have contracted that the goods will not perish, in which case he will have to bear the losses and possibly pay damages for non-performance; (3) the buyer may have contracted to bear the risk of the goods perishing, in which case he is liable for the price and possibly damages as well.[234]
Atiyah formulates the common law doctrine of frustration in cases of sales of goods so that "a contract for the sale of specific goods may be frustrated by any event [235] which destroys the basis of the contract and radically alters the obligations of the parties, provided that the event occurs before the property and risk have passed to the buyer."[236] In the case of unascertained goods, the possibility of frustration is questionable and depends on the type of the unascertained goods.[237] It would seem that frustration through perishing of purely generic goods is impossible because a whole species of goods cannot perish. However, in re Badishe Co Ltd [238] it was held that a contract to supply unascertained goods which both parties knew could only be obtained from Germany was frustrated by the outbreak of war.[239] The goods in this case did not perish, but became impossible to obtain. One could say that in the commercial sense they did perish as they disappeared from the market. It would also seem that contracts for the sale of unascertained goods can be frustrated if they are to be taken from a particular source, and this source is destroyed.[240]
5.3.1.2. Death or incapacity
It seems quite natural that certain contracts of personal character are discharged if one of the parties dies or becomes incapacitated and the contract thereby impossible to perform. As mentioned in 5.2., this was probably the law already before the doctrine of frustration started to develop. Some types of contract may be frustrated if either of the parties becomes incapacitated, e.g. contracts for apprenticeship or agency.[241] A contract that requires some special skill from one of the parties may be frustrated if this party becomes incapacitated (but not if the other one becomes). If there is, for instance, a contract to write a book, this contract would be frustrated by the supervening insanity of the author.[242]
An example of a case where the receiving party becomes incapacitated and this causes frustration is a case where a person who booked a course of dancing lessons was seriously injured and could not dance anymore.[243] A contract could also be frustrated by the death or incapacity of a third party, for example if A contracted B to paint a portrait of C, and C died.[244]
5.3.1.3. Unavailability of an essential factor
Performance can become impossible also when the subject matter, or a thing or person essential for it becomes unavailable for that purpose though it continues to exist or retains capacity. Contracts for charterparties have been frustrated for example when a ship was seized, detained or requisitioned and when cargo was impossible because of a strike at the port. Sales contracts have been frustrated for instance when the goods were requisitioned and contracts for personal services when one of the parties fell ill or was interned in an institution or conscripted into the armed forces.[245]
If unavailability is temporary, it will still frustrate the contract most likely if the contract was to be performed at or within a given time (there is an express term on this in the contract or it is clear from the nature of the contract) and the time of performance was of the essence [246] of the contract. Temporary unavailability may frustrate a contract in other types of situations as well. A reason for allowing discharge of the contract may be, for instance, that after a delay the performance would be of no use to the receiver. In some cases, the justification has been that the performance would be significantly more burdensome for the rendering party. In these cases, the actual or expected length of the delay has played an important part. As well as in other causes of frustration, unavailability may affect only part of the performance. As in other cases, the contract might therefore become partially frustrated.[247]
5.3.1.4. Failure of a particular source
If the subject matter of the contract was to be obtained from a specific source, the contract may become frustrated should this source become unavailable without the fault of either party.[248] If the contract expressly stipulates that the goods are to be from a specified source, the contract is frustrated if this source fails. For example, in Howell v. Coupland [249] a farmer sold potatoes that were to be grown on a specified piece of land. The crop largely failed and the court held the contract frustrated thus relieving the farmer from liability in damages.[250]
Were the source intended by one of the parties only, there is no frustration. Thus in the case of "Finland birch timber" the contract was not frustrated though the seller had expected to get timber from Finland and this proved impossible because of the outbreak of war.[251] In this case, the buyer was not interested in the origin of the goods.[252] A contract is not frustrated even if the source that failed was the only possible source as long as the buyer was not aware of this. The same applies to the buyer whose source of funding fails and who therefore is incapable of paying the price.[253]
In cases where the contract expressly stipulates no specific source but both of the parties intended a specific one to be used, the law is not clear. An implied term may perhaps be construed into the contract. Re Badishe Co Ltd has sometimes been referred to to support the view that a total failure of a mutually contemplated source frustrates the contract but, for example, Treitel is of the opinion that this case was a special one and its authority perhaps does not reach to cases where the causes of the failure of the source are less serious than a war. He sees that, on the one hand, the fact that the courts have in some cases emphasised that only one of the parties contemplated the use of a specific source would support allowing frustration where both parties agreed on this matter, but on the other, the fact that in some such cases the commercial reality nowadays may be that the seller usually protects himself against such failures would speak against frustration.[254]
The failure of the source can also be partial. This would normally have three consequences: (1) the seller is excused from delivering the missing goods, (2) he is under obligation to deliver the goods that he has been able to obtain, and (3) the buyer is obliged to accept delivery of the goods obtained.[255] If the seller has entered into a number of contracts to deliver goods from a specific source and the source partially fails, there are in principle four possibilities of how to solve the situation: (1) frustrate all the contracts, (2) frustrate none of the contracts, (3) frustrate part of the contracts and (4) divide what has been obtained from the source pro rata. None of these alternatives is without difficulties. If all the contracts are frustrated, the seller would be free to try to make extra profit by renegotiating prices in the changed-market situation. Frustrating none of the contracts would mean that the seller would have to answer for his non-performance to those buyers who were left without their goods. Frustrating only part of the contracts, of course, leads to problems in how to choose which contracts to discharge. And finally pro rata division would mean modifying the contract, which has traditionally been thought beyond the power of the courts unless there are express provisions allowing it in the contracts.[256] Treitel states that the common law doctrine of frustration appears to apply to the contract as a whole only, so it would be impossible to discharge the contracts partially.[257]
5.3.1.5. Method of performance impossible
If the contract stipulates that a specified method be used, and this method becomes impossible to perform, the contract may be discharged. For example, a contract to ship some cargo on a specified vessel during a specified time period was held to be frustrated after the ship went aground and could therefore not be used for the shipment as agreed.[258] The rules as to the method of performance seem to be derived from shipping cases solely, i.e. from cases where the problem has been which route to use.
The closing of the Suez Canal in 1956 and again in 1967 caused a number of cases where the contract had been to ship cargo to places most conveniently reached via Suez. Because this route became unavailable, the only option would have been to ship the goods via the Cape of Good Hope, which had meant significant extra costs to the person responsible for the shipping if the price was fixed, or in some cases to the charterer, if the price depended on the time spent on the voyage. The holdings in these cases seem to have focused on two questions: (1) was there an express term stipulating that a certain route be used (or was a certain route clearly contemplated by both parties), and (2) was the difference in the obligations of the suffering party sufficiently fundamental to frustrate the contract.[259]
In cases where the performance of one of the parties was fundamentally altered by the impossibility to use the specified method, the contract would likely be frustrated if the method was at least contemplated by both of the parties. On the other hand, not even an express provision to use a certain route would seem to suffice to frustrate the contract if the performance did not become fundamentally more onerous to one of the parties. Thus the answer to both of the above posed questions should be yes in order for frustration to be granted.[260]
These decisions would interestingly seem to differ from the failure-of-a-particular-source cases, where an express provision to use a certain source sufficed as a ground for frustration. What makes impossibility to use a specific source and impossibility to use an agreed route so different that this allows varying handling of the cases? Furthermore, in Krell v. Henry the decision was based on the assumption that the owner of the flat knew that the hirer intended to use it to watch the coronation proceedings, so the fact that the purpose of the contract was mutually contemplated by the parties was sufficient for a decision to discharge the contract even though there was no express provision in the contract itself.
The interpretation of the rules on when to discharge a contract seem to have been stricter in cases of shipments via alternative routes. So: why does it sometimes suffice that some aspect of the contract is mutually contemplated by both of the parties, sometimes an express term is required, and sometimes not even this is enough but a fundamental change in the significance of the obligations has to occur? Is it just that some types of contract are to be treated differently, or is it so that there actually are no uniform rules as to when to discharge a contract? Or maybe the cases have been distinguished on some other basis, perhaps not even mentioned in the decisions?
According to Atiyah, a change of circumstances which only affects the way in which the performance is to be carried out does not normally frustrate the contract (Atiyah 1995a, p. 240). In this sense, Krell v. Henry differs from the method and source cases, as the question was not of the way of the performance, but how do the other two cases differ from each other? Furthermore, in all of these cases one could have asked what is the subject matter of the contract and has it become impossible to perform it?
5.3.1.6. Impossibility versus impracticability
The concept of impossibility has already been discussed above in chapter 2. As was noticed, the question of especially practical impossibility is problematic. As mentioned, a trend in the United States has been to use the term impracticability instead of impossibility. In Britain, however, this trend has not been accepted. Also the term "commercial impossibility" has been rejected [261] and the House of Lords has stated that "a wholly abnormal rise or fall in prices" would not affect the bargain.[262] What is required is a fundamental change in the circumstances. In Davis Contractors Ltd. v. Fareham U.D.C.[263] it was stated that "It is not hardship or inconvenience or material loss itself which calls the principle of frustration into play. There must be as well such a change in the significance of the obligation that the thing undertaken would, if performed, be a different thing from that contracted for."[264]
Treitel [265] lists four possible exceptions to the general rule that impracticability is not sufficient to frustrate a contract. Firstly, there have been some cases where performance was delayed for a long time due to wartime conditions and the contracts were held frustrated after the war, though they could have been fulfilled. Secondly, express contractual provisions can lead to discharge (under this condition, and not under the doctrine of frustration). If the contract is of an indefinite duration, impracticability could bring them to discharge. In Staffordshire Area Health Authority v. South Staffordshire Waterwoks Co., there was a manyfold increase in the costs (of supplying water) over a fifty-year period. However, though frustration was said to have caused the discharge, in this case the court actually decided only that the indefinite contract was terminable on reasonable notice, which can be said to be another general principle not connected with frustration at all.[266] The fourth possible exception would be where there is a cross-border sales contract and a breakdown of diplomatic and commercial relations between the two countries in question occurs. This would only, however, frustrate the contract if the parties to the contract were controlled by the governments in question.[267]
5.3.2. Frustration of the common venture
As has already been mentioned, the doctrine of frustration eventually expanded to cover some situations other than impossibility as well. In frustration of the common venture, the actual performance has not become impossible, but the ultimate purpose pursued by both of the contracting parties.[268] Instead of common venture, many authors just speak of frustration of purpose or common purpose.
The decision most often referred to in association with frustration of purpose is Krell v. Henry ,[269] which has already been mentioned. As has been stated above in 5.2., one could see this decision as a case of impossibility as well. Another example of frustration of purpose is Denny, Mott & Dickson v. James B. Fraser & Co. Ltd.[270] where an agreement for the lease of a timber yard was made for the purpose of enabling the parties to carry out a contract between them for the sale of timber. The performance of the sales contract was prevented by wartime regulations and this was held to be sufficient to frustrate the lease as well. Once again, one might say that the subject matter of the contract included both the lease and the purpose. When the sales contract was discharged the performance of the lease contract became impossible. Through construction of the contract the case could have been decided on the basis of impossibility (see also 5.5. below). One could also perhaps say that as the agreement in the two referred cases was to render something for a certain purpose, it impliedly included a rescinding term in case the purpose became impossible to attain.
The courts have been reluctant to grant frustration on the basis of frustration of purpose. To illustrate this, Treitel, for example, quotes a decision saying that "the frustrated expectations and intentions of one party to a contract do not necessarily, or indeed usually, lead to the frustration of that contract."[271] This, however, seems natural as the question essentially is of a common venture, not the goals of one of the parties. As has been stated "it is the common object that has to be frustrated, not merely the individual advantage that one party or the other might have gained from the contract."[272] In this sense, the doctrine of frustration would clearly seem to differ from hardship type of rules. Anyhow, the two above mentioned cases were the only ones representing frustration of purpose that were referred to in the literature reviewed for this study, whereas there seems to be a body of cases where frustration has not been granted on this basis.[273]
The idea of a common purpose is somewhat vague altogether.[274] As has been mentioned earlier, Atiyah has been of the mind that Krell v. Henry was justified partly because the owner was aware of the purpose of the hirer.[275] Do we talk of common purpose whenever one party is aware of the other party's objectives? For instance, a seller may have assumed a duty to see that the goods are fit for the purposes of the buyer or such duty may be imposed upon him by a statute.[276] Then the contract could be avoided if this duty had not been observed (because of breach, not frustration), or frustrated if the circumstances were beyond the parties' control, and performance became impossible. These cases have briefly been addressed in relation to frustration of purpose by, for example, Atiyah.[277] There is a difference, however, between cases where the rendering party assures that goods are fit for a purpose and cases in which it becomes impossible to use the goods for the intended purpose. It is a different thing to guarantee that the goods are fit to be exported than to bear the risk that the goods cannot be exported because of a prohibition of export (see 5.3.3. below).
5.3.3. Illegality
That a contract is discharged after its performance has become illegal would seem natural as a society can hardly give protection to ventures it has announced as illegal. Instead, the party who refuses to perform the illegal acts should be protected. The apportioning of risks can, however, be difficult. Both parties have entered the contract when it was still legal. Who bears the risk of the laws changing, and is this a question different from other types of supervening events beyond the parties' control?
In relation to frustration, illegality has sometimes been seen as a separate ground of discharge, and not as a subcategory of impossibility. According to Treitel, the object of the doctrine of frustration in cases of supervening impossibility or frustration of purpose is to allocate the losses caused by the supervening event in a satisfactory manner, whereas in a case of supervening illegality, the court has to take into account, apart from the parties' interests, also public interests which leads to some extent to special rules of frustration.[278]
Illegality can also bring about frustration of purpose. For example, a sales contract may be frustrated by prohibition of export if it provides that the goods be exported, but not if the buyer only intended to export the goods, not even if the seller was aware of this.[279]
5.3.4. Limitations
There are some limitations to the applicability of the doctrine of frustration. Frustration may be excluded, for instance, in cases where (1) there are express provisions for the occurred event in the contract, (2) the event was foreseen or foreseeable or (3) the event occurred due to the fault of one of the parties.[280] These limitations can also be associated with the sets of rules discussed in previous parts of this study.
According to Treitel, the object of the doctrine of frustration is to allocate the risks of supervening events satisfactorily.[281] There is, however, no reason why the parties could not themselves prepare for the risks in the contract. Even though the doctrine of absolute contracts has been modified by the later developments in law, it still remains the main rule from which there are then some exceptions. When the parties have clearly allocated the risks in the contract, the contract is to be kept and frustration does not come into question.[282] A provision excluding frustration may also be implied, for example, if the contract is essentially a speculative one.[283]
There are some qualifications to the said exception. For example, in cases where the contract has required trading with the enemy at war times, provisions for only suspending the activities in the occasion of war have been set aside on the basis of public policy considerations. Furthermore, if the construction of the provision is narrow, this may lead to the interpretation that it does not cover events that fundamentally change the conditions, but is restricted to, for example, temporary difficulties, like lack of labour, bad weather, or failure of supplies. The provision may also be incomplete so that though it may exclude frustration by some supervening events, the event that has happened is not one of them.[284] The same would apply to, for example, a force majeure clause as well.
If the risk of a potentially frustrating event has been foreseen by the parties or it has been foreseeable, the inference is that the doctrine of frustration is excluded. This is because the parties have, or should have, taken it into consideration when entering into the contract.[285] This is, however, only a prima facie interpretation, and it can be set aside by contrary evidence,[286] unlike in the force majeure type of rules discussed above.
A party cannot call on self-induced frustration, that is, on frustration caused by his own actions or the actions of those he is responsible for. Negligence may also be enough to exclude frustration, depending on the case. If the question is for example of a singer, who has lost her voice, and cannot therefore keep her contract to perform, she could probably plead frustration as long as she had not deliberately tried to get ill and thereby be freed of her obligations.[287] On the other hand, for example, in Taylor v. Caldwell, if the fire had been caused by the hall owner's negligence, this would probably have been enough to exclude the possibility of frustration.[288] In the regulations studied above in chapters 3 and 4, fault typically does not affect the right to be exempted from specific performance. However, fault on the obligor's side usually leads to liability in damages and fault on the obligee's side to the exemption of the performing party.[289]
In cases where there has been more than one contract and it has become impossible to perform all of them, frustration has in the courts been denied on the basis that this would allow the performing party to elect which of the contracts to frustrate and frustration would be caused by this election by one of the parties. Treitel has criticised this view and said that the rationale of the doctrine should lead to the discharge of some of the contracts. Furthermore, the onus of proving that frustration has been self-induced is on the party who alleges this.[290]
One limitation to the doctrine of frustration has also been said to be that it does not apply where the event does not displace the basic obligation of the contract but merely makes it more onerous for one of the parties.[291] A person who undertakes to do something takes the risk that performing the undertaking proves, for instance, more difficult or expensive than expected or even impossible due to changes in circumstances which are "normal or merely slight deviations from the normal."[292] In cases where the parties have made a contract that is to be performed in some distant future, they will generally be held to have assumed the risk of performance whatever the future may be.[293] It should be noted that these cases are to be distinguished from the contacts of perpetual type, where the parties exchange performances on a continuous basis, like in Staffordshire Area Health Authority v. South Staffordshire Waterwoks Co. discussed in 5.3.1.6. above.
Furthermore, a person is thought to have taken the risk of impossibility if the result of impossibility gives him a remedy over some other person. The courts are especially reluctant to grant frustration to a party who does not suffer from the frustrating event but tries to gain some additional advantage through frustrating the contract, if the other party, who is affected by the frustrating event, denies that the contract is frustrated.[294] This could be seen as a reference to the observance of good faith, co-operation, or loyalty as well.
5.4. Effects of frustration
In the common law, the effect of frustration is that the contract is automatically terminated at the time of the frustrating event. Both of the parties are freed from their contractual obligations from that moment on. Initially this caused unjust results as the parties were still held to be liable for any performance fallen due before that date. There was no possibility of recovering advance payments and so forth. Statutory measures to change this and other injustices were then taken.[295]
Section 1(2) of the Law Reform (Frustrated Contracts) Act 1943 contains three rules: (1) all sums payable under the contract before the time of discharge cease to be payable when frustration occurs, (2) all sums paid before the time of discharge are recoverable, and (3) if the party to whom sums were paid or payable to perform the contract has before the time of discharge incurred expenses to perform the contract, the court may allow him to retain or recover all or part of the sums (but not more than actual amount). S. 1(3) contains the rule that where one of the parties has obtained a valuable benefit (other than a payment of money to which s. 1(2) applies), the court can order him to pay a sum that the court considers just, having regard to all the circumstances of the case.[296] The effects are similar to the consequences of avoidance of contract under Finnish law (a question outside the scope of this study).
The referred Act does not apply to (1) voyage charterparties and other contracts for the carriage of goods by sea, (2) contracts of insurance, and (3) certain contracts for the sale of goods: (a) contracts to which s. 7 of the Sale of Goods Act 1979 applies, and (b) "any other contract for the sale, or the sale and delivery, of specific goods, where the contract is frustrated by reason of the fact that the goods have perished," which would seem to refer to any other contract than those governed by s. 7 of the Sale of Goods Act 1979. As earlier mentioned, s. 7 provides that an agreement to sell specific goods is avoided if without any fault on the part of the seller or buyer, the goods perish before the risk has passed to the buyer. The last of the said exceptions (3.b) has caused controversy, because it is hard to imagine how, after the risk has passed to the buyer, in any case the contract could be frustrated by the perishing of the goods.[297]
5.5. Justification of frustration
Five main theories have been presented for the basis of the doctrine of frustration. The narrowest of these theories attempts to explain why both of the parties are discharged even if the frustrating event only affects the performance of one of the parties. The theory says that the other party is discharged as well as there is a total failure of consideration, i.e. the other party receives nothing in exchange for his performance. This is an explanation more usually used in the U.S. In England, a more often used argument is that the common object of the parties has been frustrated. The problem of the theory of failure of consideration is that the failure should be total whereas in reality the other party often benefits from a partial performance.[298]
The first theory as to why a contract can be frustrated at all is that the contract is discharged because it contains an implied term that it should cease to be binding in certain circumstances. This theory binds the termination to the intention of the parties (as if the court would only state what the parties had wanted). In subjective sense, the theory has some problems. The parties often may not have had any common view on the subject, (or any individual view, for that matter).[299] And as the frustrating event is to be unforeseeable, how could they have had any intentions concerning it?[300] The objective version of the theory is that it is not the intention of the actual parties but of "reasonable men" which should be considered. This version takes the decision further away from the parties and starts to emphasise the role of the court.[301] It is also unclear how even reasonable men could have prepared themselves for an unforeseeable event and reached an agreement on it.[302]
Due to the mentioned and other such difficulties, some judges began to say that it was not the intention of the parties that was decisive, but it was the court who decided what is reasonable in the circumstances.[303] As one judge put it, "The court is exercising powers, when it decides that a contract is frustrated, in order to achieve a result which is just and reasonable."[304]
According to the next theory, when there is a contract which is dependent on the continued availability of a specific thing, and the thing becomes unavailable, the contract is prima facie discharged, because the foundation of the contract has disappeared.[305] It would seem to infer that the possibility of frustration is built in in the type of contracts for the performance of which the availability of some specific thing is essential. The difficulty with this theory is that it appears to apply to limited types of cases only.[306]
In the final theory, the frustration of a contract depends on the construed meaning of the contract. The abovementioned theories of an implied term, just solution and foundation of the contract seem to meet in this one. The true construction of the contract is what the decision is based on. According to Treitel, this would seem the most satisfactory explanation of the doctrine of frustration.[307]
Also Collins refers to construction of the contract as a basis for the application of the doctrine of frustration. According to him, though the courts might seem to be applying objective criteria to see whether or not the contract was frustrated, in practice, the decision depends upon the construction of the terms of the contract to discover what performance is required.[308] In Davis Contractors Ltd. v. Fareham U.D.C., Lord Radcliffe stated that "frustration occurs whenever the law recognises that, without default of either party, a contractual obligation has become incapable of being performed because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract. Non haec in foedera veni. It was not this that I promised to do."[309] If we accept this as the definition of the doctrine of frustration, we may conclude that interpretation and construction of the contract, to discover what was really required under it, would seem to be in a key position in defining whether or not performance has become impossible (or fundamentally altered).
5.6. Conclusions
The main difference between the doctrine of frustration and the force-majeure type of solutions to changed circumstances is that it directly affects the validity or the existence of the contract. Where performance as described by the contract has become impossible the contract may cease to exist. Force-majeure type of regulations would leave the contract in force, though it might be nothing but an empty shell, since the parties have become free from the obligations under it. The advantage of the force-majeure type of approach is that it makes it possible to address partial non-performance separately. Frustration terminates the contract as a whole and cases of partial impossibility may therefore prove difficult to solve (see for example 5.3.1.1. above).[310]
The Finnish Sale of Goods Act or the CISG do not affect the existence of the contract. However, in exceptional cases applying Contracts Act 36 § may lead to the discharge of the contract as a whole. In the UNIDROIT and EU Principles the hardship provisions may lead to the termination of the contract. In these cases, the court would seem to have more discretion than under the English law, where the court has to declare the contract frustrated whenever the doctrine of frustration applies.
There would seem to be some inconsistencies in the rules concerning frustration in cases of failure of a particular source and impossibility of the method of performance (see discussion in 5.3.1.5. above) though the commentators seem to ignore this, perhaps due to the different legal culture. Under Finnish law, the obligor would be under an obligation to try to overcome such difficulties by finding alternative sources or methods. However, the parties could restrict this obligation by defining the source or method more precisely in the contract. This may apply also cases of destruction of the goods. Under the Finnish Sale of Goods Act and the CISG the obligor might be under obligation to fulfil the contract through a substitute performance, and this would most likely apply to the studied Principles as well, while under English law, section 7 of the Sale of Goods Act 1979 (where applicable) and the general reluctance to order specific performance would probably lead to frustration or liability in damages instead.
Hardship would appear to have no effect in the English system. However, as has been noted in 5.3.1.3., in cases of temporary impossibility, the fact that performance has become significantly more difficult has sometimes been acknowledged. The important question would seem to be the question of what constitutes a fundamental change of circumstances (see 5.3.1.6. above). In the Finnish Sale of Goods Act, a hardship type of situation may be relevant where it leads to unreasonableness or unconscionability (cf. KL 23 and Contracts Act 36 §).
6. CONCLUSION
The
Roman
law
maxim
of
pacta
sunt
servanda
is
the
primary
rule
in
all
the
rules
discussed
in
this
paper.
There
are
two
ways
in
which
to
obey
the
contract,
which
can
also
be
perceived
as
the
criteria
of
a
binding
contract:
A
party
to
a
contract
must
either
specifically
perform
his
primary
obligations,
which
can
be
monetary
or
non-monetary,
or
to
pay
damages
for
the
breach
of
these
obligations.
The
civil
law
systems
have
traditionally
emphasised
performing
the
primary
obligations, while
in
the
common
law
damages
are
preferred.[311] Exemptions from these obligations modify the rule of pacta sunt servanda.
On the basis of the
studied
literature
and
as
also
witnessed
by
the
reviewed
legal
instruments,
there
would
seem
to
be
two
main
options
in
use
on
how
to
ease
up
the
strictness
of
the
contract
in
cases
of
changed
circumstances.
Both
of
these
provide
for
exemptions
from
the
contractual
obligations.
These
approaches
seem
to
have
evolved
mainly
in
the
19th and 20th centuries.
The
first
method
consists
of
rules
referring
to
(1)
impediments
that
exempt
from
performance, and
the
second
of
(2)
judicial
review.
Judicial
review
would
appear
to
have
developed
from
simply
discharging
the
contract
towards
adjustment,
which
would
seem
to
be
a
fairly
modern
feature
in
contract
law
and
to
emphasise
conscionability
or
fairness.
In
addition
to
the
two
approaches
mentioned
above,
it
is
suggested
on
the
basis
of
the
less
than
comprehensive
material
studied
that
a
third
option
has
started
to
evolve
in
the
20th century:
(3)
mandatory
renegotiations
backed
up
by
judicial
review.
This
approach
would
seem
to
emphasise
the
co-operation
based
nature
of
the
contract
and
the
obligations
of
loyalty
and
good
faith
of
the
contracting
parties.
The
ultima
ratio
of
this
approach
would
not
seem
to
be
to
apportion
the
risks
in
the
event
of
changed
circumstances
as
may
often
be
the
case
with
exempting
impediments,
but
to
allow
the
parties
to
continue
their
contractual
relationship.
The
approach
could
also
be
seen
as
an
attempt
to
guide
commercial
contract
practices
into
a
more
self-regulatory
direction.
The
Finnish
Sale
of
Goods
Act
and
the
CISG
apply
exempting
impediments.
Moreover,
the
Sale
of
Goods
Act
adds
elements
of
reasonableness
and
conscionability
into
the
discretion
on
remedies
for
breach
(cf.
e.g.
KL
23
no
obligation
to
perform
if
would
require
unreasonable
sacrifices,
KL
70.2
-
damages
may
be
adjusted
if
they
are
unconscionable).
Under
the
general
contract
law
in
Finland,
judicial
review
is
allowed
under
Contracts
Act
36
§
in
cases
of
unconscionability.
Contracts
Act
36
§
allows
both
adjusting
and
rescinding
the
contract.
The
UNIDROIT
and
the
EU
Principles
apply
exempting
impediments
as
well.
They
too
contain
references
to
reasonableness
(cf.
e.g.
UNIDROIT
Principles
Article
7.2.2,
EU
Principles
Article
9.102).
In addition, these Principles
allow
judicial
review
in
events
of
hardship.
This
can,
however,
only
occur
in
cases
where
the
parties
have
failed
to
renegotiate
the
terms
of
their
contract.
The
Principles
therefore
seem
to
apply
and
promote
the
new
third
approach
as
suggested
above.
This
feature
in
the
Principles
is
not
as
such
present
in
any
other
of
the
rules
discussed
in
this
paper.
As
mentioned,
it
can
be
seen
as
an
expression
of
the
principle
of
good
faith,
loyalty
or
co-operation
in
contract
law.
The
English
system
employs
judicial
review
in
managing
changed
circumstances.
Where
performance
has
become
impossible
or
where
the
party's
obligations
under
the
contract
have
been
radically
transformed
by
the
changed
circumstances,
the
contract
may
be
discharged
under
the
doctrine
of
frustration.
Traditionally, the court cannot,
however,
adjust
the
contract,
though
this
may
perhaps
be
done
in
cases
of
long
term
contracts
calling
for successive
performances.[312]
It
should
also
be
noted
that
the
English
law
is
continuously
evolving
through
common
law
as
presented
in
the
court
decisions
and
through
statutory
instruments.
A
complete
range
of
juristic
tools
to
manage
changed
circumstances
would
seem
to
consist
of
at
least
the
impossibility
and
force
majeure
type
of
rules
representing
exempting
impediments
and
the
possibility
of
judicial
review
representing
the
second
main
option
as
discussed
above.
These
tools
already
encompass
one
of
the
modern
features
of
contract
law
also
apparent
in
the
material
discussed
in
this
paper:
conscionability
or
fairness.
The
new
third
method
presented
above
would
seem
to
be
more
controversial.
It
could
be
questioned
whether
the
law
should
compel
the
parties
to
renegotiate
or
whether
this
would
be
better
left
to
the
parties
to
decide.
It
is
submitted
that
the
law
may
in
this
matter
follow
contract
practices
already
in use in international trade and that eventually in the future, as the concept of contract evolves, such an approach may seem only natural.[313] However, without more specific definition in the individual contract, an obligation to renegotiate (or co-operate in general) may provide for uncertainty: when has one performed such an obligation? The co-operation approach in legislation is, in any case, an interesting development and further studies would be warranted.
|
|||
| SGA: exempting circumstances - seller's obligations | SGA: - buyer's obligations | CISG: - seller's / buyer's | Exemption |
| 23 § 1. impediment - insurmountable 2. imbalance - sacrifices unreasonable in relation to buyer's benefit |
52 § 1. cancellation - goods procured or produced especially for the buyer - unless harm or danger of noncompensation to the seller |
Arts. 46/62 + 28 1. court's own law |
from performance in cases of delay |
| 34.1 § 1. unreasonable costs or unreasonable trouble |
Arts. 46 + 28 1. unreasonable - regard to all the circumstances 2. court's own law |
from the duty to repair | |
| 34.2 § 1. impediment or imbalance such as described in 23§ + significant importance to buyer + seller understood or ought to have understood this 2. existing, nonsubstitutable goods |
Arts. 46 + 28 1. not a fundamental breach of contract 2. court's own law |
from new delivery | |
| 53 § (cf. 23 §) 1. impediment - insurmountable 2. imbalance - sacrifices unreasonable in comparison to buyer's benefit |
Arts. 62 + 28 1. court's own law |
from contribution | |
| 27 § (cf. Art. 79) 1. impediment - beyond control - reasonably unforeseeable - reasonably unavoidable and insurmountable |
57.1 § 1. impediment - a provision of law, an interruption in public traffic or payment transactions or other such event - reasonably unforeseeable - reasonably unavoidable and insurmountable |
Art. 79 (cf. 27 §) 1. impediment - beyond control - reasonably unforeseeable - reasonably unavoidable and insurmountable |
from damages for late performance |
| 57.2 § (refers to 27 §) | Art. 79 | from damages for non-contribution | |
| 40 § (refers to 27 §) | Art. 79 | From damages for non-conformity of goods | |
FOOTNOTES
1. On classifying legal systems, see e.g. Husa, p. 123 onwards.
2. Another important country is Japan. Japan has adopted a German solution to impossibility. In short, foreseeable (this term has been used by the author, perceptible might be more accurate) initial impossibility renders the contract void whereas supervening impossibility leads to an exemption from the primary obligations and the remedies available to the other party are avoidance and damages. Kagayama, under Remedies for Breach Contract under the Civil Code.
3. English law here includes Wales as well. The Irish law also acknowledges the doctrine of frustration. Scottish law in turn broadly follows the common law. Lando & Beale, p. 146.
4. See e.g. Tallon, p. 573.
5. Tallon, p. 573-574.
6. Nystén-Haarala, p. 175-176. Hellner, p. 61. Ramberg (1989), p. 207. BGB 306-308 § (initial impossibility), 275, 279-282 § (supervening impossibility).
7. Hellner, p. 62.
8. Hellner, p. 62; Nystén-Haarala, p. 185. See also Ramberg (1989), p. 210.
9. Hellner, p. 63-64. See also Ramberg (1989), p. 214-215; Nystén-Haarala, p. 179. In Finnish law an example of termination for an important reason can be found in the law concerning partnerships (laki avoimesta yhtiöstä ja kommandiittiyhtiöstä 389/1988) 2:5.
10. Hellner, p. 65. See also Nystén-Haarala, p. 186-196; Ramberg (1989), p. 210-212.
11. Tallon, p. 574.
12. Vihma, p. 49-51. See also Godenhielm p. 38-40.
13. Vihma, p. 51 and 289.
14. Ibid., p. 289.
15. E.g. Treitel, p. 778-779.
16. As has also been speculated by Fuller & Eisenberg, Basic Contract Law, 3rd ed., p. 801, as cited by Treitel, p. 793.
17. Treitel, p. 793.
18. Vihma, p. 45-48.
19. The grounds of the Scandinavian views on impossibility would seem to be in the German doctrine of impossibility which emerged in the 19th century. Rules on impossibility still remain in the BGB though they have been criticised. According to Hellner for example, this doctrine should not have any effect on Swedish law any more. The same would seem to apply to Finland as well. See Hellner, p. 61.
20. There is also a rule of equity which provides that "the court does not compel a person to do what is impossible." Treitel (1994), p. 3, who refers to Forrer v. Nash (1865) 35 Beav. 167, 171.
21. Hellner, p. 64. Important here is also that the focus is not on the individual parties but the contract.
22. E.g. Vihma, p. 321; Godenhielm, p. 40.
23. See e.g. Atiyah (1995a), p. 229; Vihma, p. 322. Vihma (p. 60) states that English law usually does not distinguish initial impossibility from subsequent. This would seem to be incorrect at least judging by the materials used in this study (see e.g. Atiyah cited above).
24. E.g. Vihma, p. 322-325; Godenhielm, p. 40-44.
25. Vihma, p. 61-62 and 322.
26. See also 2.5. below
27. Godenhielm, p. 42.
28. Aurejärvi, p. 85.
29. See e.g. Hemmo II, p. 233; Nystén-Haarala, p. 184.
30. Vihma, p. 157.
31. Treitel (1994), p. 2.
32. Nicholas, p. 21, who uses the term strict liability.
33. Schmitthoff, p. 164. However, other preconditions are often required, such as unforeseeability.
34. Saarnilehto, p. 145.
35. Hellner, p. 59.
36. Mestad, p. 4-5 and 276.
37. Nicholas, p. 21.
38. Kozlow, under 9.1.
39. The wording in UNIDROIT Principles Art. 7.1.7(1) is almost identical to the wordings in the Finnish Sale of Goods Act 27.1 § and CISG Art. 79(1).
40. Lando & Beale, p. 115 and 141.
41. Case 266/84 (1987) 3 CMLR 202, p. 223 ((1986) ECR 149).E.g., C-335/87, ECR 1990, p. I-2875; Case 266/84, ECR 1986, p. 149.
42. E.g., Joined cases 98/83 and 230/83, ECR 1984, p. 3763; Joined cases 154, 205, 206, 226 to 228, 263 and 264/78, 39, 31, 83 and 85/79. ECR 1980, p. 907; Case 154/78, ECR 1980, p. 907.
43. E.g., Case 20/84, ECR 1985, p. 2061.
44. E.g., C-124/92, ECR 1993, p. I-5061; Case 296/86, ECR 1988, p. 1491; Case 70/86, ECR 1987, p. 3545; Case 224/83, ECR 1984, p. 2349; Case 284/82, ECR 1984, p. 557.
45. E.g., Case 158-73, ECR 1974, p. 101; Case 4-68, ECR 1968, p. 549.
46. See also Vihma, p. 290-293.
47. Nystén-Haarala, p. 184.
48. Adlercreutz, p. 139.
49. Swadling, p. 7.
50. E.g. Berg, p. 106.
51. E.g. Perillo. This is also a typical case of the Finnish "liikavaikeus," see 2.2. and 2.3. above and Hemmo I, p. 44.
52. Perillo.
53. Hellner, p. 73.
54. Tillotsson, p. 228. See also Furmston, p. 62.
55. Schmitthoff, p. 648. See also Hemmo II, p. 107.
56. Perillo. He also submits that it may be that the common law in the U.S. is also developing into that direction by using the term impracticability instead of impossibility.
57. These matters can usually be agreed upon by the parties. They may, for instance, assume the risk of some events or agree on the consequences of even minor changes in circumstances affecting their contract. They may also define e.g. the term force majeure in another way.
58. See e.g. Taxell (1972), p. 306; Taxell (1993), p. 210.
59. Though the Commentary to the UNIDROIT Principles, p. 146, states that hardship has been acknowledged by various legal systems under the guise of concepts such as frustration of purpose, Wegfall der Geschäftsgrundlage, imprévision, the Italian eccessiva onerosità sopravvenuta and so on. In broad terms, hardship could be defined simply by referring to a fundamental change in equilibrium of the contract.
60. See e.g. Ferrari. The Sale of Goods Act can be made applicable by an express reference. See also Ramberg, p. 53-56.
61. Routamo & Ramberg, p. 48.
62. E.g. Ramberg, p. 55.
63. On tensions between validity and excuses for non-performance under the CISG, see Weitzmann.
64. Routamo, p. 70.
65. HE 93/1986, p. 67-68.
66. Sevón, Wilhelmsson & Koskelo, p. 68-69.
67. Wilhelmsson, Sevón & Koskelo, p. 52.
68. HE 93/1086, p. 68.
69. Sevón, Wilhelmsson & Koskelo, p. 69 (Wilhelmsson, Sevón & Koskelo, p. 52).
70. E.g. Routamo, p. 69.
71. HE 93/1986, p. 68.
72. HE 93/1986, p. 69.
73. Wilhelmsson, Sevón & Koskelo, p. 52.
74. Sevón, Wilhelmsson & Koskelo, p. 71.
75. Ibid.
76. Routamo, p. 69.
77. HE 93/1986, p. 69-70.
78. HE 93/1986, p. 69. Sevón, Wilhelmsson & Koskelo, p. 72.
79. HE 93/1986, p. 85-86.
80. E.g. Sevón, Wilhelmsson & Koskelo, p. 120-121.
81. HE 93/1986, p. 86. Cf. Routamo's example, p. 69.
82. Sevón, Wilhelmsson & Koskelo, p. 122 (Wilhelmsson, Sevón & Koskelo, p. 101).
83. HE 93/1987, p. 87. Sevón, Wilhelmsson & Koskelo, p. 122-123.
84. See also Rudanko, p. 42; Sevón, Wilhelmsson & Koskelo, p. 169.
85. HE 93/1986, p. 104. See also Sevón, Wilhelmsson & Koskelo, p. 167.
86. Sevón, Wilhelmsson & Koskelo, p. 174.
87. Sevón, Wilhelmsson & Koskelo, p. 173 (Wilhelmsson, Sevón & Koskelo, p. 148-149).
88. HE 93/1986, p. 108.
89. This is also a factor that generally distinguishes liability in damages from liability for specific performance. Only events beyond the performing party's control can release him from liability in damages. E.g. Ämmälä (1999), p. 6.
90. E.g. Taxell 1993, p. 59, 77 and 90.
91. Wilhelmsson, Sevón & Koskelo, p. 77.
92. Sevón, Wilhelmsson & Koskelo, p. 82; HE 93/1986, p. 67; Routamo, p. 82-83.
93. See HE 93/1986, p. 76: KL 27 § refers only to the consequences of the impediment but avoiding or overcoming the impediment itself naturally prevents the consequences as well. Cf. CISG Art. 79(1).
94. HE 93/1986, p. 73 and 77.
95. HE 93/1986, p. 73-74.
96. Sevón, Wilhelmsson & Koskelo, p. 83; HE 93/1986, p. 74.
97. Sevón, Wilhelmsson & Koskelo, p. 82-83 (Wilhelmsson, Sevón & Koskelo, p. 63-64).
98. Routamo, p. 82.
99. Sevón, Wilhelmsson & Koskelo, p. 84-85; HE 93/1986, p. 74.
100. HE 93/1986, p. 75.
101. HE 93/1986, p. 76.
102. Sevón, Wilhelmsson & Koskelo, p. 86.
103. Sevón, Wilhelmsson & Koskelo, p. 86-87; HE 93/1986, p. 76-77.
104. Sevón, Wilhelmsson & Koskelo, p. 86-87; HE 93/1986, p. 76-77.
105. Koskelo, p. 300.
106. HE 93/1986, p. 77.
107. HE 93/1986, p. 77-78.
108. Sevón, p. 24; Koskelo, p. 305-306; Routamo & Ramberg, p. 223-225.
109. HE 93/1986, p. 77.
110. Routamo & Ramberg, p. 229.
111. Sevón, Wilhelmsson & Koskelo, p. 133-134; HE 93/1986, p. 91-92.
112. HE 93/86, p. 87.
113. Rudanko, p. 259.
114. Rudanko, p. 40; Sevón, Wilhelmsson & Koskelo, p. 164-165; HE 93/1986, p. 112.