Go to Database Directory || Go to Bibliography
Reproduced with permission of Pace Review of the Convention on Contracts for the International Sale of Goods, Kluwer (1999-2000) 79-192
I. Legislative History of Avoidance in International Sale of Goods
II. Remedy of Renouncement in the Polish Civil Code
III. The Buyer's Right to Avoid the Contract
IV. The Seller's Right to Avoid the Contract
VII. The General Provisions of the CISG and the Remedy of Avoidance
Introduction
"Pacta sunt servanda" is one of the commonly accepted principles in
international trade. Parties are obliged to perform a contract in a way that
complies to its terms, even if the performance becomes unfavourable for one
of the parties or excessively difficult. This is a basic rule of "lex mercatoria".
It ensures the safety of the trade turnover. Another principle, which results
from "pacta sunt servanda" substantiates that the characteristic performance
under the contract should be rendered "in natura". Thus, the debtor cannot --
without the consent of the creditor -- perform something different, from that
which was agreed to under the contract. He also cannot unilaterally terminate
the contract or render substitute performance by payment of a given sum of
money. This principle has been recognized in both the continental and
common law and it contributes to the safety and certainty of trade turnover.
Nowadays, the above principles do not have an absolute character. Their
scope is limited by exceptions, which are provided for by law; for example,
legal or physical impossibility of performance and unjust enrichment. The
right of a party to withdraw from the contract is contradictory to the principle
of sanctity of contracts. The foremost interest of the parties, at the time the
contract is concluded, is that it must be honored. However, it may happen that
despite the good faith with which the parties had upon entering into the
contract, it is nevertheless performed defectively or, in some instances not
performed at all. In such a situation, the party aggrieved by non-performance
is equipped in law with a battery of remedies. The most drastic remedy,
which reflects the gravity of the negative effects of non-performance or
performance not complying with the terms of contract, is avoidance.
The right to avoidance functions as a far-reaching sanction for non-performance under the 1980 United Nations Convention on Contracts for the
International Sale of Goods,[1] as well as under Polish law. It signals the
breakdown of the sales contract and excludes belated approximate
performance. The advantages of early avoidance are clearly justified under [page 81]
the Convention. Avoidance makes it possible for the aggrieved party to
clarify his situation by reselling or repurchasing the goods required by the
initial contract. The aggrieved party may not mind in such a detrimental
situation, whether the non-performing party changes his mind and fulfils the
contract. The aggrieved party is entitled to exercise the right vested in him
and claim damages if the compensation for damages provide adequate
protection.
Under Polish Law, the remedy vested in the party to a synallagmatic
contract is justified by the need for stronger protection of the aggrieved party,
by the character of this type of contract, and by the purpose of such contracts
- to stimulate economic turnover. The party who withdraws from the contract
with an unreliable trader may, by concluding another contract, attain his
purpose without forcing the party in default to perform by commencing a
legal action in a court or arbitral tribunal.
In the present dissertation I compare the remedy of avoidance under
the 1980 United Nations Convention on Contracts for the International Sale
of Goods with its counterpart remedy in the Polish Civil Code. The purpose
of the comparison is to ascertain possible concurrences and differences in the
regulation of the remedy of avoidance under a sale contract which include the
norms created as a result of international legislation with the regulation which
is contained in the norms of Polish national law.
Regarding terminology, I have had a little doubt about the choice of the
proper term denoting the Polish law counterpart of the remedy of avoidance
that is regulated under the Convention. I hesitated between the terms
"rescission" and "termination," as the meanings of the terms in the English language do not reflect the real
nature of the remedy under the Polish law. "Rescission" of the contract ab
initio is in principle retrospective, "termination" is not retrospective and may
be exercised when the party is guilty of breach of contract.[2] Under Polish law, the discussed remedy has a
retrospective effect and is, in principle, available when the party in breach is
liable for the circumstances which caused the non-performance or defective
performance of the contract. On the basis of the reasons mentioned above, I have chosen a third
alternative: for the purposes of this dissertation, I have adopted the term
"renouncement of the contract."
I focus attention on the questions: What are the legal grounds giving
rise to the right to avoidance? Is liability for breach of contract a necessary [page 82]
element? When and in what form can the right be exercised? What are the
restrictions imposed on the entitled right holder to limit the exercise of his
right? What situation will appear after the sale contract has been avoided?
The formal limits imposed on the dissertation have not allowed
discussion of other interesting problems inherently connected with the remedy
of avoidance, such as obligations of the parties to preserve the goods after the
right has been exercised or the methods for measuring damages in the case of avoidance.
The dissertation commences with an overview of the regulation of
avoidance under the 1964 Hague Convention relating to a Uniform Law on
International Sale [3] and the 1978 Draft Convention on Contracts for the
International Sale of Goods.[4] This background allows us to ascertain changes
that took place with regard to the remedy of avoidance during its legislative
history. The final part of the work focuses on the influence of the general
provisions of the 1980 United Nations Convention on Contracts for the
International Sale of Goods on the remedy of avoidance of the sales contract
as regulated in the Convention's specific provisions.
I. Legislative History of Avoidance in International Sale of Goods
A. Problems concerning terminology
Starting with the considerations on avoidance it is necessary to
describe the concept and the terminology most often used in relation to it.
Avoidance is the legal remedy under contract law, which takes effect in
situations when a party to a contract aggrieved as a result of not obtaining the
performance for which he bargained, wishes to put an end to further [page 83]
performance of the contract and to put matters into the position, as far as it is
possible, in which they were before performance by the other party had
begun.[5]
Generally speaking, there are three courses of actions open to a party that
suffers from the other party's failure to perform a contract. Other remedies,
such as the claim for specific relief, that is, actual performance of the
defaulting party's undertaking, and a claim for substitutionary relief, usually
meaning monetary compensation for not having received the promised
performance are also available to an aggrieved party.[6] These forms of relief
are recognized by all legal systems.[7] They can be combined in various ways
and the form of monetary relief can be given in conjunction with either a
requirement of performance of the contract or its avoidance.
The effect of avoidance may be reached by different mechanisms in various
legal systems. The consequence of this is a different terminology used.
Common law uses the terms "rescission of a contract," "repudiation,"
"cancellation," "termination" and "rejection of the goods."[8] The Polish Civil Code [9] uses the term "to renounce a
contract."[10] The 1964 Hague Convention relating to a Uniform Law on
International Sale [11] and the 1980 United Nations Convention on Contracts for
the International Sale of Goods [12] adopts the term "to avoid a contract." "Avoidance" under the
Vienna Convention denotes an early end to the contract [13] and comprises
national [page 84] concepts of rescission as well as termination.[14] "Avoidance of the
contract" is an example of a term used in the Convention whose wording or
expression in other languages does not always have the same definite legal
significance attributed to it.[15] Such terms are non-technical in a legal sense and
become legal terms by the Convention only. The question of terminology, is
closely connected to the problem of which interpretation should be applied
under the Convention. The interpretation of the terminology used should be
based on its contents, having regard to the international character of the
Convention,[16] without referring to the meaning of the terms in national legal
systems.[17] The precise and detailed legal significance of terms such as
"avoidance" will be defined autonomously [18] in the process of the application [page 85]
under the Convention, taking into account the context and function they have.
Such a compromise [19] on terminology accepted by the legislators during the
Vienna Conference,[20] including the term "avoidance", emphasizes a very
special function of the Convention and a goal to be achieved through its
provisions -- to replace diverse domestic rules with uniform international law.
B. Avoidance under the 1964 Convention on the International Sale of Goods
The remedy of avoidance was already contained in the 1964 Hague
Convention relating to a Uniform Law on International Sales (ULIS). The
ULIS provisions on avoidance are spread among many articles.[21] The system
adopted in the 1964 Hague Convention differs from the 1980 Vienna
Convention.
Avoidance under the ULIS was in principle justified for a fundamental
breach of contract.[22] The regulation provided for two forms of avoiding the
contract: 1) avoidance declared by the buyer; and 2) ipso facto avoidance.[page 86]
The right to declare a contract avoided could be exercised by the aggrieved
party when the breach of the contract was fundamental [23] as well as when it was
not fundamental.[24] It depended on the will of the injured party.
Ipso facto avoidance was automatic by virtue of law.[25] It followed a
fundamental breach of the contract when:[26]
(a) the seller failed to deliver goods at the date fixed and the buyer did
not inform the seller of his decision to require performance within a
reasonable time;[27] or when the failure referred to a fixed place of
delivery;[28] or, in case of delay in seller's performance - when he did
not deliver within an additional time notified by the buyer;[29]
(b) when the buyer failed to pay the price at the date fixed.[30]
In these cases ipso facto avoidance took place without any preliminary
formal steps and it was not at the option of the aggrieved party. As opposed
to the provisions under the ULIS for the instances wherein the defaulting
party did not perform at all, the provisions which concerned cases in which
the seller performed defectively, (late delivery [31] or delivery of non-conforming
goods)[32] authorized the aggrieved party to avoid the contract by a declaration.
When the breach was not fundamental, the aggrieved party could give
a notice requiring performance and stating an additional period of time.[page 87]
Failure to perform at the end of the period so fixed might result in: (a) ipso
facto avoidance if the seller did not perform at all;[33] or (b) avoidance by declaration of the aggrieved party if it was
a seller performing defectively [34] or a buyer failing to pay the price.[35] The
prerequisite to avoidance in the case of delivery of non-conforming goods
under the ULIS was an obligation imposed on the buyer to give a notice of
non-conformity.[36]
In cases of partial default in which the performance was rendered not
in accordance with the contract as to the required quantity or quality of
goods, ULIS allowed partial avoidance.[37] Avoidance of the whole contract
could take place when the defect in performance constituted a fundamental
breach of the contract as a whole.[38]
The meaning of avoidance under the ULIS was defined under article
78, that stated its effect. In principle, neither party could claim performance
from the other [39] however, the right to claim damages still remained at the
aggrieved party's disposal. Moreover, each party might require the other party
to return whatever he had supplied or paid prior to the avoidance of the
contract. In addition, the buyer had to account to the seller for all benefits
derived from the goods and the seller had to pay interest on the price.[40]
The function of the institution of ipso facto avoidance, as it was
underlined in the legal doctrine,[41] was to fix at an early date the time with
reference to which damages were to be assessed - usually occurred at the [page 88]
time of avoidance under ULIS.[42] Ipso facto avoidance also functioned as a means to force or encourage the buyer to make an
election between two remedies,[43] accessible to him by virtue of the ULIS
article 26(1), and to exclude, in this way, the buyer's claim for specific
performance when he did not inform the seller of his decision as to which of
the remedies he had chosen. This protected the defaulting party against the
burden of being ordered to make specific performance after a long delay,
especially when the prices of the goods fluctuated.[44] Such a regulation could
thus place the defaulting party in a better position in cases of fundamental
rather than of non-fundamental breach.[45]
Fault was not mentioned in the ULIS as a requirement of the remedy of
avoidance.[46] However, in cases of excused non-performance [47] although the
provisions of the ULIS protected the party who has not performed from
liability for damages, they did not take away from the aggrieved party the
possibility to avoid the contract if other provisions of ULIS gave grounds for
it.[48]
The regulation of avoidance contained in the ULIS was frequently criticized
in legal literature as evincing complexity [49] and entailing some uncertainty [50] over
the fate of the contract. This was particularly true when the contract was
avoided,[51] thereby creating the danger that the party could be [page 89]
unaware that certain conduct of the other (or lack of conduct) party justifies avoidance of
the contract by law. This could, for example, make salvaging and re-disposing
of rejected goods complicated for the seller when the goods have left his
custody, thus contributing to the waste of resources.
ULIS adopted a rule that avoidance in case of non-conformity and non-delivery at the date fixed was allowed only if such a defect in performance
constituted a fundamental breach of the contract. In all other situations of
non-performance of the seller's obligations, the buyer had to fix an additional
period of time and wait for the remedy of automatic avoidance after the
additional time expired. As immediate avoidance was an exception under this
rule, the remedy seemed to be a slow remedy.[52]
Ipso facto avoidance under the ULIS was broad in its scope. First,
under article 25, (the right to require specific performance),[53] where the
contract would be automatically avoided for a fundamental or even a non-fundamental breach, if it was in conformity with customary trade usage and it
was reasonably possible for the buyer to purchase goods to replace those to
which the contract related, since this option was often taken by traders.[54]
Second, the buyer could transform any insignificant breach of contract into a
fundamental breach by fixing an additional period of time for performance
and thereafter release himself from the contract, especially when the prices on
the market fell.[55] Ipso facto avoidance under ULIS was a remedy of a
subsidiary character for a fundamental breach of the contract (with the
exception of article 25 and article 61). This character evinced in cases where
the injured party failed to choose from remedies available to [page 90] him upon other
party's fundamental breach within a reasonable time [56] or failed to comply
promptly with the request of the breaching party to inform about the choice of
the remedy despite the fact that such request was made.[57]
The concept of ipso facto avoidance was abstract and very
controversial,[58] arousing debate [59] over the question if the effect of this remedy
could be achieved through regulation, which would adopt avoidance based
only on an explicit declaration by the party, according to his wish and specific
interest.
C. Avoidance under the 1978 Draft Convention on Contracts for the International Sale
of Goods
The 1964 Hague Convention relating to a Uniform Law on the
International Sale of Goods together with the second 1964 Hague Convention
relating to a Uniform Law on the Formation of Contracts for the International
Sale of Goods, did not receive widespread acceptance. There were many
different reasons for this.[60] One reason was the fact that ULIS contained
abstract and complex concepts, which could constitute a basis for ambiguity
and error and could be easily misunderstood by traders. Ipso facto avoidance
is a prime example.[61] The result of works undertaken by the United Nations
Commission on International Trade Law was the Draft Convention on
Contracts for International Sale of Goods.[62] It was [page 91] unanimously approved on
16 June 1978 by UNCITRAL. The text of the 1978 Draft Convention
involved structural changes for clarity, simplicity and practicality in order to
win approval of the States.
Under the 1978 Draft Convention avoidance occurred only by
declaration. The concept of ipso facto avoidance was eliminated. The
formulation that a declaration of avoidance must be communicated by "notice
to the other party" in order to become effective in all cases of avoidance, was
inserted in a general provision of article 24 of the 1978 Draft.
Under the 1978 Draft, as under ULIS, a party might declare the contract
avoided if the other party committed a fundamental breach of contract or
failed to fulfill his obligations within a reasonable time.[63] The definition of
fundamental breach however was changed under the Draft.[64] Additionally, the
provision that failure to deliver the goods at the date fixed is a fundamental
breach if the price of the goods is quoted on a market, where the buyer can
obtain them, was not included in the Draft, although present under ULIS.[65]
As far as effects of avoidance are concerned, the principles expressed in
ULIS were maintained in the 1978 Draft.[66] Avoidance of the contract released
the parties from their obligations under the contract, subject to any damages
that might be due. However, it was stressed in the 1978 Draft [67] that avoidance
did not affect any provisions of the contract regarding settlement of disputes
or the rights and obligations of the parties if the contract was avoided. This
provision did not exist in ULIS. The Draft [68] and ULIS [69] stated the same reason
that could justify the loss of the buyer's right to avoidance: where it was
impossible for him to make restitution of the goods in the condition in which
he received them. However, even in such a situation, the buyer could still
exercise his right in the cases enumerated in both regulations.[70] Although both
regulations were concurrent on that point, ULIS did [page 92] not give the buyer a
possibility to require delivery of substitute goods while the Draft did.[71]
Provisions in both regulations [72] clearly stated that even if the right to declare
the contract avoided was lost by the buyer, he still retained all other remedies
at his disposal. Provisions of the 1978 Draft [73] as well as ULIS [74] laid down the
rule that when restitution was to be made, the party had to return that which
was received in course of performance of the contract and to account to the
other party for all benefits.
In general, the provisions of the 1978 Draft Convention dealing with
the remedy of avoidance correspond to the concept of ULIS, however they
took into account practical needs of trade.[75] The Draft Convention formed the
basis of the 1980 UN Sales Convention. The provisions of the Draft on
avoidance were in their majority substantively identical to the final version of
the regulation on avoidance adopted during the Vienna Conference in 1980.
The difference occurred in wording of some provisions and in numbering of
the articles. Some minor, legislative changes took place.
II. Remedy of Renouncement in the Polish Civil Code
The remedy of renouncement in the Polish Civil Code is one of the
remedies available to the aggrieved party under the regime of contractual
liability of a party for non-performance of the contract. Provisions concerning
renouncement are included in the several articles of Book III on obligations, in its Title VII regulating the
performance of obligations and effects of their non-performance. The right is
referred to mainly in section II on effects of non-performance of obligations in
article 477, and in section III dealing with performance and effects of non-performance of obligations in [page 93] synallagmatic contracts in articles 491-495.
Particular regulations on renouncement are also included as one of the named
agreements in special provisions relating to a contract of sale, which concern
warranty and guarantee liability of a seller in articles 560, 562, and 566.
Performance of synallagmatic contracts,[76] because of their special
character in relation to the performance of contracts in general, are regulated
in a particular way. Provisions in which renouncement is included constitute
lex specialis towards provisions concerning the performance of contracts in
general. However, article 487, paragraph 1 states that questions not answered
in lex specialis should be solved in accordance with the latter. The right to
renounce a contract is an exception to the principle of "pacta sunt servanda,"
according to which parties who have concluded a contract are bound by it and
cannot cease to perform without consent of the other [77] under Polish legal
doctrine.[78] A legally binding contract cannot be terminated by a unilateral
decision of a party via renouncement, unless this right is vested in him by the
law.
As a statutory right, it is allowed in the rare cases mentioned above,
when the defect in performance is due to the delay caused by the party, or in
the cases of impossibility of performance. In addition, as provided in article
395, paragraph 1, the parties may stipulate at the moment of the conclusion of
the contract, or after its conclusion, that one or both of them may be entitled
to unilateral renouncement of the contract within a defined period of time.[79]
Insertion of such a stipulation in the contract impairs the legal relationship
resulting from it and introduces doubt as to whether the contract will be
maintained. The limitation on these disadvantageous [page 94] consequences is the
period of time the parties have to define during which the right can be
exercised.
The right to stipulate in the contract that either of the parties may unilaterally
renounce a contract by paying a given amount of money is the special type of
the contractual right to renouncement provided for in article 396 CC. Such a
clause decreases to some extent, the impairment of the legal relationship
ensuing from the plain stipulation of renouncement, because it imposes on the
party availing himself of this right the duty to pay the money at the moment of
renouncement.[80] The money paid is considered to be compensation for the
contract not having materialized.[81]
Parties are also allowed to take advantage of the lex commissoria and
stipulate in the contract that a party may renounce the contract if the other
party does not perform or performs improperly. This right is usually foreseen
in cases of non-performance of the contract at the date fixed,[82] however, it can be a remedy for all cases of
non-performance or defective performance irrespective of the reason causing
it.[83] The right to renouncement provided for in the CC, as well as the right
stipulated in the agreement must always be exercised in the form of a
declaration communicated to the other party.
Having written this brief summary of the remedy of renouncement
adopted in the Polish CC, I will discuss the regulation in more detail while
making analysis of the provisions on avoidance included in the Vienna
Convention on the International Sale of Goods.
III. The Buyer's Right to Avoid the Contract
The remedy of avoidance is one of the listed remedies available to the
buyer when the seller breaches the contract under article 45 of the Vienna
Convention.[page 95]
A. Grounds for avoidance by the buyer
1. Grounds for avoidance under the Vienna Convention
The grounds for avoidance are provided in article 49(1) of the Vienna
Convention. The buyer may exercise his right in two different situations; (a)
when the seller fails to perform any of his obligations under the contract and
the Convention, and the failure constitutes a fundamental breach of the
contract; or (b) in the case of non-delivery, if the seller does not deliver the
goods within an additional period of time fixed by a buyer's notice made in
compliance with article 47 of the Convention or where the seller declares that
he will not deliver within the fixed period. These are the specific conditions
under which the buyer has the right to avoid a contract. If they are fulfilled,
the buyer can declare the contract avoided, however, he does not have to do
this. He may wish to insist on performance of the contract as provided for in
article 46 of the Convention.
Article 49 refers to situations where the failure to perform by the seller
concerns the contract as a whole. However, when in performance of the
contract, the seller delivers only a part of the goods or it appears that only
part of the goods are in conformity with the contract, the buyer may, if the
conditions included in article 49 are met, avoid the contract with respect to
that missing or non-conforming part. This principle is stated in article 51(1) of
the Convention.[84] Paragraph 2 of this article clearly provides that in cases of
partial performance, the buyer may declare the contract avoided in its
entirety, only if the seller, by making incomplete delivery or by delivering
goods that do not conform with the contract, commits a fundamental breach
which causes a substantial detriment to the buyer with respect to [page 96] the whole
contract. Paragraph 2 of article 51 constitutes an exception to the general rule
included in paragraph 1 of this article.[85] Such a function can be induced from
the use of the word "only" in the provision. If the delivery of goods in
excessive quantity, foreseen by the Convention in article 52(2) constitutes
substantial burden for the buyer, this amounts to a fundamental breach of
contract and may entitle him to avoid the whole contract.[86] Thus, article 52(2)
makes it legally possible for the buyer to reject the goods delivered in
excessive quantity.
2. Other situations
The Convention, under article 72, provides the buyer with the
possibility to avoid the contract if it is clear, prior to the date of performance,
that the seller will commit a fundamental breach of contract. The buyer can
declare avoidance before the performance is due; however, he should refrain
from exercising this right, if the seller gives adequate assurance of his
performance, unless the seller declares that he will not perform. A high
degree of certainty about occurrence of the breach and its fundamental
character is required. This certainty will arise when the seller resells to a third
party the goods he was to deliver to the buyer, or when he sells machines
necessary for the production of goods contracted for by the buyer,[87] or in the
case of seller's insolvency and initiation of bankruptcy proceeding.[88] When a
deficiency in the seller's ability to perform, usually a deficiency in his
creditworthiness, becomes so serious that it is clear that a fundamental breach
of contract will be committed, the buyer also will have grounds for avoidance.[89]
The buyer is not required to be absolutely certain about the grounds for
avoidance because adequate assurance of the performance may be given by
the seller. However, the buyer should act prudently in this situation under
article 72 since his avoidance without the ground for his action[page 97] may result in
his fundamental breach of the contract committed subsequently.[90] The notice of
the buyer demanding that the seller provide adequate assurance of the
performance, as article 72(2) allows in such a case, seems to be the best
solution to relieve the buyer from doubts about occurrence of the seller's
breach and reduces the risk the buyer would otherwise be taking. Legal
doctrine however, differs on the question if the refusal of the party to provide
assurance makes it clear that the breach will occur.[91] Despite the absence of the
uniform treatment of this question, the seller's adequate assurance of
performance will be the signal for the buyer that he has to proceed with his
own performance.
When the contract provides for the delivery of goods by installments, the
Vienna Convention makes it possible for the buyer, according to article 73:
(a) to avoid the contract with respect to a given installment when the seller
committed a fundamental breach of contract concerning this installment;
b) to declare the contract avoided with respect to future installments if an
actual breach of contract, even a simple one [92] which has already occurred,
gives the buyer good grounds to conclude that a fundamental breach of
contract may befall as far as future installments are concerned. In this
situation, the buyer cannot avoid the contract regarding installments already
delivered because the breach of contract concerning them is not fundamental.
The impairment of the creditworthiness of the seller and his declaration of
intentional non-performance do not constitute sufficient grounds for avoidance by the buyer;[93]
c) to declare the contract avoided with respect to deliveries already
made or to future deliveries while declaring it avoided as regards [page 98] present
deliveries, if by reason of their interdependence, these deliveries could not be
used for the purpose contemplated by the parties at the time of the conclusion
of the contract. The seller's awareness of the interdependence of the deliveries
is important in this case. The buyer should inform the seller about the purpose
of the deliveries resulting in their interdependence and the right time for this
is the moment of the conclusion of the contract. Due to this, the seller will
know that the defective or failed performance makes past or future
installments worthless and that the contract can be avoided. The parties must
know about each other's interest in complete performance.
As mentioned above, the Convention entitles the buyer to avoid the contract
when it provides for the installment of goods which are usable or resalable
independently of the other installments and when individual installments
constitute an integrated entirety.
Article 73 enables the buyer to avoid a given installment. However, it may
under certain circumstances, lead to avoidance of a contract as a whole,[94]
especially when under the principle in paragraph (3), the breach affects only a
part of the contract directly, but has an impact on the performance of the
entire contract.[95]
The goods for delivery by installments do not have to be similar in
every installment [96] to make avoidance possible. The contract may provide for
deliveries of different goods or partial deliveries [97] in a given installment. The
contract also does not have to provide for fixed dates of deliveries; what is
more, agreement may be reached on deliveries called for when they are
necessary.
Application of article 73 may concur with article 51 (read in conjunction with
article 49) which provides a buyer with a right to avoid a part of a contract and such a part
could be an installment. Then the buyer has a choice between article 51 and article 73 of
the Convention.[98] The provision included in article 73 is intended specifically for installment deliveries and [page 99] for avoidance not only of the installment with respect to which a breach has occurred but also future and interdependent installments. However, under article 73(1) the
breach must be fundamental as far as the failed installment is concerned; whereas under
article 51, the buyer is allowed to fix an additional period of time to enable the seller to
perform his obligations.[99] If the seller does not effect such a partial delivery within the
period so set, the buyer is free to avoid the contract as regards this installment,
irrespective of whether the failure constitutes a fundamental breach of the part of the
contract in question. So, by acting under article 51 the buyer will not have to ascertain if
the breach has been fundamental.
The buyer is not deprived of the right to avoidance of the contract where the risk
of accidental loss or damage to the goods during transport has passed to him in a manner
regulated under articles 67, 68, and 69 of the CISG.[100] Article 70 of the Convention
does not exclude such avoidance when the seller has committed a fundamental breach.
When non-conforming goods are delivered and the non-conformity constitutes a
fundamental deficiency, the buyer can require the avoidance of the whole contract, even
when the defective goods accidentally perished or are damaged after passage of the risk.[101]
In light of article 70, the contract can be avoided if the delay constitutes a
fundamental breach of contract, as it is provided in article 49(1)(a), after the goods have
been delivered. The destruction or damage of the goods after the passing of the risk does
not exclude the buyer's right to avoidance. When the seller delivers only after the
expiration of an additional period set by the buyer, according to article 49(1)(b), the
contract can be avoided without a fundamental breach of contract having been committed.[102]
The possibility given by the Convention to avoid the contract where the goods perished or
are damaged by accident after the passing of the risk may stongly tempt the buyer to avail
himself of this remedy. However, to prevent the abuse of his right, it will have to be
carefully examined, [page 100] if a fundamental breach of contract already existed before the event
took place, in order to ascertain whether he could have claimed avoidance at that moment.[103]
Pursuant to article 79(5), the claim to avoid the contract is not eliminated [104] in
situations which are regulated in the Convention under the section titled "Exemptions," if
other provisions of the Convention give rise to it. When the failure to perform was due
to an impediment beyond the seller's control and he could not reasonably be expected to
have taken the impediment into account at the time of conclusion of the contract or to
have avoided or overcome it or its consequences after the conclusion of the contract, he is
not liable for damages. However, the exemption from liability is confined only to damages
and the right to avoidance remains unimpaired, justified above all when there is a
fundamental breach ascribed to the seller. Under this regulation the objective character of
breach of contract is not affected by the presence of impediments which exempt the
breaching party from only certain legal consequences, leaving others untouched.[105]
3. Grounds for renouncement in Polish Law
The remedy of renouncement may be exercised when one of the parties is in delay
due to the circumstances for which the party is liable.[106] This [page 101] is one of the particular cases of
non-performance or defective performance of synallagmatic contracts regulated within the
general regime of contractual liability for non-performance or defective performance of
obligations.
The case where the performance was not fulfilled at the time it was due falls under
performance not complying to the contractual requirements concerning the time for it. The
performance is assumed to be possible, but not rendered on time when it was expected
under the terms of the contract. The aggrieved party may, according to article 491,
paragraph 1 CC, renounce the contract after setting additional, adequate time for the party
in delay along with a stipulation that after the inefficient expiration of this time, he will be
authorized to renounce the contract. However, pursuant to article 492, second sentence,
the aggrieved party may renounce the contract without setting an additional period of time
when performance after the original time set in the contract does not have any significance
for the aggrieved party, either because of the nature of the obligation or the intended
purpose of the contract which was known to the party who delayed.[107] The same applies
when, under the contract, the performance is to be made at a date fixed and the parties
stipulated the remedy of renouncement in a case of non-performance.[108]
[page 102]
Article 491, paragraph 2 CC regulates the remedy of renouncement when the party
fulfills his obligations only in part, or the performance of both parties under the contract is
divisible. When one of the parties is in delay to part of the performance, the other party
has an option. He may, according to his choice, renounce the contract with respect to this
relevant part of the contract, or to this part as well as the part that is to be performed in
the future. The aggrieved party may renounce the whole contract only when the partial
performance does not have any significance for him due to the nature of the obligation or
the intended purpose of the contract, which was known to the party in delay. The rules for
setting an additional period of time with the exceptions mentioned above, as provided in
article 492, are applicable in this case.
Another situation, where the grounds for renouncement may arise, is impossibility of
performance.[109] Besides delay this is another case of non-performance, which is regulated in
detail in the CC. The impossibility must be permanent, otherwise when it ceases to exist
and the performance can be made, the situation is treated as delay in performance.[110] When
the impossibility is caused by circumstances for which one of the parties is liable, the
aggrieved party may under article 493 CC, at his choice, either renounce the contract or
claim damages based upon general contract liability principles. The claim may also be
accompanied by a demand for a substitute performance. If he chooses renouncement, he
may also assert a claim for damages which he suffered with regard to the non-performance
of contract. This applies even if the performance of the part of the contract cannot be
rendered with regard to that part on grounds of the impossibility. However, if performance
of another part does not have any significance to the aggrieved party because of the nature
of the obligation or its purpose, which was known to the party in breach, the aggrieved
party may renounce the whole contract.[page 103]
Under the regulation of article 495, paragraph 1 CC, the impossibility of
performance by one party, in circumstances where neither the parties is liable has an
impact on the situation of both parties.They are released from obligation to perform. If
the performance of one party has already been rendered, he may claim restitution of what
he has performed in accordance with the provisions on unjust enrichment. Then the whole
contract is terminated. However, the aggrieved party may demand substitute performance
from the party whose performance has become impossible. When the performance is only
partially impossible, the rule in article 495, paragraph 2, allows for the reduction of
reciprocal performance. The aggrieved party may, nonetheless, renounce the whole
contract, if partial performance is of no significance to him due to the nature of the
obligation or the intended purpose of the contract, known to the party whose performance
has become partially impossible.
Additionally, other grounds concerning exclusively the buyer's right to renounce the
contract are provided in the regulation of the sales contract in the CC. Under the CC, the
buyer's right to renouncement results from the seller's warranty liability for physical [111] and
legal defects [112] of goods. Under article 560 CC, the buyer may renounce the contract if the
goods have defects and the seller does not exchange, without delay, these goods for
conforming goods, or does not remove the defects. The buyer is authorized by article 561,
paragraph 2 CC to exercise his remedy of renouncement if the contract of sale concerns
specific goods and the seller who is a producer of the goods, has not repaired them within
the additional time set by the buyer for repair. However, the buyer is free to renounce the
contract without setting additional time for repair.[113] The seller on his part, may refuse to repair [page 104] if it involves high costs.[114] If the goods, according to the sales contract, are to be
delivered in parts and the seller has not delivered conforming goods due to the buyer's
demand, the buyer may under article 562 renounce the contract with regard also to the
parts which are to be delivered in future.
B. Fundamental breach of contract
1. Regulation under the Vienna Convention
As mentioned, fundamental breach of contract is one of the decisive prerequisites
for the buyer's right to avoidance. It is indispensable to get closer to the meaning of the
term in order to understand properly the mechanism of avoidance under the Vienna
Convention.
The notion of breach of contract under the CISG comprises any non-fulfillment of
contractual obligations originating in the contract between the parties, in the Convention,
established practices and usages. A breach of contract constitutes an objective fact
irrespective of whether the party who commits the breach is at fault or not.[115] Fault is not
mentioned as a requirement of any remedy in the Convention,[116] including the remedy of
avoidance. This is true whether avoidance is as a result of non-payment, non-delivery of
generic goods, or if the goods are defective. Furthermore, as for the defects themselves,
the Convention does not distinguish between liability for breach of contract and guarantee
liability. On the other hand, the party may be exempted from certain consequences of
failure to perform his obligations, if, for example he has not been able to prevent the
breach, and the breach is caused by the conduct of the other party. The objective character
of the breach of contract is visible in cases of anticipatory breach when avoidance may be
exercised, irrespective of whether the performance is prevented by objective circumstances [117]
or whether anticipated non-performance by the seller is intentional.[118]
[page 105]
The Convention distinguishes between fundamental breach of contract and other breaches
of contract in article 25 and links a fundamental breach with more severe consequences
than those associated with an ordinary breach of contract. Article 25 of the Convention
defines fundamental breach as one that results in such detriment to the other party so as to
substantially deprive him of what he is entitled to expect under the contract, unless the
party in breach did not foresee and a reasonable person of the same kind in the same
circumstances would not have foreseen such a result. The fundamental breach is
characterized by reference to the results of the breach.
An important element in the definition is the degree of seriousness of the detriment
resulting from the breach; it must be such as to deprive the buyer of what the contract
entitles him to expect.[119] It should be considered as having quantitative as well as qualitative
meaning.[120] The substantiality of the detriment will be considered in each case on the basis of
such circumstances as the monetary value of the contract, the monetary harm caused by
the breach, or the extent to which the breach influences other activities of the injured
party.[121]
The aim of defining the term "fundamental breach" is to classify the situation
wherein the injured party, the buyer, has no further interest in the performance of the
contract because the purpose for the contract no longer exists,[122] and to allow the buyer to take advantage of avoidance (among [page 106] other remedies) put at his disposal by the
Convention.[123] The interest of the buyer will be defined according to the terms of the given
contract, which may state that the time of delivery, the conformity of goods, the
packaging or insurance of the goods, is of special interest to the buyer.[124]
Representatives of the legal doctrine of avoidance consider other cases where the
breach may appear to be fundamental. For instance, in cases where the delivered goods
are non-conforming, that is, they are not fit for their intended use [125] and are not reparable; or
the goods are not free from claims of a third party; or claims based upon industrial or
other intellectual property, if these claims are not removed and impede buyer's use of the
goods.[126]
According to article 49(1)(a), the fundamental breach is the test for immediate avoidance
of the contract in all cases, irrespective of when it [page 107] takes place,[127] before or after the
acceptance of the goods by the buyer.[128] However, in order to give basis for avoidance, it
must be undoubtful. Sometimes, a fundamental breach of contract may become obvious
when it persists. Then, time may constitute a decisive element as its lapse may convert a
non-fundamental (simple) breach of contract into a fundamental breach. For example, in
the case of a delivery of non-conforming goods which have a reparable lack of conformity.
If the time for delivery has been essential in a contract, such a reparable lack of conformity
will be considered a fundamental breach of contract. If this is not the case, a non-conforming delivery can become a fundamental breach when the lack of conformity is not
repaired. Delivery of an aliud may entail a right to require performance and if such a
further delivery is a violation of the time for performance, it can be characterized as a
fundamental breach.[129] In the case of partial delivery of the goods, a fundamental breach is
necessary to avoid the contract as to the part of the goods that do not conform to the
contract. However, if such a failure in delivery causes a substantial detriment to the buyer
and it concerns the entire contract, he may, according to article 51, avoid the whole
contract. A close examination of the facts of the case in relation to the function of the
remedy of avoidance is necessary in order to justify its exercise in this situation.[130]
[page 108]
The estimation whether the failure to perform a part of an installment contract constitutes
a fundamental breach of contract will have to take place with respect to a given installment
first. On the basis of the contractual terms, as a whole conclusions can be drawn for future
and earlier installments.[131]
The onus of proof is vested in the party in breach, the seller. If he shows that he
did not foresee and that a reasonable person in the same circumstances would not have
foreseen such a detrimental result, he can relieve himself from the serious consequences of his breach. These two premises: lack of anticipation by the seller of the
substantial detriment caused and lack of anticipation by a reasonable person in the same
circumstances, must be proved at the same time. The test of a reasonable person is an
objective [132] element in the definition of a fundamental breach. The time in which the seller
should have foreseen the detrimental consequences to the buyer is not indicated in the
definition provided in article 25. Legal doctrine asserts that it is the moment of the
conclusion of the contract [133] or the time until the moment of the breach.[134]
2. Regulation in Polish Law
The remedy of renouncement based on the grounds indicated in the Polish CC may
be available to the aggrieved party both if the non-performance has resulted from the
circumstances for which the party in breach is liable, and circumstances for which he is not
liable. The remedy is also available within the scope of the warranty liability of the seller.
According to the general principle provided for in article 471 CC, the debtor is
obliged to redress damages resulting from non-performance or defective performance
under the contract, unless the non-performance or defective performance results from
circumstances for which he is not liable.[page 109] The Code does not define the meaning of
"circumstances for which the party is liable" but it is accepted [135] that the notion embraces:
a) acts and omissions of the debtor based on his fault;
b) acts and omissions of persons who help the debtor perform the contract or who
are entrusted by him with the performance of the contract;[136]
c) acts and omissions of the statutory representative of the debtor;
d) events exceeding the scope of a)-c), which are defined by a statute;
e) events exceeding the scope of a) - c), which are defined by a contract according
to the principle of freedom of contract.
As far as the premise of fault is concerned, different grades of fault are considered
in light of the contractual liability.[137] However, the objective measure is included in
article 355 CC which lays down the rule that the debtor should evince the due care
commonly required in given types of legal obligations. This is the minimum for
which the debtor is liable. In the professional turnover this ceiling is increased.[138] The
parties may extend or narrow the scope of the debtor's liability in the contract
under article 473, paragraph 1, however, they are not allowed to exclude the
debtor's liability for damage caused by him intentionally. Such a stipulation would
be void. On the other hand, the debtor may accept an absolute liability of the
guarantee type. The onus of proof, according to the general evidence rule [139] under article 471, is
placed upon the creditor, who must prove the existence and extent of damage; the fact
that the damage resulted from non-performance or defective performance by the debtor;
and the causal nexus between the non-performance and the damage. The creditor is not
obliged to prove anything more. In particular, he is not obliged to prove that the non-performance or defective performance resulted from circumstances for [page 110] which the debtor is
liable.[140] The legal presumption adopted from the provision of article 471, is that the non-performance or defective performance is just the effect of these circumstances.[141] The debtor
should prove the opposite. If he does not indicate the reasons releasing him from the
liability, he will have to pay damages.
The adoption of such a presumption is based on the needs of turnover. The creditor
usually does not know, and often cannot know, what were the reasons that caused the
non-complying performance. Those reasons must or, at least, should be known to the
debtor. The practical effect of this is that if the cause of non-performance remains
unascertained, the debtor will have to redress the damage incurred by the creditor.
The warranty liability of the seller for physical or legal defects of the goods
foreseen under the Polish law is stricter than the liability based on general principles of
article 471 CC. The warranty liability is absolute in its character. It does not depend on
the fault of the seller or on an indication of a loss resulting from the delivery of defective
goods.[142] Moreover, the liability exists irrespective of the seller's knowledge of the defect,
because deceitful concealment of the defect by the seller increases his liability. The
warranty liability of the seller can be expanded, limited or excluded by the will of the
parties in a contract. Nonetheless, the exclusion or limitation of this liability is ineffective
if the seller has concealed the defect deceitfully.[143]
C. The seller's delay in performance
1. The seller's delay in performance under the Vienna Convention
When the seller is late with the performance of the contract [144] and the contract does
not have the character of a fixed-time contract, the buyer is not entitled to declare it
avoided immediately. First, he must proceed pursuant to the provisions of article 47(1).
He should send the seller a notice in [page 111] which he fixes an additional period of time of
reasonable length for performance by the seller of his obligations.[145] Such a notice is termed
Nachfrist, for it is related to a concept originating in the German legal system.[146] It
constitutes, on one hand, an assurance of the buyer's continuous interest in the fulfillment
of the contract [147] and, on the other hand, it is a warning about the possibility of its
avoidance after lapse of the time set. The notice must state clearly a given date or period
of time, otherwise it is not sufficient.[148]
The determination of the length of the period for performance has been left to the
discretion of the buyer, the aggrieved party, with the indication that the time must be
reasonable. It should be appropriate to the interests of the buyer in the performance of
the contract and the possibilities of the seller in realization of the delivery. The notice may
be communicated orally or in writing to the seller. According to article 27 of the CISG,
risk of its transmission is placed with the seller. Thus the buyer may avail himself of his
right after inefficient expiration of the Nachfrist, even when the seller has not received the
notice.[149]
The expiration of the additional period of time without delivery being effected
gives the buyer the right to declare the contract avoided even if the breach is not
fundamental.[150] However, he remains free to set a second or [page 112]
further additional period of time
for performance, if he has a purpose to save the contract. The buyer may also follow the
described procedure if the delay constitutes a fundamental breach, as he may have reasons
to obtain performance. Moreover, he may apply the Nachfrist when he is uncertain
whether the non-delivery amounts to a fundamental breach in order not to risk his right.
A notice setting an additional period of time may be sent to the seller in case of partial
non-performance if some parts are missing in a delivery. According to the provision of
article 51, the seller's non-delivery of the missing part within this additional period of time
entitles the buyer to avoid the contract with respect to this part of the goods.[151] A Nachfrist
notice can be useful when the buyer is not sure, as in an installment contract, whether a
breach which occurred, is in fact fundamental. He may, like under article 51, set an
additional time and if the seller does not perform with its expiration, the buyer may avoid
the contract.[152]
2. The delay in performance in Polish Law
The delay is assumed to be a non-performance of a temporary character. However,
it may transform into total non-performance. The party who does not perform at the time
due may still objectively perform and if he does, his obligations will be fulfilled, although
not in a proper way.[153] The legal effect connected with the delay arises when the
performance has not been rendered at the time which has been indicated in the contract or
which resulted from the nature of the obligation or, if the two cases are not applicable,
immediately after the performance has been called for. The Code treats differently
obligations which are to be performed at the date fixed and "simple" obligations to be
performed in due time,[154]where the aggrieved party is not deprived of his interest in receiving the performance after the delay.[page 113]
If the performance under the contract is to be made on a fixed date, or if performance
after the delay does not have any significance to the aggrieved party due to the special
nature of the obligations and the intended purpose of the contract, which was known to
the party in breach, then the aggrieved party may renounce the contract without setting an
additional period of time.[155] In the event of delay in performance of simple obligations to be
fulfilled in due time, the aggrieved party may renounce the contract but only after
adequate additional time, set by the buyer, for the other party to perform, has expired
inefficiently.
The setting of a Nachfrist means, under the Polish law, a unilateral postponement
of the original time set in the contract for performance.[156] It also constitutes a necessary
warning for the party in delay.[157] The additional time required by the CC regulation should
be adequate. That is, it should be long enough to give the party in breach real possibility to
perform. What time is adequate will be considered on the basis of all the circumstances of
the case, the nature of the performance and the particular obligations arising under the
contract.
The CC does not provide for the form in which setting of the Nachfrist should take
place; therefore, it may be oral or written. It is effective according to article 61 CC, when
the notice setting the Nachfrist has reached the other party in such a way that he could
have known its content; the receipt principle is applied.[158] As the party sending the notice is
burdened with the risk of its transmission, he should take the proper care in choosing the
means of its communication.
The Code does not regulate the cases when the initial delay turns into
impossibility. The provisions on renouncement in case of delay are not concurrent with
those applicable to renouncement in the case of impossibility. In such a case, the
provisions concerning the remedies for delay in [page 114] performance are said to be applicable until
the moment of impossibility.[159] The remedies accessible in a situation of impossibility become
available after the moment the impossibility occurred. So, the effects of the remedies
available for delay in performance, which had been exercised until the moment of
impossibility, will have to be respected.[160]
D. Declaration of avoidance
1. Declaration of avoidance under the Vienna Convention
A declaration of avoidance is a right of the buyer, which can be exercised by him
under the authorization of the provisions of the Vienna Convention or under the terms of
the contract agreed to by the parties. It is a unilateral right. Article 26 of the Convention
requires it to be done in the form of a notice [161] sent to the other party. The notice can be oral
or in writing but it should state clearly an intent of avoidance.[162] Other conduct implying an
intent to avoid a contract is not recognized under the Convention's regulation [163] (for
example, the goods are sent back to [page 115] the seller).[164] The declaration of avoidance is subject to
the provisions of article 27 of the Convention. It should be made with the means
appropriate under the circumstances, as the dispatch is decisive.[165] Particular care will have
to be taken when choosing the means for communication of such an important decision
like avoidance.[166] The buyer may rely on the notice, although it is not necessary that the
communication reach the seller. It may happen that he will continue performance of the
avoided contract, not having received the notice.[167] In such a situation it is a question of
good faith [168] or mitigation of loss [169] for the buyer to draw the seller's attention in the content of
the notice if the buyer becomes aware from the conduct of the seller that he did not
receive the communication.[170]
[page 116]
On the other hand, one may admit that the transmission risk in communication of a
notice of avoidance should be borne by the seller, if he caused the notice to be sent in a
manner not fitting to the contract terms.[171] Such an approach however, would not be
justified in situations exempted under the Convention, such as when the avoidance does
not result from defective performance attributable to the seller. The declaration of
avoidance cannot be conditional, nor can it be revoked unilaterally.[172]
2. Declaration of renouncement in Polish Law
The right to renouncement in cases of delay in performance, impossibility and in
other situations provided for in the CC is required to be exercised by a declaration.[173]
This conclusion might be drawn from article 61 CC, which refers generally to declarations
made to the other party and that the transmission risk in communication of the declaration
of renouncement is borne by the aggrieved party. The aggrieved party becomes bound by
the declaration upon its formal receipt. The declaration of renouncement is the
prerequisite of the effectiveness of the exercise of the right.[174] It cannot be revoked without
the consent of the other party unless the revocation has reached the addressee at the same
moment as the formal receipt of the declaration of renouncement or before this moment;
nor can the declaration of renouncement be conditional.[175] The form in which it should be
exercised is not defined, so it may be oral or written. However, if the contract has been
made in a written form, the declaration of renouncement should be in the same form.[176]
[page 117]
E. Time for exercising the right to avoidance by the buyer
1. Time for avoidance under the Vienna Convention
Generally speaking, there is no provision in the Convention that precisely defines
the time for the buyer to declare the contract avoided. Under article 49(1)(a), when there
is a fundamental breach of any obligation, not only the obligation to deliver, the buyer can
avoid the contract immediately [177] without referring the matter to the court or arbitral
tribunal.[178]
When the buyer has set a Nachfrist in the case of non-delivery, according to article
49(1)(b), he has to wait until the fixed period inefficiently expires and cannot declare the
contract avoided before that moment, because it is not possible to require performance
and at the same time to avoid the contract.[179] Only when the seller has declared that he will
not perform within the additional period of time does the buyer not have to wait until the
expiration of the Nachfrist period. Such a seller's declaration ends uncertainty on the
buyer's part about whether the seller will perform or not within the additional period of
time. However, when the buyer anticipates a fundamental breach of contract will be
committed by the seller prior to the date performance is due, the buyer may avoid the
contract at any time before the period for the performance expires because article 72
prescribes no time limit for such a declaration.[180] Nonetheless, the two cases can be
distinguished in order to define the time for exercising the right to avoidance under this
article:[page 118]
a) the buyer may avoid immediately if he is absolutely
certain about the fundamental character of the impending
breach of the contract, or when the time does not allow the
buyer, according to the wording of article 72(2), to send a
reasonable notice to the seller permitting him to provide
adequate assurance of his performance, or the seller
declares that he will not perform his obligations;[181]
b) the buyer may exercise his right after the ineffective
lapse of the sufficient time necessary for the seller to
provide adequate assurance of the performance when the
buyer has sent a reasonable notice requiring such an
assurance.[182]
As far as installment contracts are concerned, there are no time limits for making
the avoidance declaration under article 73(1), referring to avoidance of a given installment,
and 73(3), which allows avoidance of future installments and installments already made.
Nonetheless, under article 73(3), the buyer wishing to avoid the contract with regard to
the latest as well as earlier and future installments, has to do it at the same time. However,
the requirement to declare the contract avoided within a reasonable time is imposed on the
buyer under the provision of article 73(2), if he has good grounds to conclude on the basis
of the seller's failure to perform his obligations under any installment, that a fundamental
breach will occur with respect to future installments. What time is reasonable in the
installment contract depends, among other things, on the length of the interval between the
latest and the next installment and its reception and payment.[183] The time runs since the
occurrence of the failure.
Avoidance of the contract has significant results as far as care and disposition of
the goods are concerned. Delay in declaring the contract avoided by the buyer may
contribute to higher demurrage and warehouse costs, it may expose the goods to
additional unnecessary risks of damage or loss, and, in the meantime, market prices may
change. Deferring the declaration of avoidance creates expenses and risk for both parties
to the contract. [page 119] In order to protect them against the undesirable effects of the
postponement of the buyer's right, the Convention lays down, under article 49(2), rules
setting a time limit for the hesitant buyer.
The regulation included in article 49(2)(a) refers to cases where the seller has
delivered the goods following delay in delivery, not only when it constitutes a fundamental
breach, but also when the late delivery is effected after the deadline set in a Nachfrist. In
such a situation the buyer has to avail himself of his right within a reasonable time which
begins to run when he has become aware that the delivery has been made.[184] The term "a
reasonable time" is not defined under the provision. Such a formulation of the time limit
within the exercise of the right to avoidance enables a flexible application of the provision
to many different international sales contracts. The time limit will vary with respect to the
nature of the goods according to the market conditions in which the transaction will be
pursued or other factors such as, usages developed within a trade, or a course of dealing
between parties to a contract.[185] So, the time limit would have to be evaluated pursuant to
the circumstances of a given case.[186]
All cases of non-performance, other than the late delivery of the goods provided
that a fundamental breach of the contract occurs, are regulated under article 49(2)(b). It
embraces delivery of non-conforming goods as well as delivery of goods not free from
claims of a third party. The general rule is that the buyer has to exercise his right within a
reasonable time. The time may differ in particular situations. It starts to run:[page 120]
a) after the buyer knew or ought to have known of the
breach. This moment will have to be fixed - in cases when
the goods delivered fail to conform to the contract - in light
of article 38 of the Convention which describes the period
within which the buyer must examine the delivered goods;[187]
b) after the expiration of any additional period of time
fixed by the buyer pursuant to article 47(1), or after the
buyer receives the seller's declaration refusing performance
within such an additional period. This refers to cases of
setting a time limit for the delivery of substitute goods as
well as for repair of goods if the buyer prefers such
performance in case of a fundamental breach of contract.
When there is no fundamental breach of contract, the buyer
does not have the right to avoid either before or after a
Nachfrist was set for repair;[188]
[page 121]
c) after the expiration of any additional period of time set
by the seller under article 48(2) governing the seller's right
to remedy a failure to perform, or when the buyer has
declared that he will not accept performance, which,
however, equals a declaration of avoidance.[189]
The period for declaring avoidance does not begin to run as long as the buyer requests
delivery of substitute goods under article 46(2).
The rules of the Convention governing the time for avoidance have a very
significant role. First, in the case of delay under article 49(2)(a), the aggrieved buyer does
not have to take the risk of deciding how much delay will amount to a fundamental
breach, but may wait to declare avoidance until the delayed performance is made.[190] Second,
their most important function is to provide a sanction for contravening the time limits laid
down to declare the contract avoided, namely, under article 49(2), the loss of the right to
declare avoidance, notwithstanding the presence of substantive grounds for it.
In addition to the rules on the time limits for avoidance, the Convention clearly
states in article 45(3) that no period of grace can be granted by a State court or arbitral
tribunal. This rule applies to the remedy of avoidance.[191] As the Convention does not
foresee any procedure for applying to a court for avoidance of the contract, such an
additional period cannot be maintained in the Convention's regulation. Such a procedure
would be inappropriate in international trade as it could be expensive and take time for a
judge to decide to allow immediate avoidance or to grant a period of grace. The situation
is different when the buyer is equipped with the right to grant the seller a reasonable
additional period. It would be highly undesirable to leave the matter to judicial discretion.
In the case of a fundamental breach of contract, the right of the buyer to avoid the
contract arises immediately at the time of the breach (or in case of an anticipatory breach
even before), and it cannot be deferred by any court or arbitral tribunal.[page 122]
2. Time for renouncement in Polish Law
According to the regulation in the Polish CC, if a Nachfrist has been set for
delayed performance, the aggrieved party has to wait to exercise his right until the
expiration of the Nachfrist. Then, he is entitled to renounce the contract starting from
the day following the last day of the additional period of time fixed (if there are still
grounds for it). Immediate renouncement in the case of delay, may take place without
setting a Nachfrist according to the provisions of article 492 CC when: (a) performance after the time due would not have any significance for the aggrieved party
because of the nature of the obligation or the intended purpose of the contract, known to
the party in delay; or when, (b) the right to immediate renouncement has been stipulated in
the contract for performance at the date fixed (lex commissoria). Immediate
renouncement means that the right can be exercised starting from the day following the
day the performance became due.
In cases of renouncement for physical defects, the buyer may renounce the
contract: (a) after he notifies the seller of the defects and the seller does not, without
delay, either exchange the defective goods for non-defective goods, or remove the defects;[192] or (b) after inefficient expiration of a Nachfrist which the buyer set for the seller (a
producer) to remove the defects, or after the seller's refusal to fulfil the buyer's demand,
before the Nachfrist expires.[193] The notification requirement will be observed for the time purpose if the buyer sends the notice by registered mail as soon as possible after the defect
has been ascertained.[194] Thus, the dispatch principle is effective.
Regarding legal defects, the buyer will be entitled to exercise the right to renouncement
after he has become aware of the defect. He may learn about the defect due to a third
party's initiation of judicial proceedings against the buyer or in another way.[195] The
notification requirement is not explicitly stipulated in the Code's provisions as a
prerequisite to exercise the right in case of legal defects with one exception. Under article
573, when the [page 123] third party claims his rights against the buyer, the buyer is obliged to notify
the seller about it.[196]
The Code does not precisely define the time for renouncement of the contract if
impossibility constitutes the legal ground for it. This question is also not answered in the
publications. However, it may be assumed that the buyer can exercise his right
immediately after he knows about impossibility of performance. I will consider the
question of time limits imposed on the exercise of the buyer's right to renouncement under
the Polish law in the section on loss and suspension of the remedy.
F. Loss or suspension of the buyer's right to avoid the contract
1. Loss or suspension of the right to avoidance under the Vienna Convention
The provisions of the Convention directly or indirectly restrict the exercise of the
remedy of avoidance by the buyer although he would otherwise have grounds to take
advantage of his right. The purpose of the restrictions, which primarily serve the interests
of the seller, is to prevent the buyer from abusing his right. One of the limitations imposed
on the buyer's right to exercise the remedy of avoidance is provided in the provisions
governing the time for avoidance under article 49(2), discussed above. Suffice it to add
here that under these provisions the buyer does not lose his right to declare the contract
avoided until all the goods have been delivered, irrespective of the type of the breach
giving grounds for the avoidance. Under these provisions all the installments in an
installment contract must be delivered before the buyer loses the right to declare the
contract avoided.
The restrictions upon the remedy of avoidance result not only from the second paragraph
of article 49 but also from other articles scattered through the text of the Convention. The
buyer loses his right to declare the [page 124] contract avoided under article 39 on the basis of non-conformity of the goods amounting to fundamental breach of contract, if he has failed to
give timely notice to the seller, specifying the nature of the lack of conformity.[197] Such a
notice must be given by the buyer within a reasonable time after he has discovered the lack
of conformity or ought to have discovered it, at the latest within two years from the date
of the physical handing over of the goods (unless the period of the guarantee is longer).
The time limits set in article 39 are said [198] to prevail over those indicated in article 49(2)(b),
although they both begin to run simultaneously: at the moment the buyer discovered
(knew) or ought to have discovered (have known) of the defect. However, the buyer
retains his right to avoidance devolving from a lack of conformity of the goods, even if he
fails to examine the goods delivered and fails to give notice, if the lack of conformity
relates to facts of which the seller knew or could not have been unaware and which he did
not disclose to the buyer.[199] This exception laid down in article 40 of the Convention applies
also to the maximum period of two years.[200]
[page 125]
The buyer also forfeits his right to avoid the contract on the ground that the goods
received are not free from claims of a third party (including claims based on industrial or
intellectual property rights) when it amounts to a fundamental breach, if, according to
article 43, the buyer has not notified the seller about the defect specifying the nature of the
third-party right or claim. The buyer is obliged to send the notice within a reasonable
time after he has become aware or ought to have become aware of the right or claim. The
buyer will retain his right in spite of his failure to give the notice if, pursuant to article
43(2), the seller knew of the third-party right or claim and the nature of it at the time of
delivery.[201] The buyer will also retain this right with regard to third-party claims based on
industrial or intellectual property where the seller knew of it at time of the conclusion of
the contract.[202]
Where the seller knew of the facts, the Convention creates a favourable situation
for the buyer. He may still exercise his right to avoidance, under the regulation of articles
40 and 43, even if he has failed, having an excuse, to give the notice of non-conformity of
the goods, based also on the third-party claims.
Article 82 of the Convention provides another restriction on the buyer's right to
avoid the contract. The remedy is lost if it is impossible for [page 126] the buyer to make restitution
of the goods substantially in the condition in which he received them, and he cannot rely
on three exceptions stated in paragraph (2) of this article:
a) the impossibility of making restitution of the goods or
of making restitution of the goods substantially in the
condition in which the buyer received them, is not due to his
act or omission;
b) the goods or part of the goods have perished or
deteriorated as a result of their examination;
c) the goods or part of the goods have been sold in the
normal course of business or have been consumed or
transformed by the buyer in the course of normal use, before
he discovered or ought to have discovered the lack of
conformity.
These restrictions on the exercise of the existing buyer's right to avoidance apply
when the restitution of the goods is impossible before the buyer has declared the contract
avoided,[203] as well as when the restitution becomes impossible after the declaration.[204] There is
an opinion that the realization of the buyer's right to avoidance is blocked when concurrent
restitution cannot be made, that is, when the price cannot be refunded.[205] The buyer may also
be prevented from making restitution because of foreign trade rules.[206]
[page 127]
The above mentioned restrictions imposed on the buyer's right to avoidance do not
entirely impair his position because he may still claim damages resulting from the seller's
breach of contract.[207]
The buyer, who has not received performance because he contributed to the seller's
failure by his own act or omission, cannot, under article 80, retain the right to avoidance.[208]
Moreover, under article 79 such buyer's conduct may constitute an exemption for damage
claims against the seller. This solution is justified, because the buyer cannot have rights
based on his wrongful action.
The suspension of the buyer's remedy of avoidance is provided in articles 46, 47
and 48 of the Convention. If the buyer chooses to require performance under article 46, he
cannot exercise the avoidance remedy, which immediately releases the seller from his
further obligations. The right to require performance, however, does not hinder the buyer
from resorting to a claim for avoidance later on, if there are still grounds for it. This refers
also to the case in which the buyer requires the delivery of substitute goods, if the lack of
conformity constitutes a fundamental breach of contract.[209] It seems also to apply to a right
to claim delivery of substitute goods free from third party rights [210] and to remedy the lack of
conformity by repair.[211]
Under article 47(2), the buyer's resort to the remedy of avoidance for breach of
contract is restricted if he fixed an additional period of time for performance of the seller's
obligation. The buyer cannot avoid within this [page 128] period, even if non-fulfillment of an
obligation was from the outset a fundamental breach of contract.
The suspension of the remedy of avoidance takes place also in a situation where
the buyer could avoid the contract after the date for delivery, having good grounds for it
under article 49, but has not yet done so, and the seller has offered to cure the defect
as article 48 allows him. If the buyer does not respond to the seller's request whether the
performance will be accepted, the avoidance cannot be exercised before the date indicated
in the seller's request by which he intends to fulfil his duties. The relationship between
article 49 giving the buyer the right to avoid the contract and article 48 referring to the
seller's right to cure the defects of performance, remains controversial among scholars. On
one hand, it is said that the right to avoidance prevails over the seller's right to cure [212] and
the seller has no right to remedy his failure to perform if the buyer avoids the contract. On
the other hand, it is said that the offer to cure prevents the breach from being fundamental
and takes priority over the right to avoidance.[213] This opinion is strengthen by the argument that in international sales, preservation of the contract is preferred over avoidance; upon
breach by the seller he should be required to or encouraged to cure.[214] In practice, however,
to answer this question each case will have to be considered on the basis of all the
circumstances.[215] The right to avoid, which could cancel the right to cure, may only be
exercised if the breach is fundamental -- which may appear only after ascertainment
whether the breach can be cured according to article 48 laying down the limits for it.[216]
In any event, the exercise of the remedy of avoidance is inconsistent with other
remedies. Thus, the suspension of the buyer's remedy of avoidance protects the
maintenance of the contract and realization of the principle [page 129] "pacta sunt servanda."[217] Since
every avoidance of contract entails additional expenses and risks for the parties, the ceiling
for exercising this right should be high.
2. Loss or suspension of the right to renounce the contract in Polish Law
When a contract is governed by the CISG, the periods of limitation are those
contained in the gap-filling law applicable by virtue of the rules of private international
law. Under the general rule included in article 117 of the Polish CC,[218] claims are subject to
a period of limitation. This period, according to article 118, amounts to three years for
claims connected with the professional activity of the parties.[219] This rule is exclusively
applicable to claims whereby the entitled party has the right to demand defined conduct
from the party obliged to perform.[220] The right to renouncement is not classified as a claim
in the Polish legal system. According to legal doctrine, it is called "a shaping right," which
means that the party entitled to the right has a competence to change or to end an existing
legal relation due to a unilateral legal action.[221] Thus, the right does not fall within the scope
of articles dealing with limitation periods and is not limited in time.[222]
[page 130]
The above consideration refers to the remedy of renouncement on the grounds of
delay or impossibility. It cannot be said, however, that the aggrieved creditor, in this case
the buyer, will be completely free to delay the avoidance and to exercise his right at the
moment he wishes whenever the market situation is favourable for him. It is accepted in
the legal literature that, despite the fact that the exercise of some rights is not limited by
the legislator in the Polish CC with respect to time, a legal relation as a whole related to
this right may require such a time limitation considering justified interests of other persons.[223]
Therefore, if someone exercises his right with excessive delay to the detriment of another
party, he abuses his right and thereby he does not deserve legal protection.[224] The source of
such a limitation of the right is the provision of article 5 CC, according to which one
cannot exercise his right in a way that would be inconsistent with the socio-economic
purpose of the right or principles of social coexistence.[225] Such an act or omission of the
entitled rightholder is not considered as an exercise of the right and is not legally
protected.[226]
Apart from this indirect limitation imposed on the right to avoidance, there is also
a period of limitation applicable to mutual claims of the parties for restitution of what has
been performed.[227] The obligations of parties to return the performance are stipulated in article 494 CC. They arise after the [page 131] right is exercised and they constitute the effect of
avoidance of the contract.[228] Claims to return the performance are subject to periods of
limitation foreseen in the Code. The period of limitation with respect to the restitution
claim of the buyer (the creditor) commences on the day the right to avoidance might have
been exercised by him at the earliest possible time (due to the grounds that have arisen).[229]
Having this in mind, the buyer will be restrained to delay the avoidance, at least
intentionally.
If the right to renounce the contract is based on warranty liability of the seller for physical
or legal defects of the goods, the Polish CC provides for different restrictions imposed on
exercise of the buyer's right. According to article 563 paragraph 2, which concerns sales
in professional activity of the parties, the buyer loses his right to renounce the contract if
he has not examined the goods within the time and in the way adopted in the trade usage
established for goods of that kind, and he fails to notify the seller immediately about the
defects. When the defect has been revealed later, the right is lost, if he has not notified the
seller immediately after that.
The notice can be oral or written, and the time will be observed if, before its expiration,
the buyer sends the notice by registered mail, so the dispatch principle is effective.[230]
However, the right of the buyer to renounce the contract in the case of physical defects,
expires definitively one year after the goods were handed over [231] to him and, in the case of legal defects, after one [page 132] year once he was aware of the defect. If the buyer first learned of
the legal defect due to the legal action of a third party, the period of one year is counted
starting from the day on which the court order became legally valid.[232]
The purpose of the time restrictions imposed on the buyer is not to excessively
extend the warranty liability of the seller, which is stricter than the liability, based on the
general principles of article 471 CC. The buyer is released from the obligation to observe
the above time limits and his right will be still preserved if the seller has concealed the
defect deceitfully.[233]
The loss of the buyer's right occurs also when the seller is exempted from the warranty
liability. If the buyer knew about the defects at the moment of the conclusion of the
contract, and, in a case of goods in kind, at the moment the goods were handed over to
him. Pursuant to article 559, the seller is not liable for physical defects which occurred
after the risk of loss had passed to the buyer, unless the defects resulted from a cause
existing then in the goods sold.
The Polish CC regulates the relation between the remedy of renouncement and other
remedies available to the aggrieved party in the provisions on performance of
synallagmatic contracts and in provisions concerning renouncement in the light of the
warranty liability of the seller. Under article 493, paragraph 1, the remedy of
renouncement is excluded if, in a case of impossibility due to the circumstances for which
the party is liable, the aggrieved party chooses the right to claim damages for non-performance or requires substitute performance (in this case he is obliged to proceed with
his own performance).[234] The renouncement is also excluded under article 491, paragraph 1, if in a case of delay, the buyer chooses the right to [page 133] require performance and claims for
damages after expiration of a Nachfrist instead of resorting to renouncement. However,
the Code does not solve the question, if the aggrieved party, opting for a remedy other
than renouncement in the above mentioned cases, may still exercise his right provided the
required performance is not rendered. If the answer to this question is positive, as the case
seems to be, the remedy of renouncement will only be suspended but not completely
excluded.
According to the provisions on warranty liability of the seller, the right to require
the reduction of price in article 560, paragraph 1, or the right to require delivery of
conforming goods under article 561, paragraph 1, excludes the remedy of renouncement.
Moreover, the Code states clearly that the right is excluded if the seller exchanges the
defective goods for conforming goods or repairs them without delay.[235] However, under
article 561, paragraph 2, (discussed in the section dealing with grounds for avoidance
under the CC), the buyer should suspend his right to renounce until the inefficient
expiration of the additional time he set for repair, even if he is entitled to exercise his right
without fixing the Nachfrist.[236] Only the persistent refusal of the seller to repair defective
goods or to reduce the price or to deliver conforming goods seems to restore the buyer's
freedom to exercise his remedy of renouncement.
IV. The Seller's Right to Avoid the Contract
The remedy of avoidance is indexed as one of remedies available to the seller for a breach
of contract by the buyer under article 61 of the Vienna Convention.
A. Grounds for avoidance by the seller
1. Grounds for avoidance under the Vienna Convention
The grounds for avoidance by the seller are provided in article 64(1) of the Vienna
Convention. According to it, he may exercise his right:[page 134]
a) if the buyer fails to perform any of his obligations
under the contract or the Convention and the failure
amounts to a fundamental breach of contract; or
b) in case of non-payment or non-taking of the delivery
by the buyer, if he does not perform his obligations within
an additional period of time fixed by a seller's notice made in
compliance with article 63 of the Convention, or declares
that he will not perform within the period so fixed.
These are the conditions constituting the justification of the avoidance of a
contract and if they are met, the seller is authorized, but not obliged, to declare the
contract avoided. In case of dispute, the seller has to prove that the conditions are present.
Avoidance of the contract with its further consequences will normally be chosen by the
seller only when it might lead to the recovery of the goods and the goods are wanted.
2. Other situations
Other situations in which the seller may avoid the contract are regulated under the
Convention in the same way as those in which the buyer is entitled to the remedy of
avoidance because provisions concerning them are common to the buyer and seller.
Having considered them thoroughly in the previous chapter, I will discuss them at present
in a limited extent, taking into account specificity of the seller's position.
Under article 72 the seller may avoid the contract if prior to the date for
performance of the contract it is clear that the buyer will commit a fundamental breach of
contract, unless the buyer provides adequate assurance of his performance. Suffice it to
say that the serious worsening of creditworthiness of the buyer to such an extent that a
fundamental breach of contract will be committed may play a role if he is the one to
perform first (for example, in the case of advance payment or if it is clear that the buyer
will not be in a position at the time of delivery to open a letter of credit).[237]
[page 135]
The seller may avoid the contract in a case of an installment contract, according to article
73, because the buyer may breach a contract with respect to a particular installment, either
by not taking delivery of the goods [238] or not paying for them if prior payment for that
installment is required.[239] The provisions of article 73(1) and (2) are said to apply to the
buyer directly, [240] although, according to another opinion, by analogy;[241] in situations in which
the buyer has the right to pay in installments for one delivery, the provisions of article 73
should not be applied, because if the buyer does not fulfil his obligations to pay in
installments, the seller may exercise the right to avoid the contract under article 64 or
article 72 of the Convention.[242]
Under article 79(5), the remedy of avoidance may be exercised, even if the situation,
described in preceding paragraphs of the article, justifies exemption of the buyer for
damage claims. The provision applies indifferently to either party to the contract. Even
though the failure to perform is attributable to an impediment which was beyond the
buyer's control, it is possible that this failure to perform will constitute a fundamental
breach of contract, and the seller's right to avoid the contract will not be precluded.
3. Regulation in Polish Law
The provisions in the Polish CC regulating the grounds for renouncement of the
contract due to delay and impossibility, which I considered in the previous chapter, are
applicable to the buyer and seller with the exceptions to those grounds which are
characteristic only of the buyer's [page 136] right to renouncement resulting from the seller's warranty
liability. The remarks concerning other elements, like the liability of the party for non-performance, time for exercising the remedy of renouncement, the declaration of
renouncement and grounds justifying the loss of the remedy are fully valid with regard to
the seller's right [243] and I will refrain from repeating them in this chapter.
In addition to the grounds for renouncement applicable to both parties, the Polish CC
gives the seller other possibilities that are included in the regulation concerning exclusively
the contract of sale. According to article 552, if the buyer is late [244]
with the payment for a part of the goods sold, or, if due to his financial standing it is
doubtful whether the payment for the goods which are to be delivered in the future will
take place in time, the seller is authorized to suspend the delivery of the next parts of
the goods, setting the buyer an adequate additional time for the assurance of the payment.
The seller may renounce the whole contract after the time has expired inefficiently.
When the price is to be paid in installments under an installment contract, the seller
may, pursuant to article 586 CC, renounce the contract because of non-payment only
when the buyer is in delay [245] with the payment of two installments and their joint sum
exceeds one fifth of the total price. However, in this case the seller should fix an additional
time for the payment with the stipulation that after its inefficient expiration, he is entitled
to renounce the contract.
B. Fundamental breach by the buyer
The legal character of fundamental breach of contract under the Vienna
Convention, discussed under the previous chapter referring to the buyer's remedy of
avoidance, is applicable also to the seller's right. Taking this into account, I would like to
consider the fundamental breach of [page 137] contract committed by the buyer in the particular
aspect of his obligations under the contract.
As far as the most important obligations of the buyer are concerned, for example,
payment of the price and taking delivery, the possibility of avoidance by the seller can be
reached by using the Nachfrist procedure provided in article 64(1)(b). In the event of
other buyer obligations under the contract or the Convention, avoidance is possible only
when, according to article 64(1)(a), the non-fulfillment is a fundamental breach. To what
extent a non-fulfillment of an obligation is a fundamental breach will depend on the
purpose of the contract for the achievement of which the given obligation is relevant.[246] A non-fulfillment can be ascertained in many cases only after the awaiting for fulfillment of
obligations.
If payment is to be made at the fixed date or taking the delivery should occur at the
date specified in the contract, and where time is of the essence, non-performance at the
time indicated for performance will constitute a fundamental breach of contract. In other
cases the late payment can amount to a fundamental breach of contract if there is a rapid
decline in currency,[247] and taking late delivery can be a fundamental breach of contract when
the goods cannot be stored.[248] The longer the delay in payment or in taking the delivery, the
more a breach becomes fundamental, so that the seller will always be entitled to avail
himself of a right to avoid the contract in the event of non-payment [249] or not taking [page 138] delivery.[250]
Cases where the fundamental breach takes place can also include non-supply by the buyer
of agreed drawings or of part of the materials.[251]
The requirement of a fundamental breach of contract as a basis for avoidance is
less formal and thus less clear than avoidance after the expiration of a Nachfrist.
Therefore, it is better for the seller, having a doubt as to whether the buyer's delay in
making payment or taking delivery constitutes a fundamental breach, to fix an additional
period of time for the buyer to perform. When the buyer continues not to pay the price or
take the delivery of the goods, the seller, by fixing a Nachfrist, always has the option to
avoid the contract, as a non-performance of these essential obligations also within the
Nachfrist is said to constitute a fundamental breach of contract.[252] In case of other
obligations whose non-performance becomes fundamental when the time passes (for
example, the obligation to participate in the manufacture of the goods) setting a Nachfrist
also may be helpful for the seller. However, it will not be sufficient for the avoidance of
the contract to prove that the Nachfrist expired and performance was not made. The seller
will have to show that a breach of a fundamental character exists. Otherwise, the contract
is avoided without justification and the seller's non-performance resulting from it will be
considered a breach of contract.[page 139]
C. The buyer's delay in performance
The typical breach by the buyer of an obligation under the contract is a delay. In a
case of a delay in payment or in taking the delivery, the seller is entitled to decide how
long he intends to wait. This is the advantage of lack of strict prescription of the period
during which the right to avoidance must be exercised. However, the seller will not be
allowed to speculate at the cost of the buyer, because he would have to make up his mind
within a reasonable time, at least at the inquiry of the buyer.[253]
If the seller wishes to avoid the contract when the buyer breaches his obligations to
pay the price or to take the delivery and the breach is not fundamental, he may declare the
contract avoided after following the procedure described in article 64(1)(b). He should fix
an additional time of reasonable length for the buyer to pay the price or, as the case may
be, to take delivery.
The nature of a Nachfrist set by the seller is the same as in the case of the buyer's
right to avoidance. The fixing of an additional period of time must be done by a written or
oral notice addressed to the buyer. Its transmission which may be done by any means is
subject to article 27 and the seller can rely on the dispatched notice.[254] Determination of the
additional time is left to the reasonable discretion of the seller, according to his
commercial needs. However, he is expected to state it unequivocally by indicating the
date by which performance must be made or a period of time.
The expiration of the Nachfrist without expected performance from the buyer,
entitles the seller to resort to the remedy of avoidance. However, the first Nachfrist is not
final and the seller can set another one, as the expiration of the Nachfrist gives the seller an
option to stick to the contract or to avoid it.[255] Moreover, the seller is entitled to take
advantage of his right to [page 140] avoidance without waiting for the expiration of the Nachfrist, if
he receives the buyer's declaration that he will not pay or he will not take the goods within
the additional time.[256]
The seller is allowed under the Convention to avoid the contract for delay in payment
irrespective of whether the buyer has already taken the delivery of the goods.[257] The
obligation to pay the price includes steps and formalities required under article 54 of the
Convention. In case of the buyer's delay to take such steps, the procedure of a Nachfrist
provided in article 64(1) is applicable,[258] unless the failure to make the necessary
preparations for payment in itself constitutes a fundamental breach of contract.[259]
Apart from non-payment and not taking delivery, the procedure of fixing an additional
period of time may be applied by the seller in cases of delay in performance of the buyer's
other obligations (for example: delay in examination of the goods). However, the fixing of
an additional period of time for performance of obligations other than payment and taking
delivery, mentioned in article 64(1)(b), has only the consequences provided in article
63(2), sentence 1, namely, that the seller cannot resort to the remedy of avoidance for the
breach during the fixed period. It would be inconsistent with the requirement to perform.
Only when the passing of time makes the delay in performance a fundamental breach of
contract can the seller exercise his right to avoidance.
D. Declaration of avoidance
As in the chapter dealing with the buyer's remedy of avoidance, it should be stated
that the declaration of avoidance is a unilateral right vested in the seller if the conditions
provided under the Convention are satisfied. [page 141] The declaration of avoidance should be
made by a written or oral notice, which according to article 26, has to be communicated to
the other party.[260] The wording of the declaration should be unequivocal. Conduct of the
seller implying an intent is not sufficient to constitute a declaration of avoidance.[261] Prior
notice of the seller's intention to declare the contract avoided in the case of a fundamental
breach is not necessary. Pursuant to article 27, the declaration of avoidance is effective
after dispatch. Accordingly, the seller may rely on the notice even if it does not reach the
buyer.[262]
E. Time for exercising the right to avoidance by the seller
The Convention does not include strict rules prescribing the moment for exercising
the right to avoidance by the seller, similar to the case of the buyer. This may result from
the assumption that the exercise of the right to avoidance, even if there are grounds for it,
is left to the decision of the aggrieved seller. The seller should not be forced by strict rules
on time, to avoid the contract. On the other hand, the Convention does not leave the
choice of time for avoidance completely to the discretion of the seller.
The seller is entitled to avoid the contract immediately for a fundamental breach of
the contract. The rule of article 64(1)(a) assumes that the breach is committed under the
conditions in which the seller's right is effective at once, starting from the day the
non-fulfilled obligation became due. Immediate avoidance is also at the seller's option
when the buyer [page 142] declares that he will not pay the price or take delivery of the goods within
the additional period of time set by the seller according to article 64(1)(b),[264] or if the seller
otherwise receives a notice from the buyer that he will not perform, even if the delay in
performance has not amounted to a fundamental breach of contract. When the seller has
set a Nachfrist in the case of non-payment or not taking delivery by the buyer, as provided
in article 64(1)(b), he may avoid the contract after inefficient expiration of the additional
time.
Time for avoidance in the event of anticipatory breach of contract or in case of an
installment contract has been discussed under the previous chapter on the right to
avoidance by the buyer. The same remarks are relevant for the time of the seller's
avoidance in these situations, however, one should take into consideration the specific
obligations of the buyer.
The time when the seller exercises his right to avoidance is significant for the
buyer, a party in breach. The situation when the seller waits and watches the market
developments before making his decision to avoid the contract, would constitute an abuse
of the seller's right and he should be prevented from speculating at the buyer's cost. Once
the buyer has paid the price (in full), the seller must exercise his right to avoidance within
the time limits set by the Convention.
The seller may, according to article 64(2)(a), avoid the contract with respect to the
late buyer's performance, before the seller has become aware that the performance has
been rendered. The late performance under this rule covers late payment and/or late
performance of other obligations.[264] This will embrace situations where the performance was
not performed at the time it was due or it was refused due to lack of conformity with the
contract (place of performance was different than that stipulated in
the contract or in the law) or performance was partially performed, where this was not
allowed by the contract.
In the case of breaches other than late performance, if the breach gives grounds for
avoidance according to the Convention, the seller may exercise [page 143] his right, under the rule in
article 64(2)(b), within a reasonable time and the time begins to run: (a) after the seller
knew or ought to have known of the breach; [265] or (b) after expiration of any additional
period of time set under the Convention for performance, or after the buyer has declared
that he will not perform within this period.[266] The "reasonable time" limit is not defined
under the Convention; it will depend on all circumstances of a case.[267] The rule refers to
cases like sub-supply of defective materials, breaches of the prohibition to re-export
goods, pledging of goods which were not sold under a reservation of title.[268] The time limits
imposed on the seller have a disciplining character. In the event he exceeds them, he loses
his right to declare the contract avoided.
The Convention provides in article 61(3) (similar to article 45(3)) that no period of
grace may be granted to the buyer by a court or arbitral tribunal when the seller resorts to
a remedy for breach of contract. This includes the remedy of avoidance. The seller's right
to avoidance cannot be deferred by any judge or arbitral tribunal either before, at the same
time as, or after the seller has resorted to the remedy for breach of contract by the buyer.
F. Loss or suspension of the seller's right to avoid the contract
The rules of the Convention governing the right to avoid the contract by the seller
also provide for restrictions upon its exercise even if there are substantive grounds
authorizing its existence. The main purpose is not to allow the seller to abuse his right to
the disadvantage of the buyer. The restrictions on the seller's right to exercise the remedy
of avoidance are regulated in the provisions governing the time limits for avoidance under
article 64(2), discussed above. It is worth remembering that under paragraph 2(a) of this
article, the seller's right to avoid the contract lapses when the obligation on whose breach
it is based has been fulfilled and the seller has known about its fulfillment.[269] Under
paragraph (2)(b) of article 64 the right is lost [page 144] when the seller has not exercised his right
within a reasonable time, which has run from the moment indicated in the provision for its
commencement.
The Convention does not describe in detail the relation between the remedy of avoidance
and other remedies available to the seller. The relation is not as complex and controversial
as in the cases of the buyer's remedy of avoidance for a breach of contract by the seller.
Generally speaking, the seller cannot exercise the remedy of avoidance when he resorted
to other remedies inconsistent with it, namely the remedy to require performance.
Under article 63(2), if the seller fixes an additional period of time for performance
of the buyer's obligations, the breach of which is already fundamental, he cannot resort to
his remedy of avoidance, which is suspended during this period. However, if the seller
has fixed an additional period of time for payment, avoidance is not excluded during this
period, because of the occurrence of another fundamental breach, for example, not taking
the delivery.[270] In addition, if the seller has set a Nachfrist in accordance with article
64(1)(b), avoidance of the contract is suspended under article 63(2) as long as the
Nachfrist runs and the performance is not refused. To reassure the seller that his right to
avoidance is retained after the inefficient expiration of that period, he is granted an
additional reasonable time [271] for its exercise.
The realization of the seller's right to avoidance is said to be blocked when concurrent restitution cannot be made (when the price cannot be refunded or goods returned, because of the party's bankruptcy).[272] The seller may also be prevented from making restitution because of foreign trade rules,[273] that may result in the suspension of avoidance.
If the seller has not received performance because he contributed to the buyer's
failure by his own act or omission, he has, under article 80, no right to avoidance.[274]
Moreover, under article 79, such conduct may constitute [page 145] an exemption for the buyer for
damage claims. This solution is justified, because the seller cannot have rights based on his
wrongful action.
V. Effect of Avoidance
A. Effect of avoidance under the Vienna Convention
The consequences of avoidance are governed by article 81 and following it other
articles of the Convention. According to article 81, avoidance of the contract releases
both parties from their obligations under it subject to any damages which may be due. The
most important obligations are generally: a) the obligations of the seller to deliver the
goods, to transfer title to the goods and to hand over the documents; and b) the
obligations of the buyer to pay the price and to take delivery of the goods. If the
obligations have not been fulfilled by the moment of the avoidance of the contract, the
parties do not have to fulfill them later. Apart from the avoidance of the contract, claims
for damages which have arisen in connection with the non-performance of the obligations
can be asserted by the aggrieved party.
Avoidance, pursuant to article 81, does not affect any provision of the contract for the
settlement of disputes. It also does not influence any other provision of the contract
governing the rights and obligations of the parties that arise due to the avoidance of the
contract. This concerns rights and obligations which are ancillary to the avoidance of the
contract, for example, penalty provisions, but also provisions for the purpose of helping to
resolve a conflict between the parties (especially in a situation in which the contract is
avoided),[275] such as arbitration and renegotiation clauses and forum selection clauses. Other
rights and obligations not affected by avoidance are the obligation of the party to preserve
the goods,[276] and rights based on the provisions governing the amount of damages.[277]
Under the provisions of article 81, a party who has performed the contract either entirely
or in part may claim restitution from the other party of whatever the first party has
supplied or paid under the contract. Thus, the parties are free to claim restitution as they
may wish to leave what has been [page 146] supplied or paid with the other party.[278] In the case of a
contract for delivery and payment of goods by installment, they may agree to retain what
they received prior to the avoidance.[279] Usually, the avoidance of the contract is at the same
time accompanied by a claim to return that which has been supplied or paid.[280] The buyer,
however, will be freed from his obligation to return the goods when the contract is
avoided insofar as such restitution is made impossible because of an event for which he
already bears the risk,[281] such as avoidance, under the provision of article 70, which does
not influence the rules on passage of risk.[282]
If both parties are bound to make restitution, they must do so concurrently.[283]
Moreover, the non-performing party may be required by the other party to cover all costs
incurred to return that which has been supplied or paid. This rule, although not provided
in the Convention, is acknowledged by the doctrine.[284] If the contract is partially avoided,
the rules governing its effects are relevant to that part of the contract, which has been
avoided.
The Convention, under article 84, provides for additional rules requiring restitution
of benefits received by the parties. If the seller is obliged to refund the price, he is
accountable for interest on it which he will have to reimburse from the date on which the
price was paid.[285] This obligation is [page 147] irrespective of the grounds for the avoidance and is based on the assumption that the seller has acquired a benefit from the price since it was at
his disposal. The buyer, if he is expected to make restitution of the goods or part of them
or if it is impossible for him to make restitution of the goods at all or substantially in the
condition in which he received them (because the goods were destroyed), must account to
the seller for all benefits he has derived from the goods or part of them (also those which
accrued before the goods were destroyed).[286] The benefits gained by the use of the goods
usually will be returned in money. This will enable the parties to set off against each other
the claims they might have under this article.[287]
It should be concluded that the contract is not nullified upon the exercise of the
remedy of avoidance.[288] Some obligations of the parties are terminated and some remain in
existence. The specific obligations characteristic of the sales contract end or performance
already made in fulfilling these obligations has to be returned in goods or in price so that a
situation is achieved as from before the conclusion of the contract. However, the contract
remains in force as long as there are still claims of the parties
under it, including claims for returning the goods or the price.[289]
On these grounds, the contract cannot be considered as terminated either ex nunc
or ex tunc,[290], although legal doctrine does not adopt unified opinion on that question.[291] The
discussion, whether the avoidance operates retrospectively or prospectively is said [292] to be
of little help as [page 148] avoidance always releases the parties from future characteristic obligations
and, at the same time, imposes on the parties reciprocal duties of restoration having
retrospective effect. The buyer who avoids the contract because of non-conformity of the
goods is released from the obligation to pay the price but, if he has already paid, he is
entitled to restitution.
Avoidance does not have the effect of termination. The right to avoid the contract
is narrower in its scope than the right to terminate the contract [293] because avoidance does
not release a party whose breach leads to avoidance from his contractual obligation to
compensate the aggrieved party for the loss.[294] In the case of a contract for delivery by
installment the avoidance might be said to have the effect of a termination of the contract.[295]
B. Effect of renouncement in Polish Law
The exercise of the remedy of renouncement in all cases of defective performance
or non-performance of the contract provided by the CC (i.e., delay, impossibility of
performance due to the circumstances for which the party is liable, impossibility of partial
performance due to the circumstances for which the party is not liable, and physical or
legal defects of the goods) has the same effect as if the contract has never been concluded.[296]
This is the special status, which arises after contract renouncement. The renouncement
results ex tunc.[297] The parties are released from their obligations to perform and they are
entitled to claim restitution of whatever has been performed under the contract.[298] If parties
are bound to make restitution, each of them may, pursuant to article 496, suspend
restitution until the other party offers the received performance. The provision confirms
the [page 149] principle that the restitution should be made concurrently. In this way, the CC protects
the interests of the aggrieved party against insolvency or dishonesty of the other.
The parties are bound by the provisions on preservation of the goods.[299] The party
who is obliged to return the goods should indemnify the other party for the use of the
goods which cannot be returned in kind.[300] However, the buyer who has renounced the
contract due to physical defects of the goods is not obliged to indemnify the seller for
usual wear of the goods which took place in the course of their normal use up to the
moment of renouncement. He is obliged, however, to indemnify the seller if the
impairment of the value of the goods results from the circumstances the buyer is liable for,
or if the goods are used after the declaration of renouncement has been made.[301]
The party renouncing the contract may, under article 494, claim damages resulting
from non-performance of the contract.[302] The damages cannot be claimed when the right to
renounce the contract has been exercised on the grounds of impossibility to perform a part
of the contract by the party in circumstances for which he is not liable [303] if the performance
of the remaining part has lost any significance to the aggrieved party.[page 150]
The contract, after renouncement under the Polish CC is not void, but is considered as if it has never been concluded. This is the special status with the effect ex tunc. It differentiates the unilateral renouncement of a synallagmatic contract because of non-performance or defective performance from the termination of the contract by the parties who are always free to decide the ex nunc or ex tunc effect of the termination
depending on the reasons causing it.[304]
VI. Conclusions
The remedy of avoidance regulated under the provisions of the 1980 Vienna
Convention and the remedy of renouncement, which is its counterpart in the Polish civil
law are remedies of a particular character. They may be defined as last resort remedies,
due to the drastic effects, which result from their exercise. The substantive grounds
constituting the basis of their existence under both regulations prove that situations that
arise under the contract between the parties must be exceptionally disadvantageous for the
interests of the aggrieved party when he decides to avail himself of this right. The
alternative accessibility of other remedies at the disposal of the aggrieved party in the case
of non-performance or defective performance of the contract or the possibility to avoid
only the part of the contract, is evidence that the legislators of both Codes support the
idea of maintenance of the contract, assuming that it better serves the interests of the
parties. This argument is strengthened by the fact that in both regulations the remedy is
the right of the party and not an obligation.
The method of regulation of the remedy of avoidance adopted in the Vienna
Convention is different than in the Polish Civil Code. Under the legislative solutions of the
Convention, the grounds for the remedy of avoidance are regulated separately for the
buyer and seller. The regulation on the buyer's right to avoidance is included in the
provisions of the Convention dealing exclusively with the remedies for breach of contract
by the seller, which follow the norms on his obligations defined under the sales contract.
The same method is adopted as far as the seller's right to avoidance is concerned. On the
other hand, the articles, where the remedy of avoidance is taken under consideration, are
included in other parts of the Convention, [page 151] which contain norms common to both parties to
the sales contract. Under the Polish CC, the remedy of renouncement of contract is subject to the provisions on performance of synallagmatic contracts, which constitute lex specialis towards general principles of contractual liability and refer to both parties of the sales contract. The regulation of the remedy is, to a narrow extent, included in the provisions concerning the sales contract under the regime of the warranty liability of the
seller for defects of goods. The substantive provisions on the remedy of avoidance under
the Convention and the remedy of renouncement in the Polish law evince many common
features. Nonetheless, there are visible differences between both regulations. The
differences seem to result mainly from the specific needs of the parties in international
trade and conditions in which contracts are concluded and performed.
The general approach of the legislators in formulating the grounds giving rise to
the remedy of avoidance under the Convention and Polish law is quite similar. The right is
available in cases of delay in performance of the contract and, other than delay, in
situations, in which the performance does not comply with the contract terms agreed to by
the parties. However, the concept of avoidance in the Convention is not based on liability
of the party for non-performance or defective performance of the contract. The remedy is
available due to the objective fact of the breach of contract irrespective of the reasons
behind this. The fundamental character of the breach by either of the parties is the basic
notion underlying the concept of avoidance of the contract and is important in determining
the consequences ensuing from non-performance by the buyer or seller. Such a concept
allows the aggrieved party to avoid the contract in the situations of exemption for damage
claims. However, the party in breach, who may be affected by the changes under the
provisions concerning exemptions, does not have the right to avoid the contract. This
seems to be an insufficiency of the Convention.
Generally, the Polish CC makes the remedy of renouncement subject to the liability
of the party for circumstances which led to the non-performance of the contract (cases of
delay and impossibility). What is more, the Code adopts the presumption that the party
breaching the contract bears the liability; this party is burdened with the proof that the
non-performance has resulted from circumstances for which he is not liable. Only uniquely
to this regulation, the Code equips the aggrieved party with the right
to renounce the whole contract when the opposite party does not [page 152] bear the liability for non-performance of part of the contract. Namely, when the performance of what has been left
under the contract would not have any significance to the aggrieved party (if impossibility
of performance not based on the party's liability touches the whole contract, the contract is
terminated). As regards the buyer's right to renouncement, the Polish CC subjects it to a
second regime. This is the regime of the seller's warranty liability which is absolute in its
character, irrespective of the liability of the seller or another party he employs to perform
the sales contract. This liability does not depend on a proof of loss resulting from
defective performance of the goods, nor on the knowledge of the seller about the defects.
As far as the time for exercise of the right is concerned, both regulations allow the
aggrieved party to avoid the contract as soon as the legal grounds giving rise to it come to
existence. The Convention, as well as the CC, lays down the possibility of setting
an additional period of time by the aggrieved party and awaiting the performance to be
rendered. The main differences in regulations refer to the time limits imposed on the
exercise of avoidance. The Convention indicates when the reasonable time for exercise of
the remedy commences. Opposite to this, the CC does not limit expressly the exercise of
the right in time in cases of delay or impossibility. However, it provides for precise
ceilings for the expiration of time, namely the periods of limitation for claims of restitution
of the performance already made. This indirectly influences the unlimited-in-time
possibility to exercise the right in these cases. Moreover, there are special periods of
limitation foreseen for the remedy of renouncement under the regime of the seller's
warranty liability for defects of goods.
The form in which the remedy of avoidance is exercised under both regulations is
concurrent. Avoidance is not automatic even upon the expiration of an additional period
of time set by the aggrieved party. The declaration of avoidance communicated to the
other party is the necessary requirement imposed on the entitled party if he wants to give
rise to the effects of his right.
The right to avoid the contract is not an absolute one. It is subject not only to
substantive requirements, but also to restrictions imposed on its exercise. The Convention
regulates explicitly and comprehensively the relation between the remedy of avoidance and
other remedies available for breach of contract. Although the Polish Civil Code underlines
that the remedy of renouncement can be exercised alternatively with other remedies for
[page 153]
breach of contract (and together with damages as under the Convention), it does not solve
all the questions concerning the loss of the right and its suspension.
Damages can always be claimed with the exercise of the remedy of avoidance under the Convention and the remedy of renouncement under Polish law. However, there are cases where the party is released from the obligation to pay damages, for example, the exemption situation under the Convention, where non-performance results from the circumstances which are behind the control of the party and, under Polish law, non-performance due to an impossibility for which the party does not bear liability.
The effects of the exercise of the remedy of avoidance are the same under the
regime of the Convention and Polish law. Parties are released from their obligations under
the contract of sale and are obliged to make concurrent restitution. The debate over the
question whether the avoidance has retrospective or prospective effects is of more abstract
than practical character. However, according to unequivocal opinions of the
representatives of the Polish legal doctrine, the remedy of renouncement has the effects ex
tunc. The commentators of the Vienna Convention differ in their views on that point.
Under the Vienna Convention as well as under Polish law the interests of both parties
seem to be equally protected. This is made clear in:
- - a Nachfrist procedure which gives the party in breach another chance to perform and
assures him that the performance is still awaited by the other party;
-- the time limits imposed on the aggrieved party which prevent him from abusing his
position even if his right is fully justified;
-- the requirement of the declaration of avoidance, which serves the interests of both
parties: the aggrieved party avoids the contract when he wants to stop the contract
binding him, and the party in breach knows clearly about this decision.
The essence of the difference in both regulations of the remedy can be reduced to
the problem of one of the elements of the grounds that would justify the operation of the
provisions of the two regulations. Under the Convention, a fundamental breach of the
contract is decisive for the exercise of the right and the fate of the contract (the regulation
of the situation of delay is the exception to the rule). Under Polish law, the liability of a
[page 154]
party is based on the requirement of fault of the party for non-performance or defective
performance of the contract. Only in exceptional circumstances can the right be exercised
when the non-performance was due to the circumstances for which the party was not
liable (cases of impossibility). Moreover, in case of defects in the goods delivered the
remedy is based on the warranty liability that is stricter than the general principles of
liability in the CC. This demonstrates that under the regime of the Convention this
element of the grounds for the remedy of avoidance is formulated in a more uniform way
then under the Polish law.
VII. The General Provisions of the CISG and the Remedy of Avoidance
The remedy of avoidance should not be analysed without taking into account the
general provisions of the Convention, as the grounds for the remedy and its effects may be
influenced by the operation of these provisions. The Convention constitutes one
whole [305] and its general provisions [306] are of the utmost importance while considering particular
issues regulated under it. The general provisions of the Convention can affect the rights
and obligations of the seller and the buyer arising from a contract of international sale.
The general provisions that seem to have the most significant impact on the remedy of
avoidance in Part III of the CISG are articles 4(a), 7(1), 7(2), 8 and 9. They deal with the
interpretation of the Convention, [page 155] with the substantial problems of the applicable law and
the interpretation of a contract.
A. Problems excluded from the scope of the Convention and avoidance of contract
Article 4 might be called "the table of contents of the Convention." It indicates
which questions are and are not covered by the Convention. The first sentence of this
article describes in a positive way the regime of the Convention; it covers the formation of
the contract and rights and obligations of the parties agreed to by them in a contract. The
second sentence defines in a negative way the scope of the Convention. It enumerates
issues excluded from the regime of the Convention, namely, "except as otherwise
expressly provided in this Convention," the validity of the contract, its provisions and
usages and questions of property in the goods sold. On one hand, one of these definitions
would be enough to express the coverage of the Convention; on the other hand, it is said
that the sentences reinforce each other, clarifying the meaning of the Convention as a
whole.[307] Moreover, they underline the interplay between the Convention and national law.[308]
The terms which describe in article 4 the substantive scope of the Convention have
to be identified under it without reference to domestic law or to other conventions,[309] but the
text of the Convention itself does not provide guidance on how to determine whether a
question is one of validity. The main function of article 4(a) is to set aside the operation
of the [page 156] provisions of the CISG from cases involving issues that were not susceptible to unification within the framework of the Convention. This happened due to enormous differentiation in the regulation of avoidance under national laws of various countries [310] that
uphold the interest in maintaining a uniform policy on problems related to a valid contract
and to curb the parties' autonomy in this field.[311] Moreover, the term "validity" has a
different meaning in each national legal system. This causes difficulty in interpretation of
the term itself - the difficulty that results from the exclusion of validity questions within
the scope of the Convention.[312]
The examination of article 4(a) of the Convention suggests that issues falling under
the term "validity" can be related to the question of avoidance of the contract in the broad
meaning of the term "avoidance." The issues which arise in avoidance problems may
according to various countries be [page 157] considered as an obstacle to the creation of a valid
contract or in the case of its conclusion, constitute the reason to avoid (cancel, rescind,
nullify) the contract.[313] The reasons for avoidance may be classified [314] as validity issues either
formally and/or substantively. Substantive validity arguments for avoidance, inter alia,
lack of capacity to enter a contract, defects of consent, and illegality. Defects for consent
include mistake, misrepresentation, fraud, duress, undue influence and mental incapacity.[315]
Reasons concerning the form of a contract, which under domestic law may influence the
validity of a contract, are defined by the Convention itself in article 11 [316] and supplemented
in articles 12 [317] and 29;[318] matters of form constitute an exception to the article 4(a) referral of
issues of validity to national law.[319]
[page 158]
As far as so-called substantive validity is concerned, issues of contractual capacity are
beyond the scope of the Convention. However, it is said that they rarely occur in
international transactions.[320] If a person not having capacity to enter a contract concludes it,
this might be a basis to avoid the contract under national law [321] as is authorized by article
4(a). It is also accepted [322] that domestic rules defining defects like duress, threat,[323] fraud,[324] or
deceit [325] which create the basis for avoidance of a contract under national law, are applicable
to contracts for international sale of goods. A situation where a contract is obtained by
fraud and characterized by domestic law as voidable, gives an innocent party a possibility
to avoid the contract under the domestic law (due to article 4 CISG). This right is not
forfeited under the Convention.
Application of domestic rules on mistake and misrepresentation (especially innocent
misrepresentation) to a contract for the international sale [page 159] of goods gives rise to debate
among scholars. It is said that rules on misrepresentation and mistake are of great
practical importance under the Convention because they refer to the question of warranty
as to the quality of the goods. At the same time the problems they raise are the most
difficult to deal with under the CISG.[326] The problem concerns the concurrent availability of
two systems of remedies that may be applied under domestic law based upon reasons of
contract validity (avoidance of a contract) and under the Convention (for instance,
avoidance in case of a fundamental breach of contract). This may happen if one party
invokes mistake [327] or innocent misrepresentation concerning the quality of the goods or
claims non-conformity of the goods. Can the buyer resort to remedies invalidating the
contract under national law on the basis of mistake when he has at his disposal remedies
for lack of conformity available under the Convention?
The choice has to be made as to whether to support 1) a broad [328] interpretation of
the terms under article 4(a) and give priority to domestic rules that would result in a strict
basis under which one could avoid the contract; 2) a narrow interpretation of article 4(a)
to make application of the Convention as wide as possible; or 3) to look for a compromise
between competing remedial systems of the Convention and national law. It is said [329] that a
balanced approach to article 4 (a) is desirable. This means that in each case the domestic
policy of a State, whose law would be applicable to the issue, should be examined and
considered against the needs of international trade.[330] The question remains controversial.
There is an opinion accepting the rule that when the provisions of the [page 160]
Convention could be applied to the situation which might also be the basis for the
application of a domestic law, then remedies foreseen in the domestic law (in that case, for
innocent misrepresentation or mistake) should be displaced by the remedies provided by
the Convention.[331] On the other hand, it is argued that the provisions of the Convention
which regulate the matters arising out of the conformity of the goods do not in any way
refer to the validity of the contract, so these are two different issues that should be treated
under separate legal regimes as article 4(a) indicates. The voices which support the
interpretation that questions of mistake, together with mistake concerning the quality of
the goods, constitute a validity case are numerous.[332] The conclusion which might be drawn
from the competing sets of remedies is that under article 4(a), parties will try to take
advantage to exercise all the rights they are entitled to, irrespective of whether they are
available pursuant to domestic law or the Convention.[333] That is why parties would seek to justify handling the avoidance of a contract under [page 161] domestic law in case of mistake,[334] an
approach that clearly acts against the goals of creation of a uniform law.
Initial impossibility in contract performance, which may evince in perished goods
or lost goods at the time of contracting, might be another ground under domestic rules to
avoid a contract.[335] The existence of goods that are the subject matter of the seller's
performance is the essential part of the obligation undertaken. Goods which do not exist at
the time of contracting create a controversy as to whether the issue is one of validity to be
ruled on under domestic law, or an issue that should be solved under the provisions of the
Convention (for example article 68 [336] and art. 79).[337] Moreover, whether the provisions of the Convention override the provisions of national law in order to solve the problem.[338]
According to some opinions,[339] the non-existence of goods at the time of contracting is an issue of validity and due to article 4 (a) is taken out of the scope of the Convention.[340] There are other authors who contend that such a contract of sale [page 162] would be valid [341 and in this situation the matter would entail the question of liability of a party. Thus
the provisions of the Convention, not domestic law, should apply to the case.[342] Some
represent a moderate approach concluding that a court or a domestic tribunal, which may
apply domestic rules regulating the validity of a contract, should balance the result of their
application pursuant to the international background in which the case of initial
impossibility exists.[343]
Illegality and immorality are other grounds to invalidate a contract that are left to
the discretion of the domestic law by virtue of article 4(a). This solution is rather obvious
among authors and does not cause controversy.[344] Article 4 preserves domestic
public policy in this area together with mandatory rules of public policy (in the meaning of
special protective or other market regulatory legislation) [345] as applicable to contracts for the international sale of goods.[346]
The next validity issue which appears under article 4 can play a significant role in
light of considerations of the right to avoidance as defined under the Vienna Convention.
Domestic rules controlling unfair, unreasonable or unconscionable terms apply, due to
article 4, to contracts for the international sale of goods. The opinion exists that
contractual fairness may be controlled at two levels: (a) the control may be pursued in
order to [page 163] detect procedural defects in the bargaining process (what often happens in the
case of standard forms); or (b) in order to check the substantive allocation of
risks/advantages in the concluded contract.[347] Such control is aimed at the protection of the
party who has a weak bargaining position and the effects of the control are defined in
domestic law.[348]
Allocation of risks will be controlled through examination of exculpatory clauses
when a contract for the international sale of goods contains so called "disclaimers."
Examples include clauses modifying, limiting or excluding the liability of a party for the
breach of contract, or clauses limiting or excluding the remedies that would otherwise be
available to the parties.[349] Such exclusion refers to the remedy of avoidance which might be
directly influenced by the clause. Exculpatory clauses are of great importance in
international commerce. The Convention does not have provisions restricting the parties'
freedom to limit or exclude their liability under contracts within its scope. Moreover,
article 6 allows parties to derogate from the Convention as a whole or from any of its
provisions. The article permits the exclusion of obligations imposed under the Convention
and permission to make such contractual changes confirms the precedence of the contract
over the Convention.
The Convention is said [350] to contain default-type rules,[351] which means that they start to
operate to the extent that the parties to the contract have not agreed otherwise. The rules
of the Convention on remedies in case of a breach are among the provisions which parties
may tend to amend or [page 164] displace. Parties, according to their will, are free to change the
grounds giving rise to the remedy of avoidance.[352]
The content of the contract in this sphere may depend on the positions of the
parties in the given case; on whether the buyer or the seller enjoys superior bargaining
power. For instance, a clause requiring a notice to be given "at latest" by a specified,
agreed date may have the effect that any delay in performance gives the right to avoid a
contract, even in the case of minor, non-fundamental breach.[353] Another example would be a
clause, which permits the buyer to reject goods which fail to conform "in any respect."
Such clauses would make the liability of the party stricter than under the Convention.
On the other hand, sellers may seek to limit or disclaim liability by softening the grounds
for avoidance of the contract (or any other remedy provided). Thus a liability limitation or
a disclaimer may at the same time serve as a limitation or exclusion [354] of a remedy. This use
would embrace the remedy of avoidance of the contract. The consequence of
constructing a clause effectively disclaiming a given obligation is elimination of the breach
of contract in this scope. Examples of clauses having this effect would be disclaimers of
liability for "any loss" or any "indirect or consequential loss" and/or limiting liability to the
selling price of the goods. However, if the seller obligates himself in the clause to "repair
or replace" non-conforming goods with a view to limiting the buyer's options under the
CISG rules which allow the avoidance of the contract in case of a fundamental breach,
such a term will be construed narrowly [355] and be restricted to cases wherein the seller can
cure the defect within a period of time which is reasonable.
In the context of article 4(a) certain questions are raised by commentators: Would the
disclaimer of a basic obligation be unconscionable and [page 165] would municipal law making it
unenforceable be applicable? Would this be an issue of validity within article 4 or would
article 6 take priority? The opinion, which is expressed in this respect, is that domestic
rules giving grounds to control unfair, unreasonable or unconscionable contracts (or
clauses) regulate the sphere of validity and apply to contracts in accordance to article 4(a).[356]
The right given under article 6 is limited by the applicable domestic law, which will be the
proper law to estimate whether the derogation from any of the Convention provisions are
valid.[357]
On the other hand, there are opinions opposite to the view that exculpatory clauses
in contracts for international sale of goods are subject to domestic law. The debate
concerns the standards for evaluating an exculpatory clause limiting a party's obligations.
Article 35 of the Convention requires that the seller must deliver goods of a certain
quality, if the parties did not express their will in another way in the agreement. The point
of disagreement [358] is whether such clauses have to be valued on the basis of domestic rules
of validity or rules of interpretation provided for by the Convention, namely article 8.[359]
According to one commentator, the rules [page 166] of domestic law imposing restrictions on
warranty disclaimers, which would result in the ineffectiveness or invalidity of a given
disclaimer clause, do not constitute a question of validity in the meaning of article 4(a) of
the Convention. Thus, such rules cannot be referred to in the intention of avoiding a given
clause (or a contract).[360] Otherwise, it might collide with the Convention's rules on
interpretation.
The questions of validity, which are governed and solved under the Convention, should
not be looked to under domestic law for solution, especially since, according to the rule
inserted in article 6 and strengthened by article 35(2), the parties may define in different
ways the seller's obligation concerning the quality of the goods.[361] The answer quoted in the
literature for this interpretation is that the validity of most exculpatory clauses, and thus
their legal effect, will be influenced by the domestic law applicable to the contract apart
from the provisions of the Convention.[362] This issue will not be left only to international
standards represented by the provisions of the Convention.
Similarly, the Convention does not embrace within its scope questions of validity of
standard terms disclaiming obligations or limiting liability in case of a breach. Thus the
remedy of avoidance may effectively be eliminated when validity of contract is questioned.[363]
This issue will be solved according to applicable contract law, indicated by the rules of
private international law of the forum.[364] Disclaimers, which are put among other standard [page 167]
terms in a contract, are subject to control of domestic law because usually they are non-negotiated and possibly unfair (or unusual).[365] The national law may treat in different ways
the validity of standard terms which incorporate disclaimers, sometimes may treat them
even stricter than the disclaimer clauses that are the result of individual negotiations.[366] Or in the most extreme case their legal effect may be refused. Hence, the Convention is said [367] to produce a balanced system of contractual obligations and remedial measures with fair access to both of them which [page 168] includes the remedy of avoidance. The parties can provide
for an optional regime within the context of the contract which may be good as well
(different allocation of risk).[368] However, the parties should not forget that each is entitled to
have at his disposal an adequate range of remedies without exclusion of the strongest of
them, namely the remedy of avoidance if a situation justifies it.
B. Interpretation of the Convention and avoidance of contract
Article 7 is another general provision of the Convention that attracts interest when
considering the remedy of avoidance. This article contains guidance on how the
provisions of the Convention should be interpreted. The main rule of its provision is
included in article 7(1). The provision indicates that in the interpretation of the
Convention attention should be drawn to its international character, to the need to
promote uniformity in its application and the observance of good faith in international
trade.
Scholars, in majority, confirm the great role of the principle of good faith in the
interpretation of the Convention and interdependence between the application of this
principle in the interpretation of the Convention and the interpretation of a contract. It is
suggested that the good faith principle, applied in the interpretation of the provisions of
the Convention, has at the same time an effect on the contract between the parties to
which the Convention is applied.[369] This would have significance not only for the conclusion [page 169]
and realization of the contract but would also influence negative effects of non-performance.
Application of the good faith principle to the process of interpreting the Convention's
provisions evinces an observance that the international character of the Convention
imposes on the courts and arbitral tribunals, and on the parties as well, an obligation to
refrain from interpreting its terms and legal institutes from a national perspective. The
terms and rules in the Convention, which form legal institutes should be construed in
accordance with the common will of the Contracting States, as expressed in the text of the
Convention, taking into account the context and the function they have. The meaning of
this approach, with reference to the remedy of avoidance, is that when the institute of
avoidance has been defined under the Convention, there is no possibility to apply national
rules defining the functional equivalent of this remedy irrespective of how it is construed,
in accordance with or different from the Convention's provisions.[370]
The obligation of observance of the principle of good faith in application of the provisions
of the Convention to the agreement of the parties [371] [page 170] constitutes a guidance that the
Convention's provisions should be interpreted in such a way that when the behavior
recommended by the Convention does not coincide with conduct based on the principle of
good faith, then it must be regarded as unlawful.[372] The existence of this recommendation
makes it clear to the parties and courts that high standards of conduct are expected in
international trade transactions. This may render the criteria for evaluation of the conduct
of the party, who does not perform or performs defectively, more stringent. Moreover,
the requirement of good faith, as one of the general principles underlying the Convention,
may impose on the parties additional obligations in the course of performance of the
contract. These obligations will be defined, if a question arises for which any specific
provision cannot be found in the Convention, through application of the principle of good
faith.[373] Even the exercise of the remedy of avoidance should not contradict conduct based
on the principle of good faith, otherwise it should not be approved.[374]
Paragraph (2) of article 7 contains another rule guiding on how to fill gaps in the
regulation of the Convention. According to the suggestion in the provision, the answers
for issues, which fall within the scope of the Convention but are not solved under it,
should be based on general principles which constitute the background of the Convention.
The exception to this premise is the suggestion (contained in this paragraph) that where a
general principle cannot be derived from the text of the Convention,[375]
the question at hand should be dealt with under the law applicable to the contract [page 171]
indicated by the rules of private international law. This general guidance is expanded upon
by scholars. Before the reference to the proper domestic law is made, one may
follow two methods seeking the solution for the issue at hand, which are complementary
to each other. The first is the analogical application of specific provisions of the
Convention. The second is the reference to general principles which are explicitly stated
in the Convention or are to be derived from the set of the Convention's provisions. The
analysis of these helps to extract a more general rule likely to be applied to situations
different from those regulated by the Convention's provisions.[376]
The methods recommended to fill the gaps are also to be applied in situations of
avoidance as one may find issues related with this legal institute which are not regulated
explicitly by the provisions of the Convention. An analogical application of specific
provisions must be pursued with care. In interpreting the analogous provisions, it may
appear that the provision is of such a character that its application is restricted to a given
situation only. Thus, any trial to apply it to other situations, not described in the
provision, would be against the will of the legislators or the intended purpose to be
achieved by the provision.[377]
An example is article 49(1)(b), which sets forth grounds for avoidance in case of
non-delivery of the goods. The lack of delivery within the additional [page 172] period of time fixed
in accordance with article 47(1), or a declaration of the seller that he will not deliver
within the period so fixed, gives the buyer right to avoid the contract, even if the non-delivery does not constitute the fundamental breach of contract. It is stated,[378] that this
provision cannot be extended to other cases of non-performance, as when the goods
delivered do not conform to the contract terms or are burdened with the rights of a third
party, because the provision in paragraph (1)(b) of article 49 constitutes an exception to
the rule included in paragraph (1)(a). There were reasons for limiting this exception to
cases of non-delivery only. In the avoidance situation, the analogous application of the
Convention's provisions might affect the issue of the place where the seller has to make
restitution of the price already paid by the buyer. This question is not explicitly settled by
the Convention, however, it falls within its scope. Proposed solutions are: (a) the seller
has to pay back the price at his own place of business; (b) or at the buyer's place of
business; or (c) somewhere else.
One commentator argues for [379] the buyer's place of business. The proposed
reasoning is as follows: according to the rule in article 57(1)(a), the buyer has to make
payment of the price at the seller's place of business. The provision could be applied per
analogy to the obligation of the seller to make restitution of the price when avoidance of
the contract has been declared. The seller, as an obligor in this situation, would be treated
in the same way as the buyer when he was obliged to fulfil his duty to pay the price to the
seller. The provision would be applied accordingly.[380] If the buyer also has to make
restitution of the goods already received, the way to achieve the solution, in the opinion of
this commentator,[381] would be different. The parties are obliged to make restitution
concurrently under article 81(2). The suggested article, which might come into play,
would be article 31(c) stating that the seller is obliged to place the goods at the buyer's [page 173]
disposal where, at the time of the conclusion of the contract, the seller has his place of
business.[382] So, the buyer would hand over the goods back to the seller at the buyer's place
of business, applying by analogy article 31(c).[383] An additional argument that might be
invoked is that it is the place where the seller would be under an obligation to make
restitution of the price. Moreover, analogical application of the Convention's
provision is indicated to define the time within which the goods should be tendered due to
the restitution claims.[384] By analogy from article 33(c), the period should be reasonable after
the receipt of the claim to make restitution.
General principles used as a means of interpretation can be applied on a wider
scale, because of their general character. This is what differentiates them from the
reasoning to achieve solutions based on provisions applied per analogy. Some of these
principles are expressly stated in the text of the Convention's provisions.[385] These principles
would be applied in the situation of avoidance (to the declaration of avoidance made to
the other party), like the one stating that any notice made after the conclusion of the
contract is effective after dispatch.[386] However, depending on the situation that might arise,
the principles would also have to be derived from the provisions of the Convention
regulating the given particular issue. The commentators of the Convention extracted
some such principles, which were the effect of an analysis of a set of rules considered by
them as an expression of a more general rule.[387] An example would be the principle
requiring the [page 174] reasonableness test with reference to the conduct of a party or to other
situations where a specific provision cannot be found.[388] This test has to be applied with
regard to the situation of avoidance on the basis of the provisions of articles 47, 49, 63, 64
and 72(2).
It is interesting to make a brief overview of general principles relating to the
remedy of avoidance of a contract. One principle contradicts the remedy of avoidance and
draws the most attention. It is the principle favouring the continuation of a contract which
demands that solutions furthering the existence of a contract should be adopted instead of
its premature termination.[389] The aim of the application of this principle is to prevent
occasional decisions to exercise the right. The principle can be extracted [390] from articles 34, 37, 48, 49, 51, 64, 71 and 72 of the CISG. The rule imposing on a party, who relies on
the breach of contract, the duty to mitigate the loss resulting from the breach and which is
extracted from the set of articles 77, 85-88, ought not to be forget in the situation of
avoidance.[391]
There is the duty to communicate the information necessary to the other party, which
results from the wider principle of cooperation between the parties. Such a duty is
evinced in article 26, providing for the notice of avoidance communicated to the
other party. In various situations, the [page 175] non-observance of the duty to communicate may
result in aggravation of the position of a party obliged to send a notice. One example is
article 39, which states the consequences of non-compliance with the notice requirement.
The lack of the communication in the situation described in article 39 [392] may influence the
buyer's right to avoidance, in that it may threaten the existence of this right. Next, article
65(1) provides that, if a buyer, who is expected to communicate his specifications fails to
do so within a reasonable time, the seller can make the specifications himself. This makes
it impossible for the buyer to avoid a contract (in bad faith) by deliberate failure to
communicate specification information significant for the seller's performance.[393]
Another example of the requirement of communication is provided in article 72,
which concerns anticipatory breach of contract. In this case, the communication prevents
surprises in the form of an announcement that the contract is avoided. Besides, it protects
the party who gives the communication against accusations of unjustified avoidance of the
contract.[394]
The general principle of predictability of effects will have its importance while assessing
the scope of the legal consequences resulting from non-conformity of the goods or
another failure of a party in performance.[395] It is manifested in articles. 25, 35(2)(b),
42(1)(a), 74, and to a lesser extent in article 79(1).
The requirement of good faith is one of the general principles that deserves special
attention. This is the basic principle mentioned already, which underlies the whole
Convention and which is written in the text of the Convention, in a specific provision,
namely article 7(1).[396] The principle [page 176] of good faith would have to be further specified in
order to be applicable in a particular avoidance situation.[397] The method of specification is
recommended according to the criteria indicated in article 7(1). The solution would have
to be found autonomously, according to the standards of the Convention or standards that
can be specified at a comparative level.[398] Reasonableness would be the criterion used to
evaluate whether a party, during the performance of a contract in a particular situation
which might lead to its avoidance, or in every avoidance circumstance, acted with due
diligence.[399] Making this test, one should restrain from instant reference to the standards of
care and professional skills required from traders in domestic conditions (for example, in a
highly industrialized country).[400]
The interpretative methods indicated in article 7(2) embrace the last significant rule
that should be applied when the above described endeavors fail to bring about a positive
result. The last step to be done is to invoke a national law in order to find a solution if the
case does not fall within the regulation of the Convention or its general principles. This
rule is valid for the [page 177] problems relating to the avoidance situation, and the reference to
national law provisions will take place in accordance with the relevant conflict of law
rules.[401] Instances of issues not explicitly regulated by the Convention which evince close
connection with the problem of contract avoidance and arouse discussion among scholars,
as far as their solution is concerned, are the hardship situation, and the method of setting
interest rates on sums in arrears.
The Convention does not regulate the influence of changed economic
circumstances on a contract. Commentators of the Convention represent divergent
approaches. They propose different methods of interpretation to deal with the case and
offer different solutions. Some support the view that the hardship situation does not
represent a gap to be filled by solutions derived from national law. In their view, the
matter can be solved under the Convention's regulation without damage to the unification
of sales law.[402] According to their opinion, the hardship situation constitutes ground for the
trading partner of a party affected by the changed circumstances to avoid the contract and
deprives him at the same time of the right to claim the performance as agreed to in the
contract.[403] On the other hand, as these authors see it, the party influenced by the changes
would not have the right to avoid the contract.[404] Generally speaking, the change of
circumstances could be considered, in the view of these authors, as an impediment and the
case could be viewed in the context of article 79 of the Convention.[405]
[page 178]
It is claimed by some authors [406] that application of article 79 to the situation of an
extreme and unforeseeable change in economic circumstances, which could be qualified
under this article as an impediment, is not excluded by the legislative history of the
Convention. The mentioned authors are proponents of the analogy looking for the
solutions in a case of changed economic circumstances.[407] This might result in generating
the situations falling within the scope of conditions underlying the grounds for avoidance
of the sales contract according to the provisions of the Convention.
On the other hand, there is another quite different approach to search for a mode
to solve the question. There is strong opinion against analogous application of article 79
to the situation where the performance can be rendered, even if it is difficult to do so.
The opinion is supported by the argument that the article does not cover such situations
and, at the same time it creates in reference to the cases it covers a balance between
contractual justice and security of the transaction.[408] Moreover, the good faith notion and
justification of its application as a basis for a prospective solution is also questioned. It
would facilitate reference to solutions existing in a judge's [page 179] national legal system.[409] This
would destroy the harmony of solutions that the Convention seeks to achieve. In words of
the author representing the opinion, "the principle of good faith must not be used to
bypass explicit provisions of the Convention."[410] The author also negates reference to
national law on the basis of conflict of law rules, which might happen as a result of
reasoning that the case of changed circumstances is governed, but not expressly settled by
the Convention.[411] Such an approach would jeopardize the uniformity the Convention is
designed to achieve. In the author's opinion, the issue of changed economic circumstances
is set aside by the Convention. Therefore, the solutions should be reached on the basis of
a comparative law approach.[412] The recommended solution should represent the balance
between the two fundamental principles that govern the issue of exemption from liability in
international commercial law, namely, security of a transaction and contractual justice.[413]
Although the approach proposed above surpasses the proposal of the Convention
concerning interpretative methods included in article 7 to the case discussed, avoidance
may come into play as a remedy here as well, depending on the circumstances of a
particular situation.
Another problem related to avoidance requiring application of interpretative rules
written in article 7 is the issue of amount of interest rates payable on any sum which is in
arrears.[414] The problem of the obligation to pay interest may appear in case of avoidance
and this could concern different sums. Among other obligations, the seller is bound to
refund the price to the buyer if restitution of the goods takes place; additionally, he is
obliged to pay interest from the date on which the price was paid.[415] As the [page 180] Convention
stipulates only the right to interest (commentators admit the lack of a provision on rate of
interest), how the rate should be determined or over what period of time it is payable
constitutes a gap in the Convention.[416] Under the guidance of article 7, however, a diversity
of proposed solutions exists. Some authors argue for a uniform approach in solving the
issue without reference to domestic law.[417] Others claim the justification of applicability of
national law is indicated by the rules of private international law.[418]
[page 181]
These are not the only gaps in the regulation of problems referring to the remedy of
avoidance under the Convention. Unsolved questions within the scope of the effects of
avoidance might be pointed out.[419] In such situations, article 7 and its role must not be
forgotten in order to support the superior aims of the Convention.
C. Interpretation of contract and the remedy of avoidance
From the set of articles included in the general provisions of the Convention,
article 8 deserves attention when speaking about grounds for avoidance, exercise of the
right and its effects on the situation of the parties. This is so, because, for the purposes of
the Convention, article 8 consists of rules governing the interpretation of statements and
other conduct of a party.[420] It is commonly accepted in literature, that it pertains not only to statements and conduct of the parties which took place before the conclusion of a contract, but also to the statements and conduct displayed after its conclusion, in order to verify how the rights of the parties, defined under the contract, have been influenced by this conduct.[421] Moreover, the rules prescribed in article 8 are applied to acts such as a notification [page 182] that the goods are defective,[422] setting of an additional period for delivery,[423] the act of avoidance of a contract,[424] the restitution of supplies and expenses in a case of avoidance of a contract,[425] if parties in derogation from the Convention [426] provided for the acts in a different way in their contract.[427]
Some acts, defined in the Convention, are assumed by its provisions to be
interpreted in a given way. Article 48(3) contains such an assumption, namely, that in
circumstances described under paragraph (1) of the article,[428] the notice sent by the seller to
the buyer, that he will perform within a specified period of time, requests the buyer to
make known whether he will accept the performance. Such provisions are said [429] to
constitute dispositive rules, which produce an effect when parties did not express in a
separate statement an intent different than the one adopted in the provision. [page 183] Otherwise, the
party making the statement required under the Convention, could not intend differently
than it is assumed and the addressee of the statement could not have interpreted it in
another way.[430]
The first of the interpretative rules of article 8 recommends the subjective test to the
statements and conduct of a party. In the wording of paragraph (1), the acts ought to be
interpreted in accordance with the party's intent where the other party knew or could
not have been unaware what that intent was. Another rule suggests that, if the subjective
test does not work, the objective test is to be applied. It means that acts of a party and
other conduct are to be interpreted in such a manner that a reasonable person of the same
kind as the other party would understand it in the same circumstances.[431]
Thus, the entitlement to contract avoidance would require the evaluation of the
rights of a party vested in her within the scope of the existing contractual obligation,
taking into account statements written in a contract, statements and other conduct made
during the performance of the contract,[432] or acts made when the performance has failed.[433] It is worth [page 184] underlining that, in a moment of exposition to the danger of a dispute over the
interpretation of the contract and other acts of the parties, the relevant time will be the
time the acts took place and the meaning attached to them by each party at that time.[434] The
party who makes the statements bears the burden of proof that the other party knew or
could not have been unaware of the first party's intent. As the case may be, the party
would have to prove that a reasonable person of the same kind as the other party, in the
same circumstances, would have an understanding conforming to the first party's intent.[435]
Possible failure to prove this may effectively influence the entitlement to exercise any right
under the contract, including the right to avoidance.
D. Usages and contract avoidance
The Convention defines the criteria that make it possible to determine which
usages are binding on the parties to a contract. It also helps to establish the position of
usages in reference to the contract and uniform law in case the contract or the
Convention contains provisions conflicting with the rule of a usage. The Convention
allows the parties, under article 9(1), to be bound by any usages to which they have agreed
and by any practices which they have established between themselves.[436] A usage may be referred to in the parties' agreement explicitly or the agreement on it may be implied.[437] [page 185]
Article 9(2) is the basis for the assumption that a usage supplements the contract
independently of the parties intentions, unless the parties decided on the priority of a
contract and expressly excluded the usage. This paragraph defines precisely the
requirements for a usage to allow its implicit application, although the concept of a usage
is not defined under the Convention regulation.[438] A usage, applied to an international sales
contract in international trade, has to be widely known and regularly observed in the
particular trade concerned by the parties to a given type of contract, so that it becomes
one of the contractual expectations of the parties.[439] However, the question of validity of a
usage is not dealt with under the Convention regulation as it is stated within the
reservation made under article 4(a). Thus, the issue will be referred for solution to
domestic law applicable to a contract as indicated by the rules of private international law
of the forum.[440]
The Convention acknowledges two roles to be fulfilled by a usage, which are
important in the light of consideration of the remedy of avoidance, its grounds and effects.
A usage, as recognized in article 8(3), serves [page 186] the interpretation of the statements of the
parties and their other conduct during the performance of the contract.[441] It also plays a
normative role supplementing the provisions of a contract and constituting an additional
source of the rules of conduct, as provided under article 9 of the Convention. A given
practice of conduct established in business relations of the parties is automatically
applicable fulfilling the same role as a usage, namely supplementing the terms of a contract
(according to article 9) and assisting in determination of the parties intent (article 8(3)).[442]
The practice refers to individual aspects of the contract which are not expressly regulated,
and to matters which the practice may refer, embracing such questions as how documents
are presented, the regulation of non-conformity, regulation of certain tolerance for non-observance of statutory or contractual time requirements, for quantitative or qualitative
defects of delivered goods, the granting of a price reduction, or notice procedures.[443]
When one of the trade terms from INCOTERMS [444] is invoked by the parties to a
contract, for instance FOB,[445] it will be treated as a special term and it will have priority over the Convention and the applicable national [page 187] law [446] as to the matters regulated within the
scope of this usage. As a rule, such a commercial term defines: a) time, place and mode of
delivery (transportation); b) the division of costs related with performance of the contract
(freight, costs of various certificates which have to be taken into account in price
calculation); c) the division of risk connected with the loss or damage of the goods (this is
related indirectly with insurance costs which influence price calculation) and; d) issuance
and delivery of various documents without which goods or payment cannot be transferred
across the border. The term includes only rules determining the conduct of parties to the
international sales contract in usual (normal) trade conditions and good (normal) state of
relations between the parties. INCOTERMS do not define liability of parties for breach of
contract. Therefore, the Convention regulation will not be excluded completely and its
application will be indispensable when a dispute arises as to the non-performance of
obligations resulting from the concluded contract.
Thus, usages may impose on the parties duties different from these foreseen by the
Convention's provisions or impose auxiliary duties. The conduct of the parties (affected
by usages) would have to be evaluated in the light of these duties in order to decide
whether the performance was duly made, or whether there is non-performance of the
contract, which would justify the operation of the Convention's provisions on remedies,
including the avoidance of the sales contract.
E. Conclusions
Regulation of the remedy of avoidance under CISG, including its grounds, exercise
and effects are subject to the general provisions of the Convention. The remedy has to be
viewed in the light of these provisions; they should not be omitted in any particular case
where avoidance is considered as the applicable remedy to protect the interest of a party.
Article 4(a), in conjunction with the issue of the remedy of avoidance regulated in another
part of the Convention, reveals some problems. After analysis of the article displayed in
scholarly writings (in the English [page 188] language), and consideration of the remedy as regulated
under the Vienna Convention, one may be tempted to conclude that two meanings can be
attached to the term "avoidance" - narrow and broad. In its narrow meaning, the term
would pertain to an "early end" of a (valid) contract as an effect of the disturbances of a
fundamental character in its performance. Avoidance in this meaning would imply a
remedy exercised in case of liability of a party for breach of obligations arising from the
contract. The Convention's regulation, with reference to the term understood in this way,
determines the grounds for the remedy, effects of the exercise of the right and its
limitations. The only exception would be those issues related to the remedy which are not
regulated under the Convention and cannot be solved in accordance with interpretative
guidance provided in article 7, but have to be referred to national law for solution (for
instance, detailed questions concerning interest rates).
In its broad interpretation, the term additionally would embrace the effects of a party's
behavior at the stage of contract formation (such as fraud, duress, etc.), and the effects of
other objective obstacles which occur at this stage, for which the Convention explicitly
refers to national law for evaluation under the general heading "validity" in article 4(a).
Leaving out scholars' dispute over the interpretation of the term "validity," the effects of a
contract concluded in such circumstances under national law are termed in different ways
depending on the system, such as: contract void, voidable, annulled, invalid, invalidated,
rescinded, revoked, unenforceable. Commentators of article 4(a) use the term "contract
avoided"[447] also in this context. The term is more general ("avoidance" is an "overly-abstract" concept) [448] and impliedly embraces all the mentioned remedies irrespective of
whether the contract comes to an end due to the operation of national law or due to an act
of a party entitled under the law.
In both meanings, the narrow and the broad one, the remedy would denote an end
to a contract and have retrospective effects. The main difference concerns the grounds for
its operation and this is undeniably related to the various functions it serves. First, it
serves as a remedy protecting the interests of the aggrieved party in case of a fundamental
breach of contract by the other. Second, it serves as a remedy whose operation is justified
by [page 189] "validity reasons" defined in applicable national law in order to protect, for the most
part, interests and values reflected in public policy standards of a given State. This
functional difference is so profound that it might even act against making any trial to
construe the broad meaning of the remedy.
However, for those authors who are proponents of the idea that the CISG,
together with its regime on remedies, replaces in particular the national validity regulations
stating effects of the error and misrepresentation concerning the quality of the goods, this
divergence of functions does not have so enormous a significance. It gives way to the
aims that the Convention is to serve in international commerce and the role with which it
is burdened to fulfill. Depending on the situation, the authors' approach would result in
the replacement of the competing remedy of avoidance defined under national law on the
grounds of validity reasons by the remedy of avoidance operating on the CISG grounds
for fundamental breach of contract. The commentators of the Convention are not
unanimous in the question of priority of its provisions and system of remedies, including
avoidance, over the provisions of applicable national law on validity issues. The
formulation of article 4(a) in any way clarifies the problem. On the other hand, it allows a
tribunal to chose for application a national rule of validity which would compete with a
remedy of avoidance provided by the Convention as a rule on which a solution of a case
could be based, the more that parties to the contract may be interested in a wide range of
remedies. That is why H. E. Hartnell's standpoint on the existing requirement of balancing
the needs of a state's public policy and the needs of international legal commerce by
adjudicators is extremely justified, especially in a case where contract avoidance is a
prospective remedy to be applied for its solution.
Article 4(a) brings one more problem in the light of the consideration of the
remedy of avoidance. It influences the remedy of avoidance in a significant way, namely by
authorizing the application of domestic rules controlling unfair (negotiated and
non-negotiated) disclaimers of liability or disclaimers of remedies. The Convention
formally allows parties to extend or to narrow the grounds for the application of the right
to avoidance and to introduce other limitations imposed on the right. However, the clauses
which would be the basis for extremely disadvantageous position of one party within the
system of remedies under the contract are subject to the domestic validity provisions.
The interpretation of operative provisions of the Convention ruling the grounds,
exercise and various limits imposed on the right to avoidance [page 190] has to be pursued in the light
of the general duty of observance of good faith expressed in article 7 CISG. This means
that the remedy of avoidance under the Convention has to be perceived in an autonomous
way without attaching to it the meaning of a counterpart remedy existing in a given
national law, keeping in mind the international character of the regulation and the need to
promote uniformity in its application. Since many questions concerning the remedy of
avoidance are not answered explicitly in the Convention's regulation, the article contains
helpful guidance indicating that the questions should be settled, first in conformity with the
general principles on which the Convention's regulation is based and, in the absence of
such principles, in conformity with the national law indicated by the rules of private
international law. The principles extracted by commentators of the Convention which
might be applied in order to fill gaps in the regulation of avoidance or support its
mechanism are numerous. Among them, the principle of good faith plays a special role in
contributing to a more precise definition of standards of expectations towards the conduct
of the parties in international trade where a particular case will be submitted for evaluation
under CISG provisions on avoidance. Paradoxically, interpretation of issues related with
contract avoidance which are not solved explicitly under the Convention and have to be
referred to applicable national law present a rather difficult task, especially in the light of
the Convention's aim to strive towards predictability of solutions under it and to achieve
uniformity in its application. This might be supported by diversity of opinions of CISG
commentators in the solution of particular related-with-avoidance issues which are not
solved in its regulation and cannot be solved on the basis of its general principles.
The impact of articles 8 and 9 of the Convention on the right to avoidance cannot be
overlooked either. Article 8 would have to be taken into account to verify how the right
under the contract has been influenced by the statements and other conduct of the
parties made also after conclusion of the contract. The article also serves the interpretation
of those provisions of the contract which define in a different way the rights and
obligations of the parties (including contractual provisions on the remedy in case of the
breach of contract) than the Convention does. The exercise of the right to avoidance by
the entitled party would have to be viewed in the light of all the statements and conduct of
the parties interpreted in accordance with recommendations included in
the provisions of article 8. The applicability of usages to the contractual relationship of the
parties by power of article 9 CISG may also result in change of the position of a party
under the contract [page 191] as far as his duties and obligations are concerned, thus affecting
the exercise of any right under it, including the right to avoidance.
The impact of the general provisions of the Convention on avoidance testifies that solving
particular cases under the Convention's regulation requires getting acquainted with the full
text of the regulation, to know the spirit behind it and its particular provisions. This shows
complexity of the whole mechanism of the regulation of one of the remedies provided
under the Convention.[page 192]
| Am. J. Comp. L. | American Journal of Comparative Law |
CC |
Polish Civil Code |
Convention |
United Nations Convention on Contracts for the International Sale of Goods (Vienna, 11 April 1980) |
1978 Draft |
Draft Convention on Contracts for the International Sale of Goods approved by the UNCITRAL |
Georgia L. R. |
Georgia Law Review |
Harvard L. R. |
Harvard Law Review |
| I.L.M. | International Legal Materials |
| INCOTERMS | International Commercial Terms |
Int'l & Comp. L. Q. |
International and Comparative Law Quarterly |
| Int'l Tax & Bus. Law. | International Tax and Business Lawyer |
J. Bus. L. |
Journal of Business Law |
J. Con. L. |
Journal of Contract Law |
L. Q. R. |
Law Quarterly Review |
Liverpool L. R. |
Liverpool Law Review |
OSNCP |
Zbior Orzeczen Sadu Najwyzszego, Orzecznictwo Izby Cywilnej Sadu Najwyzszego (The Judgements of the Highest Court in Poland) |
P.P. |
Panstwo i Prawo |
ULIS |
Convention Relating to a Uniform Law on the International Sale of Goods with the annex (The Hague, 1964) |
|
UNCITRAL |
United Nations Commission on International Trade Law |
|
Vanderbilt J. Trans, L. |
Vanderbilt Journal of Transnational Law |
Yale J. Int'l L. |
The Yale Journal of International Law |
FOOTNOTES
* LL.M. Pallas Programme 1996/1997 on European Business Law organized within the framework of cooperation between the Universities of Barcelona (Spain), Bologna (Italy), LUISS (Italy), Lyon 3 (France), Essex (Great Britain), Konstanz (Germany) and Nijmegen (Netherlands). This article is dedicated to Ms. Ineke Wackers. The author would like to thank Mr. Albert Kritzer for his valuable comments which contributed to the present version of the work.
1. United Nations Convention on Contracts, April 11, 1980, U.N. Doc.A/CONF. 97/18, Annex I, reprinted
in 19 I.L.M. 668 [hereinafter CISG, Vienna Convention or the Convention].
2. P S. Atiyah, An introduction to the law of contract 339 (1995).
3. Uniform Law on the International Sale of Goods (1964), reprinted in 3 I.L.M. 855 (1964) [hereinafter
ULIS].
4. See Draft Convention on the International Sale of Goods, VII UNCITRAL 1976, 89, 91, U.N.
Doc.A/CN.9/116, Annex I (United Nations, New York 1977), (before the formation of contracts on
international sale was incorporated into the Convention) reprinted in John Honnold, Uniform Law for
International Sales under the 1980 United Nations Convention, (2nd Ed. 1991) at Appendix C.
[hereinafter referred to as the 1978 Draft].
5. G. H. Treitel, Remedies for Breach of Contract 318 (1991).
6. See 7 G. H. Treitel, International Encyclopaedia of Comparative Law, ch. 16, at 3 (1976); E.
E. Bergsten, The Law Of Sales In Comparative Law, in Les Ventes Internationales de
Marchandises, Economica Collection 7 (1981).
7. See id.
8. For the critical discussion of terminology, see Treitel, Remedies for Breach of Contract, supra
note 5, at 319-320; see Atiyah, supra note 1, at 398-403; R. Goode, Commercial Law 84 n.61 (1995);
see also S. Michida, Cancellation of Contract, 27 Am. J. Comp. L. 279 (1979); F. A. Miniter, Buyer's
Right Of Rejection Under The Uniform Commercial Code And Recent International Developments, 13
Georgia L. Rev. 838 (1979).
9. Kodeks Cywilny, Ustawa z dnia 23 kwietnia 1964 r., Dz. U. Nr 16, poz. 93 z pozn.zm. [The Polish
Civil Code of 23 of April 1964 - The Journal of Laws of the Republic of Poland 1964 with later
amendments] [hereinafter referred to as CC].
10. CC art. 491.
11. ULIS arts. 43 and 62.
12. CISG arts. 49 and 64.
13. Fritz Enderlein & Dietrich Maskow, International Sales Law, United Nations Convention
on Contracts for the International Sale of Goods - Convention on the Limitation Period in
the International Sale of Goods 340 (1992).
14. See Fritz Enderlein, Rights and Obligations of the Seller Under the UN Convention on Contracts for
the International Sale of Goods, in International Sale of Goods - Dubrovnik Lectures 195 (Petar
Šarcevic and Paul Volken eds. 1996); Denis Tallon, Effects of Avoidance, in Commentary on the
International Sales Law, The 1980 Vienna Sales Convention 602 (C. M. Bianca & M. J. Bonell
eds., 1987) [hereinafter Commentary on the International Sales Law].
15. Enderlein & Maskow, supra note 13, at 15; other terms of this nature are "to deliver", "to take
delivery," "to take over." See id.
16. Such an interpretation is called "original" by the international legal doctrine. Id. See also John O.
Honnold, Uniform Law for International Sales under the 1980 United Nations Convention
60 (1987) [hereinafter Honnold, Uniform Law]; M. J. Bonell explains that content and formal
presentation of the Convention is the result of considerations between lawyers representing different
cultural and legal backgrounds. Drafting the particular provisions they had to adopt such neutral language
upon which they could reach an agreement. See Michael .J. Bonell, Interpretation of the Convention,
in Commentary on the International Sales Law, supra note 14, at 74.
17. It is rightfully admitted "That in view of the high differentiation in national legal languages, this goal
could not consistently be reached as new adequate terms may not be found for all legal problems or the
originality obtained be lost again with the translation." See Enderlein & Maskow, supra note 13, at 15.
An example is the text of the Convention in the Polish language where the term "avoidance" sticks to the
Polish terminology maintained in the Civil Code -- "odstapienie od umowy". The Journal of Laws of the
Republic of Poland, no. 45, 1997, item 286. For the purposes of this dissertation, I will use the term
"avoidance" considering provisions of the Convention and the term "renouncement" while discussing
regulation included in the Polish Civil Code.
18. See Enderlein & Maskow, supra note 13, at 15; Michael .J. Bonell, Interpretation of the
Convention, in Commentary on the International Sales Law, supra note 14, at 74.
19. Franco Ferrari, Specific Topics Of The CISG in light of judicial application and scholarly writing,
in: 10 Preadviezen, uitgebracht voor de Vereniging voor Burgerlijk Recht 86 (1995). Compromise is one
of the two types of legislative agreements, which embraces the technical formulation of a text, concerns
the language of the rule. Consensus, another one, is achieved on the meaning of a rule -- on a practice or
norm or a principle underlying different national rules. Unification and Certainty: The United Nations
Convention on Contracts for the International Sale of Goods, 97 Harvard L. R. 1986 (1983-84).
20. The United Nations Conference on Contracts for the International Sale of Goods was held in Vienna,
from 10 March to 11 April 1980. It approved the UN Convention on Contracts for the International Sale
of Goods. See supra note 1.
21. ULIS Arts. 25, 26(1),(2), 30(1),(2), 61(1),(2) and 62(1).
22. Art. 10 ULIS defines a fundamental breach in terms whether the party knew, or ought to have known,
that a reasonable person in the same situation as the other would not have entered into the contract if he
had foreseen the breach and its effects. For a thorough discussion of the concept of fundamental breach
under ULIS regulation, see Treitel, Remedies for Breach of Contract, supra note 5, at 365-366;
Ipso Facto Avoidance In The Uniform Law On The International Sale Of Goods (ULIS): Report of the
Secretary-General A/CN.9/WG.2/WP.9), in J. O. Honnold, Documentary History of the Uniform
Law for International Sales 88-90 (1989) [hereinafter Documentary History].
23. ULIS arts. 26(1), 30(1), 62(1) and 66(1).
24. ULIS arts. 26(3), 30(3), 44(2) and 62(2).
25. During the works of UNCITRAL on ipso facto avoidance, the system of Anglo-American law was
meant to apply, according to the buyer's normal remedies, when the seller fails to deliver the goods in time
or there is a claim for damages. As far as a right to specific performance is concerned, it is granted only
under special circumstances which was intended to be reflected under ULIS, art. 25. J. Hellner, Ipso
facto Avoidance, in Privatautonomie, Eigentum und Verantwortung, Festgabe für Hermann
Weitnauer zum 70 Geburstag 89 (1980).
26. With the exception of ULIS arts. 25 and 61 which apply in cases of fundamental as well as non-fundamental breach of contract.
27. ULIS art. 26(1).
28. ULIS art. 30(1).
29. ULIS art. 27(2).
30. ULIS art. 62(1).
31. ULIS arts. 26(3) and 30(3).
32. ULIS art. 43.
33. ULIS arts. 27(2) and 31(2). Failure to deliver in such a case constituted a fundamental breach of the
contract (transformation of a non-fundamental breach into a fundamental one). According to F. A
Miniter, in this way the buyer's right of avoidance under ULIS was limited to fundamental breaches. See
Miniter, supra note 8, at 839. However such a transformation of not serious default into a serious one
seems to be artificial and not justified in all situations.
34. ULIS arts. 26(3), 30(3), and 44(2).
35. ULIS art. 62(2).
36. ULIS art. 39.
37. ULIS art. 45(1).
38. ULIS art. 45(2).
39. Avoidance did not result in a nullity of the contract, which did not cease to be in force. See Hellner,
supra note 26, at 92.
40. ULIS art. 81.
41. See Treitel, Remedies for Breach of Contract, supra note 5, at 382.
42. ULIS art. 84.
43. A right to require performance and a right to declare the contract avoided. Art. 26(1) ULIS.
44. ULIS art. 25.
45. See Treitel, Remedies for Breach of Contract, supra note 5, at 382.
46. Treitel thinks that requirement of fault is not justified in order to exercise the right of avoidance as it is
in case of a claim for damages, because these remedies differ not only in their consequences, but also in
the grounds on which they can be claimed. Treitel, Remedies for breach of contract, supra note 5,
at 348-349.
47. ULIS art. 74.
48. ULIS art. 74(3).
49. F. A. Miniter considered the regulation concerning avoidance under ULIS not flexible and creating
sophistication . See Miniter, supra note 8.
50. See Enderlein & Maskow, supra note 13, at 191; Victor Knapp, Right to Avoid Contract, in
Commentary On The International Sales Law, supra note 14, at 466.
51. The case, in which the seller having not received any request for performance from the buyer
nevertheless performs the contract after the time, when the contract was avoided ipso facto, would be
regulated by the provisions of art. 26(1) and (3) ULIS which seemed to be contradictory. However Hellner
considered, that the result they produced according to the literal interpretation (ipso facto avoidance
occurs only when the buyer has not made known his decision - paragraph. (1); the buyer has to declare the
contract avoided if he does not want to accept goods that have been delivered, even late, in fulfillment of
the contract - para. (3)) did not contradict the definition of avoidance in ULIS. Hellner, supra note 26, at
93.
52. See Michael Will, Right to Avoid Contract, in Commentary on the International Sales Law,
supra note 14, at 360.
53. ULIS art. 61 was a counterpart of it.
54. Ipso facto avoidance in the Uniform Law on the International Sale of Goods (ULIS): Report of the
Secretary-General (A/CN.9/WG.2/WP.9), in Honnold, Documentary History, supra note 22 at 90.
55. See Michael Will, Right to Avoid Contract, in Commentary on the International Sales Law,
supra note 14, at 361.
56. ULIS art. 26 (1), art. 30 (1), art. 62 (1).
57. ULIS art. 26 (2), art. 30 (2).
58. It was described also as "troublesome". See E. Allan Farnsworth, Problems of the Unification of Sales
Law From the Standpoint of the Common Law Countries, in 7 Digest of Commercial laws of the
world, 16 (1980).
59. Arguments for and against ipso facto avoidance were considered in Ipso Facto Avoidance in the
Uniform Law on the International Sale of Goods (ULIS): Report Of The Secretary-General
(A/CN.9/WG.2/WP.9) in Honnold, Documentary History, supra note 22, at 85-86.
60. Political and other reasons - Muna Ndulo, The Vienna Sales Convention 1980 And The Hague Uniform
Laws On International Sale Of Goods 1964: A Comparative Analysis 38 Int'l & Comp. L. Q. 33-34
(1988).
61. John O. Honnold, The Draft Convention on Contracts for the International Sale of Goods: An
Overview, 27 Am. J. Comp. L. 223, 228-229 (1979).
62. See 1978 Draft, supra note 4.
63. 1978 Draft, supra note 4, arts. 45(1)(a),(b), and 60(a),(b).
64. Art. 23 of the 1978 Draft provides that the breach is fundamental if it results in substantial detriment to
the other party, unless the party in breach did not foresee and had no reason to foresee such a result.
65. ULIS art. 28.
66. 1978 Draft, supra note 4, art. 66(1).
67. 1978 Draft, supra note 4, art. 66(1).
68. 1978 Draft, supra note 4, art. 67(1).
69. ULIS art. 79(1).
70. 1978 Draft, supra note 4, art. 67(2); ULIS art. 79(2).
71. 1978 Draft, supra note 4, art. 67.
72. 1978 Draft, supra note 4, art. 68; ULIS art. 80.
73. 1978 Draft, supra note 4, arts. 66(2) and 69(2).
74. ULIS arts. 78(2) and 81(2).
75. R. Herber contends that the 1978 Draft enlarged the possibility of the buyer to declare the contract
avoided in case of delivery of non-conforming goods, even if the lack of conformity did not constitute a
fundamental breach of contract, after having fixed an additional period for cure. For the reasoning of the
author, see R. Herber, The Rules of the Convention Relating to the Buyer's Remedies in Cases of
Breach of Contract, in 7 Digest of Commercial Laws of the World 122-124 (1980).
76. CC art. 487, para. 2, defines a synallagmatic contract as one in which both parties are obliged in such a
way, that the performance of one party is the equivalent of another.
77. A. Szumaski, Renegocjacja Umów w Midzynarodowym Obrocie Gospodarczym
[Renegotiation of Contracts in International Economic Turnover] 51-60
(1994).
78. W. Czachórski, Zobowizania - zarys wykadu [Obligations - Outline of Lectures] 128
(1994); J. Rajski, Prawo o Kontraktach W obrocie Gospodarczym [Law of Contract in
economic turnover] 159 (1994).
79. The parties are free to stipulate that the right may be exercised within a given time before the contract
has been performed or after its performance, for instance, within a week after taking the delivery of the
goods and payment of the price. See Rajski, supra note 76, at 160; Czachórski, supra note 76, at 129.
80. In professional practice such a stipulation happens more often than the plain renouncement stipulation.
See Rajski, supra note 76, at 161.
81. See Czachórski, supra note 76, at 130; Rajski, supra note 76, 162.
82. G. Bieniek, H. Ciepla, St. Dmowski, Komentarz do Kodeksu Cywilnego, Zobowizania,
[Commentary on Civil Code, Obligations] Tom I, 463 (1996).
83. See Czachórski, supra note 76, at 130.
84. See ICC Ct. of Arb. [7660] (1994), wherein the Tribunal stated that, when the goods are machinery,
partial avoidance of the contract (art. 51(1)) can be granted when the lack of conformity relates to an
independent part of the goods sold. This requirement was fulfilled in the case at hand as the non-conforming part was a piece of equipment replaceable without prejudice to the workability of the
machinery as a whole and to the continuation of the contract. See the UNILEX Database on International
Case Law & Bibliography on the UN Convention on Contracts for the International Sale of Goods, edited
by Professor M. J. Bonell, from the Italian National Research Council [hereinafter UNILEX]; see also the
Pace University School of Law CISG Database [hereinafter (PACE)] (last modified, September 21, 1999)
<http://cisgw3.law.pace.edu> at <http://cisgw3.law.pace.edu/cases/947660i1.html> (PACE).
85. See Michael Will, Partial Non-Performance, in Commentary on the International Sales Law,
supra note 14, at 378.
86. See Enderlein & Maskow, supra note 13, at 201; Honnold, Uniform Law, supra note 59, at 332;
Barry Nicholas, The Vienna Convention on International Sales Law 105 L. Q. R. 228 (1989); Michael
Will, Early Delivery and Excess Quantity, in Commentary on the International Sales Law, supra
note 14, at 381.
87. See Honnold, Uniform Law, supra note 16, at 402.
88. See Enderlein & Maskow, supra note 13, at 291.
89. See id.; see examples of insufficient ability to perform. Id. at 286.
90. See id. at 291.
91. According to H. T. Bennett, the lack of assurance of performance in response to a notice makes it clear
that the breach will occur. Trevor Bennett, Avoidance for Anticipatory Breach, in Commentary on
the International Sales Law, supra note 14, at 528. P. Schlechtriem is of the opposite opinion. P.
Schlechtriem, Uniform Sales Law, The UN-Convention on Contracts for the International
Sale of Goods 96 (1986) [hereinafter Schlechtriem, Uniform Sales Law].
92. See Enderlein & Maskow, supra note 13, at 296.
93. See Trevor Bennett, Avoidance of Instalment Contracts, in Commentary on the International
Sales Law, supra note 14, at 536.
94. See id.
95. See P. Schlechtriem, Some Observations On The United Nations Convention on Contracts for the International Sale of Goods, in 2 The Frontiers of Liability 32 (1994) [hereinafter Schlechtriem,
Some Observations].
96. See Enderlein & Maskow, supra note 13, at 295.
97. See id.
98. See id. at 199; Trevor Bennett, Avoidance of Instalment Contracts, in Commentary on the
International Sales Law, supra note 14.
99. See Trevor Bennett, Avoidance of Instalment Contracts, in Commentary on the International
Sales Law, supra note 14, at 537. However, some authors admit that in case of art. 73(1) the setting of a
Nachfrist in respect of an installment is also possible. This would blur the difference between the two
articles. See Enderlein & Maskow, supra note 13, at 295.
100. The passing of risk may also be regulated by trade usages like INCOTERMS.
101. See Enderlein & Maskow, supra note 13, at 279.
102. See id. at 281.
103. In other words, conclusive for the exercise of the right will be the assertion of the fact whether the
serious defect in delivery, which does not influence the passing of risk, can be attributed to the seller.
104. See Honnold, Uniform Law, supra note 16, at 427; Enderlein & Maskow, supra note 13, at 332;
Denis Tallon, however, has critical remarks about justification to claim avoidance in different variants of
the situation (definitive non-performance of the contract, partial non-performance). Denis Tallon,
Exemptions, in Commentary on the International Sales Law, supra note14, 588-89.
105. See Enderlein & Maskow, supra note 13, at 318.
106. The Polish Civil Code differentiates accessibility of remedies and also the remedy of renouncement,
with regard to the fact if the non-performance was or was not caused by the party in breach. The delay due
to the circumstances not caused by the party in breach, termed "opóznienie" (simple delay), does not lead
to special legal effects. The party in delay is still obliged to perform after the reasons of delay, for which
he is not liable, are extinguished; additionally, the buyer has to pay interest accrued during delay on the
sum due. The parties may, however, agree in the contract on special effects connected with the simple
delay related, for example, with the obligation to perform at the date fixed. The remedy of renouncement
can be exercised only in a case of delay for which the party is responsible. Such delay is termed "zwloka"
(grave delay) under CC art. 476. The right on this ground is available only in synallagmatic contracts as,
according to the general principle of contract performance, the delay does not authorise a party to
renounce a contract. Czachórski, supra note 76, at 245.