18A2 [Acceptance (time and manner): criteria for acceptance (conduct constituting acceptance)];

33C [Time for delivery (when date not fixed by or determinable from contract): reasonable time after contract's conclusion];

39A2 [Requirement to notify seller of lack of conformity: Buyer must notify seller within reasonable time];

47A [Buyer's right to fix additional final period for performance];

74A [General rules for measuring damages: loss suffered as consequence of breach];

75A2 [Damages established by substitute transaction after avoidance: repurchase by aggrieved buyer];

77A [Obligation to take reasonable measures to mitigate damages]