4B [Scope of Convention (issues excluded): assumption of liability];
18A3 [Acceptance (time and manner): silence or inactivity insufficient];
19C [Acceptance with modifications that are material: material modification of offer if related to price of goods];
74A [Damages (general rules for measuring): loss suffered as consequence of breach (interest as element of loss)];
78B [Interest on delay in receiving price or any other sum in arrears: rate of interest (applicable domestic law)]