Classification of issues using UNCITRAL classification code numbers:
54A1 [Obligations of the buyer: obligation to pay price
includes enabling steps (arranging for letter of credit)];
69D [Passage of risk: impact upon buyer's obligation to pay damages during
prolonged deposit of goods by buyer];
74A [Damages (general rules for measuring); loss suffered as consequence of
breach (expenses incurred by seller in deposit of goods];
77A [Obligation to take reasonable measures to mitigate damages: measures to
preserve the goods and to sell perishable goods may also be required, even
where a contractual duty to take such measures does not exist under Arts. 85
to 88];
78B [Interest on delay in receiving price or any other sum in arrears: rate
of interest];
79B [Exemptions (impediment excusing party from damages): suspension of
payment of foreign debts by buyer's government not regarded as a qualifying
exemption]
|
7C23 [Gap-filling by domestic law: penalty clauses];
54A1 [Obligations of the buyer: obligation to pay price
includes enabling steps (arranging for letter of credit)];
69D [Passage of risk: impact upon buyer's obligation to pay damages during
prolonged deposit of goods by buyer];
74A [Damages (general rules for measuring); loss suffered as consequence of
breach (expenses incurred by seller in deposit of goods];
77A [Obligation to take reasonable measures to mitigate damages: measures to
preserve the goods and to sell perishable goods may also be required, even
where a contractual duty to take such measures does not exist under Arts. 85
to 88];
78B [Interest on delay in receiving price or any other sum in arrears: rate
of interest];
79B [Exemptions (impediment excusing party from damages): suspension of
payment of foreign debts by buyer's government not regarded as a qualifying
exemption]