Austria 12 February 1998 Supreme Court (Umbrella case) [translation available]
[Cite as: http://cisgw3.law.pace.edu/cases/980212a3.html]
DATE OF DECISIONS:
JURISDICTION:
TRIBUNAL:
JUDGES(S):
CASE NUMBER/DOCKET NUMBER: 2 Ob 328/97t
CASE NAME:
CASE HISTORY: 1st HG Vienna (17 Cg 168/94a-28) 20 May 1996 [CISG overlooked]; 2d instance OLG Vienna 25 October 1996 [partly reversed]
SELLER'S COUNTRY: Czech Republic (plaintiff)
BUYER'S COUNTRY: Austria (defendant)
GOODS INVOLVED: Umbrellas
AUSTRIA: Supreme Court 12 February 1998
Case law on UNCITRAL texts (CLOUT) abstract no. 238
Reproduced with permission from UNCITRAL
An Austrian buyer, defendant, ordered umbrellas from a Czech seller, plaintiff. The parties agreed to a reduction of the purchase price inasmuch as the goods were defective. However, the buyer did not pay for two subsequent deliveries. Upon the seller's request for payment, the buyer showed the seller a copy of a bank payment order. Then, the buyer cancelled the bank payment order without informing the seller. Lacking liquidity, the seller could neither produce nor deliver goods ordered. The seller, therefore, suspended performance of the contract and sued the buyer. The buyer notified the seller of its compensation claim arising from non-compliance with the contract.
The Supreme Court held that although the contract between the two parties had been concluded before the CISG had entered into force in the Czech Republic, the contract was governed by the CISG under its article 1(1)(b) since the parties had agreed to the application of Austrian law.
The Supreme Court further held that a seller who acts in conformity with a contract may choose between the remedies available under CISG articles 71(1)(a) and 73(2). Neither the fact that the buyer had not paid the purchase price for a number of deliveries nor the cancellation of the bank payment order indicated with a sufficient degree of probability a serious deficiency in the buyer's ability to perform the contract or in its creditworthiness in keeping with CISG article 71(1)(a). The seller's right, therefore, to suspend performance had not been established.
Accordingly, the Supreme Court overturned the decision of the appellate court and remanded the case to the court of first instance for consideration of other issues.
APPLICATION OF CISG: Yes [Article 1(1)(b)]
APPLICABLE CISG PROVISIONS AND ISSUES
Key CISG provisions at issue:
Classification of issues using UNCITRAL classification code
numbers:
6B [Choice of law: choice of law of Contracting State held to be choice of CISG law of that State];
7C [Gap-filling: inappropriate to resort to domestic law to resolve suspension and related avoidance issues as this matter is addressed by articles 71 and 73];
71A11 [Grounds for suspension of performance: serious deficiency in ability to perform or credit-worthiness (not established with sufficient degree of probability)]
73B [Avoidance in installment contracts: refusal of future installments when breach in one installment gives grounds to expect fundamental breach with respect to future installments]
Descriptors:
Excerpts from analysis of Austrian case law by Willibald Posch & Thomas Petz published in the Vindobona Journal.*
* "Austrian Cases on the UN Convention on Contracts for the International Sale of Goods", 6 Vindobona Journal of International Commercial Law and Arbitration (2002) 1-24. The ruling of 12 February 1998 of the Oberster Gerichtshof [Supreme Court] of Austria is analyzed by Posch & Petz at pages 6-7, 16 and 20-21 of this commentary. The commentary also contains other analyses of Austrian case law on CISG issues addressed.]
Choice of law. "In this case of a contract for the sale of sunshades, the Czech manufacturer sought payment of the price by the Austrian buyer who reacted with a claim for damages for defective performance. One of the controversial issues in this case was whether a choice of law clause in favour of 'Austrian law' would entail the application of CISG. In an earlier award of the International Arbitration Tribunal of the Austrian Chamber of Commerce,25 it was regarded as 'self evident'26 that a choice of law clause held in such general terms would result in the application of CISG, which provides the specific rules for international sales contracts in Austrian law. In its 'Czech sunshades' decision, the Austrian Supreme Court came to the same conclusion.27 CISG has become, upon its ratification, an integral part of Austrian domestic law. Therefore, a choice of law clause in an international sales contract using, without any further specification, such broad language as 'Austrian law shall apply' leads to the application of CISG." [pages 6-7]
25. Award No. 4366 [<http://cisgw3.law.pace.edu/cases/940615a3.html>]. See the award of 12 October 1997 rendered by the Exchange of Agricultural Products, published in 1998 [Zeitschrift für Rechtsvergleichung, Internationales Privatrecht und Europarecht] ZfRV, at p. 211.
26. In his comment of this decision, Schlechtriem remarks that this solution not only had become the prevailing one under the Hague Conventions, but also - "undisputedly" - under CISG; see 1995 RIW [Recht der Internationalen Wirtschaft], at p. 593.
27. See also Austrian Supreme Court, 28 April 2000 [<http://cisgw3.law.pace.edu/cases/000428a3.html>] and Austrian Supreme Court, 22 October 2001 [<http://cisgwr.law.pace.edu/cases/011011a3.html>].
Notice of lack of conformity, timeliness. "Th[is] decision … set out the basic lines of how to apply Articles 38 et seq. CISG. However, in the absence of any finding of fact on the timeliness of the notice of lack of conformity, the Court could not decide on the merits, but had to remit the case to the Court of First Instance." [page 16]
Anticipatory breach ; Installment contracts ; Suspension of performance. "[T]he contract between a Czech seller and an Austrian buyer provided delivery of a great quantity of sunshades by instalments. However, because of the buyer's failure to pay for the instalments delivered, the seller stopped further deliveries and declared the contract void. Quite correctly, the Austrian Supreme Court held that in the circumstances of the case, the seller's declaration of avoidance was made too early and that Article 71 CISG applied to the merits of the case. According to this provision, a party to an international sales contract may suspend his performance without declaring the contract void.101
"Furthermore, the Court had to deal with the question of the relationship between Article 71 CISG and the more comprehensive remedies of domestic law which aim at being respected in the same situation, viz., when after the conclusion of a contract, facts become apparent that give rise for reasonable doubt that the debtor will perform his obligations. On this issue, the Court held that Article 71 CISG ruled out the application of any identical or comparable remedies of the particular domestic law that is found applicable under the rules of private international law of the forum. This was particularly true in relation to the question of whether a recourse to the more extensive rights of retention of the domestic law of a Contracting State should be granted.
"Moreover, the Austrian Supreme Court held that suspension of performance under Article 71 CISG not only required the presence of 'serious' circumstances that may prohibit performance, but also of economic difficulties including lack of creditworthiness of the other party. This would be the case if bankruptcy proceedings had commenced, or if the debtor stopped his or her payments or deliveries. However, according to the Court, a delay with a single instalment or a sluggish payment is not sufficient to indicate a serious lack of creditworthiness.102" [pages 20-21]
101. The right of suspension of performance (Article 71) exists independently from the right to avoid a contract (Article 73).
102. As payments for only two instalments were delayed, a serious lack of creditworthiness of the Austrian buyer could not be assumed in the relevant case. The cancellation of an order for remittance does not indicate such a lack of creditworthiness. Consequently, as the requirements of Article 71 CISG were not met, the right to suspend performance could not be granted to the Czech seller. The Austrian Supreme Court was criticised by Karollus in 2000 JBl, at p. 56, for interpreting the relevant criteria of Article 71 CISG too strictly: Bankruptcy proceedings need not be commenced; it should be sufficient that a reason for opening such proceedings exists.
CITATIONS TO OTHER ABSTRACTS OF DECISION
English: Unilex database <http://www.unilex.info/case.cfm?pid=1&do=case&id=385&step=Abstract>
German: Österreichische Zeitschrift für Rechtsvergleichung (1998) 158, No. 36(LS); [1999] Juristische Blätter (JBl) 54-57; [1999] Schweizerische Zeitschrift für Internationales und Europäisches Recht (SZIER)/Revue suisse de droit international et de droit européen 202; [1999] Ecolex - Fachzeitschrift für Wirtschaftsrecht 693
CITATIONS TO TEXT OF DECISION
Original language (German): CISG-Austria website <http://www.cisg.at/2_32897t.htm>; [1998] [österreichisches] Recht der Wirtschaft [örRdW] 335; [1999] Zeitschrift für Rechtsvergleichung, Internationales Privatrecht und Europarecht (ZfRV) 40, 68-70; Unilex database <http://www.unilex.info/case.cfm?pid=1&do=case&id=385&step=FullText>
Translation (English): Text presented below
CITATIONS TO COMMENTS ON DECISION
English: Spanogle/Winship, International Sales Law: A Problem Oriented Coursebook (West 2000) [suspending performance 231-247 (case at 243)] ; Willibald Posch & Thomas Petz, an English translation of the German commentary cited below that has been published in 6 Vindobona Journal of International Commercial Law and Arbitration (2002) 1-24, at pages 6-7, 16 and 20-21. [Go to this commentary in either its English or German text for an excellent comprehensive analysis of Austrian case law on the CISG.]; Bernstein & Lookofsky, Understanding the CISG in Europe, 2d ed., Kluwer (2003) §: 6-26 n.312; [2005] Schlechtriem & Schwenzer ed., Commentary on UN Convention on International Sale of Goods, 2d (English) ed., Oxford University Press, Art. 6 para. 14 Art. 71 paras. 11, 17, 25a Art. 73 para. 28; Schwenzer & Fountoulakis ed., International Sales Law, Routledge-Cavendish (2007) at pp. 30, 496
French: Niessen, Dalloz Sirey: Paris (November 1999) 359-360
German: Posch, [1999] Zeitschrift für Rechtsvergleichung, Internationales Privatrecht und Europarecht (ZfRV) 40, 68-70; Wilhelm, [1999] ecolex - Fachzeitschrift für Wirtschaftsrecht 693; Karollus, [2000] Juristische Blätter (JBl) 56; Willibald Posch & Ulfried Terlitza, Internationales Handelsrecht (2001) 47-56, at relevant pages; Mario Gnesda, Ein kritischer Kommentar, Graz Univ., Dipl.-Arb. (2000) 57 p.
Go to Case Table of ContentsQueen Mary
Case Translation Programme
12 February 1998 [2 Ob 328/97t]
Translation by Dr. Peter Feuerstein [*]
Translation edited by Ruth M. Janal [**]
On 20 May 1995, the Commercial Court Vienna granted the predominant part of
the [seller's] claim (docket no. GZ 17 cg 168/94a-28). Upon the [buyer's]
appeal, the Vienna Court of Appeals affirmed the decision of the Commercial
Court on 25 October 1996 (docket no. GZ 3 R 167/96t).
The Supreme Court, acting as the final appellate court, and composed of its
President Dr. Angst as presiding judge and Dr. Niederreiter, Dr. Schinko, Dr.
Tittel and Dr. Baumann as accompanying judges, sitting in a non-public session
over the matter of Plaintiff U..., Czech Republic, [seller], represented by
Boller, Langhammer, Schubert, Law Offices in Vienna, versus Defendant E... GmbH
[buyer], represented by Weiss-Tessbach, Law offices in Vienna, over a residual
amount of DM [Deutsche Mark] 268,500, has rendered the following
Decision
Regarding the [buyer’s] exceptional appeal:
The appeal is granted and the appealed judgment is set aside. The decision
of the Court of First Instance remains unchanged with respect to the
unappealable part, i.e., regarding its dismissal of the claim where it exceeded
an amount of DM 268,500 plus 5% interest on DM 52,000 since 19 March 1993, DM
45,500 since 16 March 1993, DM 51,300 since 17 March 1993, DM 74,100 since 19
March 1993, and DM 45,600 since 25 March 1993. The other part of the decision
is set aside; to this extent the matter is remanded for a new hearing and
decision to the Court of First Instance.
The costs of the appeal proceedings are to be treated as additional
litigation costs.
Reasons
The [seller] requested from the [buyer] the payment of DM 345,750 for the
delivery of umbrellas during the period August 1992 until March 1993.
The [seller] submits that the deliveries were made on
time and accepted without objections. Should it be proven that deliveries were
not executed, then [seller] claims it had a right to act in this manner. After
several years of smooth cooperation, the [buyer] stopped paying for the
deliveries. For this reason, the [seller] was entitled to an inconnex
retention. Upon the [seller's] enquiries, it learned that the [buyer], having
presented itself at the time of the conclusion of the sales contract as a
flourishing and stable firm with sufficient financial means, had encountered
considerable financial difficulties. This deteriorated financial condition was
not known to [seller] at the time of the conclusion of the contract. By the end
of 1992, there was a balance of payments due to [seller] in the amount of DM
128,169, which -- apart from an amount of DM 254 -- resulted from invoices
issued in the year 1992. Because [buyer] was in default of payment, [seller]
itself had been unable to pay its suppliers, which led to a stop in
deliveries. Already prior to the start of the deliveries for 1993, the [buyer]
was informed that the balance due to [seller] had to be settled prior to a
delivery. In February 1993, [buyer] requested [seller] to technically alter the
already manufactured umbrellas. Due to the default in payment and because of
this request for a modification of the contract, [seller] decided not to
deliver. As the [buyer], in spite of many promises, did not pay the amount due
from 1992, it was [seller's] understanding that the [buyer] was unable to
effect payment. On 24 February 1993, [seller] was incorrectly informed by the
[buyer] that there was an already executed bank payment order in favor of the
[seller]. [Seller] therefore made further deliveries. The payment order,
however, was not executed, because the [buyer] had revoked it. As far as
notices of non-conformity were raised, they referred to deliveries from the
year 1992; but these disagreements had been settled. The [buyer] had
acknowledged the amount in dispute; the first complaints were made on 4 March
1994.
The [buyer] raised the objection that it bought
umbrellas on 18 December 1992 and that the sales contract was a firm bargain,
but the [seller] did not adhere to the time for delivery. Therefore, [buyer]
had to make substitute purchases and had to pay transportation costs and a
penalty. In addition, it suffered a loss of profit. Thus, the [buyer] makes a
counterclaim for DM 622,197.18. At the conclusion of the contract in December
of 1992 concerning the deliveries for the year 1993, it had been agreed that
the [seller] would waive alleged claims of DM 60,685, while the [buyer] would
pay DM 86,616; the parties proceeded in the agreed manner. In the beginning of
1993, the [seller] requested an advance payment of DM 200,000 without a
legitimate contractual basis. The payment was supposed to finance the
production, because the [seller] was experiencing financial difficulties. As
[seller] had threatened to stop deliveries, a compromise between the parties
was reached on 28 February 1993, whereby clause 1.1 of the agreement of
December 1992 was altered in such a way that the [seller] would deliver a total
of 1,500 umbrellas. The [buyer] agreed to an increase of the following delivery
to 4,000 pieces. Due to an envisaged privatization and the [seller's] financial
situation, the [seller] terminated the agreement on 23 February1993; whereas
the [buyer] objected to this measure. Out of the initial 1,500 umbrellas
ordered, 800 were delivered on 26 February 1993, and another 700 on 1 March
1993. In accordance with the order of 23 February 1993, 3,000 pieces were
delivered to a Czech firm in order to exchange the pole tops of the umbrellas.
Due to the unjustified termination, [buyer] informed the [seller] that the
damage [buyer] itself sustained exceeded the [seller's] previous invoices and that [buyer] therefore refused to pay the invoices due. Apart from the damages resulting
from non-delivery, damages were also caused by the defective delivery of the
last mentioned umbrellas, which had wooden poles that were too thin. The
announcement of the bank transfer had been made to keep the [seller] from
declaring an unjustified rescission of the contract; it was correct that the
bank transfer was not executed.
The decision of the Court of First Instance
The Court of First Instance held that [seller's] claim for DM 268,500 was
justified, whereas the [buyer's] counterclaim was not justified. It
consequently handed down judgment against the [buyer] for payment of DM 268,500
plus interest and rejected the other parts of the claim.
Thereby the following findings were made:
Already in the year 1992 the [seller] (having its place of business in the
Czech Republic) sold to the [buyer] (having its place of business in Austria)
market umbrellas which the [buyer] resold. Complaints pertaining to these umbrellas
were received from the [buyer's] customers. These complaints were settled by
the parties in such a way that the [seller], on the one hand, exchanged the
umbrellas delivered to the [buyer's] customers and, on the other hand, granted
the [buyer] a price reduction in the beginning of December 1992. With payment
of DM 86,616 by the [buyer] on 9 December 1992, the parties had agreed that
both the [seller's] invoices for the deliveries from 1992 and the complaints
raised until then were settled.
By agreement dated 7/18 December 1992, the [seller] undertook to deliver the
umbrellas specified in this document. For the delivery of 800 pieces, February
1993 was agreed upon as the date of delivery; for the subsequent installments
certain time periods between 15 and 25 days were agreed upon. Furthermore, the
following was stated under clause 4.1 of the contract:
"Dates of delivery. The stated dates of
delivery have to be met unconditionally, as they are exclusively for sales
promotion purposes, for which in each case approximately 5,000,000 prospectuses
will be distributed. Should the delivery dates not be met, both parties agree
that the seller (apparently what was meant is: the buyer acting as a re-seller
of the umbrellas) recoups all [of its] incurred costs from the seller. This
includes penalties and other costs, with which the buyer will be burdened with
by its customers, as well as consequential damages and costs arising through
substitute transactions. The seller agrees that these costs can be set-off
immediately after the presentation of the relevant documents."
The payment date was stipulated as 15 days after
delivery. If this payment date was not met, [buyer] was supposed to pay the [seller]
1 pro mille interest for each working day; a specification of what the term
"working day" referred to was missing.
Already prior to the signing of the contract on 18 December 1992, the
managing directors of the parties discussed a prefinancing of the contracted
umbrella production, which should be effected by the [buyer's] customers'
acceptances; an agreement to that effect did not materialize. Soon after the
written fixation of the agreement, the parties agreed that contrary to the
agreement, the [seller] would initially deliver a total of 1,500 umbrellas
directly to one of [buyer's] customers. With a letter of 22 February 1993, the
[buyer] gave specific instructions for the shipment of these umbrellas. The
[seller] followed these instructions and sent the [buyer's] customer 800
umbrellas on 26 February 1993 and another 700 on 1 March 1993. Concerning the
800 umbrellas sent on 26 February 1993, the [seller] had already issued
invoices which were sent to the [buyer]; for the umbrellas sent on 1 March 1993
other invoices were issued. Already with fax of 19 February 1993, the [seller]
had requested in broken German "a confirmation when the 1,500 umbrellas
would be paid for".
By letter of 23 February 1993, the [seller] terminated the contract of 7/18
December 1992 with immediate effect, because of the financial situation and the
prepared privatization of its company. Later on the same day [seller] received
another order via phone for 4,000 umbrellas, to which it responded by fax
of 24 February 1993. Therein [seller] confirmed the delivery of 3,000
umbrellas, but urgently requested payment for the already delivered 1,500
umbrellas and a confirmation of the payment for the additional 3,000 announced
umbrellas. After having learned the delivery address via fax, dated 1 March
1993, the [seller] sent the other 3,000 umbrellas between 2 and 10 March and
issued according invoices.
Apparently as a reaction to the [seller's] urgent request for a confirmation
of payment for the already delivered and the imminent delivery of a total of
4,500 umbrellas (total value: DM 268,500), the [buyer] sent to the [seller] on
25 February an international bank payment order given to [buyer's] bank. The
order was in favor of the [seller]; on it was affixed an entry stamp of the
instructed bank. Without informing the [seller] previous to the delivery of the
3,000 umbrellas, the [buyer] revoked this payment order. The [seller]
consequently did not receive payment for any of the umbrellas delivered in the
year 1993 up to the present date.
Instead, the [buyer] sent the [seller] an invoice for damages of DM
622,197.18 on 4 March 1994. The invoice concerned damages which arose from the
[seller's] non-performance of the contract, which the [buyer] now alleged; this
sum also included costs for complaints regarding the deliveries made in the
year 1992. Furthermore, starting from 24 March 1993 the [buyer] sent the
[seller] additional orders for umbrellas, while referring to the agreement of
7/18 December 1992. The [seller] was unable to manufacture and deliver these
umbrellas due to the liquidity problems on account of the non-performance of
the payment order. A conversation on 26 August to settle the matter was
unsuccessful.
In the agreement of 30 June 1995, the parties stipulated that "disputes
arising from the present contractual relationship are to be solved under
Austrian law".
As a matter of law, the Court of First Instance was of the opinion that the
[seller], due to the revocation of the payment order by the [buyer], should
have noticed that the [buyer] was unwilling to comply with its payment
obligations. The [seller] was thus correct in refraining from further
deliveries. [Seller] could not be accused of breaching the contract; therefore,
the damages objection raised by the [buyer] did not have a legal foundation. As
the [seller] was not in delay with its delivery, the Court did not need to
determine whether a firm deal had been agreed to. The parties had settled the
claims in arrears for the year 1992 and the balance had been paid by the
[buyer], so that the [seller] could only request payment for the deliveries
executed in the year 1993. The contractual stipulation regarding default
interest was so incomprehensible that the only option consisted in awarding the
legal interest rate. Due to [parties'] agreement Austrian law was to be
applied.
The decision of the Court of Appeals
The [buyer] appealed the decision of the Court of First Instance regarding
the part in which the [seller's] claim was granted. The Court of Appeals
affirmed the judgment of the Court of First Instance to this extent and
declared that an orderly final appeal was not permissible. The Court of Appeals
held that the [seller's] avoidance of contract of 23 February 1993 had been
premature, as at this point in time a delivery had not yet been effected for
the year 1993. Consequently, the notice of avoidance could not have any effect.
It was undisputed that at the time of the intended payment dates, the
deliveries for the months February and March 1993 had not been paid for,
especially since the payment order had subsequently been revoked. Furthermore,
the fact that the [seller], in spite of its termination notice, had accepted
further orders on the same day and had complied with these, made it clear that
[seller] itself did not want to be bound by its notice of termination (which had
been issued prematurely).
The Court of Appeals held that according to Art. 1(1)(a) and (b) CISG, the
rules of the Convention had to be applied to the present installment contract.
[Seller] and [buyer] had their places of business in different Contracting
States and Austrian law was applicable because of the determined choice of
law. Art. 73(2) CISG entitles one party to an installment contract to declare
the contract avoided for the future, if one party's failure to perform any of
its obligations in respect of any installment gives the other party good
grounds to conclude that a fundamental breach of contract will occur with
respect to future installments.
According to Art. 7(2) CISG, questions concerning matters governed by the
Convention which are not expressly settled in it are to be decided in
conformity with the general principles on which the Convention is based or, in
the absence of such principles, in conformity with the law applicable by virtue
of the rules of private international law. Consequently, the provisions of the
Convention were to be supplemented by the rules of Austrian civil law, as the
law chosen by the parties. Under these rules for installment contracts, the
objection of a non-fulfilled contract could not only be raised against the
immediate corresponding installment, but had to be granted extensively. The
seller who is to perform first may retain the next mature installment if the
preceding one has not been paid for, as the exchange relationship relevant to
the objection not only exists between the corresponding installments, but
between the entirety of the reciprocal obligations. Due to the [buyer's]
default in payment, the [seller] was entitled to hold back further installments,
which was why the Court could not find [seller] at fault. This, however, was a
prerequisite for a successful claim of damages by the [buyer]. The Court did
not allow an orderly appeal on points of law due to the lack of a legal
interest in accordance with § 502(2) ZPO ( = Austrian Civil Procedure Act).
The findings of the Supreme Court
The [buyer's] exceptional appeal on points of law against the judgment of
the Court of Appeals is admissible, for there is no existing case law by the
Supreme Court on the question whether the objection of an insecurity suspension
may be based on national law in the sphere of the application of the CISG. The
appeal is justified regarding the secondary motion to set aside the appealed
decisions.
The [buyer] submits in its appeal that Art. 73(2) CISG grants the other
party only a right of avoidance, of which the [seller] did not make proper use,
as its notice of avoidance was premature. [Buyer] holds that there was no
reason to grant the [seller] a right of retention contrary to the wording of
Art. 73(2). By taking recourse to Art. 7(2), the Court circumvented the
requirement to give an explicit notice of avoidance. Furthermore, the Court of
Appeals did not examine whether the payment for the umbrellas delivered between
25 February until 10 March 1993 could have been expected from the [buyer] and
whether the future performance of the contract was unreasonable for the
[seller] following the default in payment. [Buyer] submits that it did not
revoke the payment order without reason, but because the [seller]:
a) On 2 February 1993 requested -- contrary to the
parties' agreement -- payment of DM 200,000 combined with a threat to stop the
production;
b) After failure of this threat, invoiced its --
not even delivered -- dead stock with invoices of 6 January and 11 February;
c) After failure of this step, terminated the
contract prematurely on 23 February;
d) After failure of this step, requested advance
payment on 24 February 1993 for the first actual delivery of the umbrellas; and
e) Forced on the [buyer] its dead stock, which did
not comply with the specifications of the contract, by threatening to otherwise
deliver nothing.
Admittedly, the [buyer] had breached the contract by failing to pay for the
first delivery of 25 February 1993. However, at this point in time it was
already obvious to its that it would suffer immense damages, as it was clearly
visible after the [seller's] last deliveries that it would not be able to
deliver goods in conformity with the contract. The [buyer] submits that its
claims for damages were therefore principally legitimate and that the lower
instances would have had to make findings concerning the matter.
The Supreme Court considered as follows
The Court of Appeals was correct in its finding that the CISG is the
applicable law for the assessment of the obligations resulting from the sales
contract between the parties, respectively the consequences of a breach of
contract. The parties have their respective places of business in different
States. Even though the sales contract was concluded prior to the ratification
of the CISG in the Czech Republic on 1 January 1993 (see Posch in
Schwimann, Kommentar zum ABGB, 2d ed., vol. 5, Introduction to the CISG, n. 11),
Art. 1(1)(b) CISG states that the Convention is also to be applied when the
rules of private international law lead to the application of the law of a
Contracting State (see SZ [*] 69/26). Thereby, it
has to be noted that § 35 in connection with § 11 IPRG [Austrian Code on
Private International Law] also constitute rules of private international law
as addressed by Art. 1(1)(b) CISG. If the parties, as in the present case,
choose the law of a member State of the CISG, the CISG is to be applied even
without an express statement that the parties wish to apply it (Posch, op.
cit., Art. 1 CISG n. 20).
As the Court of Appeals correctly stated, the [seller's] avoidance of
contract on 23 February 1993 was premature, as at this point in time a delivery
for the year 1993 had not yet been effected. However, contrary to the opinion
of the Court of Appeals, the legal consequences of the (subsequent) default in
payment of the [buyer] are not to be determined under Austrian law.
Irrespective of the right to avoid individual installments of an installment contract,
Art. 71 CISG offers a right of suspension (cf. Schneider/Straub in
Honsell, Kommentar zum UN-Kaufrecht, Art. 73 n. 105). According to this rule, a
party has the right to suspend the performance of its obligations if, after the
conclusion of the contract, it becomes apparent that the other party will not
perform a substantial part of its obligations, as a result of (a) its serious
deficiency in its ability to perform or its creditworthiness, or (b) its
conduct in preparing to perform or in performing the contract (Art. 71(1)
CISG). Art. 71 CISG excludes all legal remedies of the applicable national law,
which are envisaged for the situation that -- subsequent to the conclusion of
the contract -- serious doubts arise whether the other party is able to perform
its obligations. A recourse to broader retention rights of the national law is
therefore excluded (cf. Magnus in Staudinger, Kommentar zum BGB, vol.
13, Art. 71 CISG n. 40; Herber/Czerwenka, Internationales Kaufrecht, Art. 71 n.
16). The right of suspension according to Art. 71 CISG exists independent of
the right to avoid an installment contract pertaining to individual
installments; the aggrieved party may choose between exercising one or the
other legal remedy (cf. Schnyder/Straub, op. cit., Art. 73 n. 105).
According to Art. 71 CISG, all "serious" circumstances that put
the orderly performance at risk may be considered as indicators that the
performance is jeopardized, as well as economic difficulties including a lack
of creditworthiness (Art. 71(1)(a) CISG). Furthermore, a risk may result from
the debtor's conduct in performing or preparing to perform the contract (Art.
71(1)(b) CISG). A serious lack of creditworthiness, as alleged by the [seller],
is present if insolvency proceedings have been opened regarding the debtor's
property or if the debtor has stopped its payments or deliveries (cf. Magnus,
op. cit., Art. 71 CISG n. 25, Leser in von Caemmerer/ Schlechtriem, Kommentar
zum einheitlichen UN-Kaufrecht, 2d ed., Art. 71 n. 11). Singular delayed
payments or a sluggish mode of payment are normally not sufficient to show a
serious loss of creditworthiness (cf. Magnus, op. cit., Art 71 CISG n.
25; Leser, op. cit., Art. 71 CISG n. 11; Pilz, Internationales Kaufrecht, § 4
n. 252). The Court of Appeals held that the [seller] possessed a right to
retention under § 1052 AGBG [Austrian Civil Code], due to the [buyer's] default
in payment of the deliveries from the February and March 1993. These grounds
are not sufficient to legitimize a right of suspension according to Art. 71
CISG. Furthermore, the revocation of the payment order does also not show a
serious lack of creditworthiness on the part of the [buyer] with high
probability -- such a degree is necessary in order to establish a right of
suspension according to Art. 71 (Karollus, UN-Kaufrecht 87; Magnus, op. cit.,
Art. 71 n. 18; Leser, op. cit., Art. 71 n. 17).
It follows that the reasons enlisted by the lower courts to support a right
of suspension on the part of the [seller] are not suited to grant such a right
under Art. 71 CISG. Consequently, the [buyer's] counterclaim cannot be simply
dismissed. However, the [seller] has also alleged that it learned through its
inquiries that the [buyer], which supposedly presented itself as a flourishing
and stable company at the time of the conclusion of the sales contract, had
encountered considerable financial difficulties. This allegation was submitted
with regard to § 1052 AGBG. The submission will need to be discussed with the
parties during the continued proceedings on the basis of the above-mentioned
principles regarding Art. 71 CISG. If required, the necessary facts will have
to be established.
If the [seller] did not possess a right to suspend its performance, the
[buyer] would be entitled to seek damages according to Arts. 45(1), 74 to 77
CISG. However, the established facts do not reveal whether the [seller] failed
to perform its obligations under the contract, because the content of the
agreement between the parties has not been determined.
The Court feels compelled to note in this context that the [buyer] also
claims damages for a non-conforming performance. This claim may be legitimate,
as the Convention requires that the aggrieved party be put in the same position
that it would have been in if the other party had not committed an objective
breach of its contractual obligation, but effected an orderly performance (SZ [*] 69/26 with further reference). However, the [seller] also
raised the objection that the [buyer's] notice of lack of conformity was
belated. According to Art. 38 CISG, the buyer must examine the goods or cause
them to be examined within as short a period as is practicable in the
circumstances. According to Art. 39(1) CISG, the buyer loses the right to rely
on a lack of conformity of the goods if it does not give notice to the seller
specifying the nature of the lack of conformity within a reasonable time after
it has discovered it or ought to have discovered it. The legal consequences of
a failure to notify the seller of a lack of conformity, respectively the
failure to give an orderly notice, is that the buyer loses all legal remedies
pertaining to the respective lack of conformity. This is, unless the seller
acted in faulty manner in the meaning of Art. 40 CISG and unless the buyer
possesses a reasonable excuse for its failure to give the required notice (Art.
44 CISG; cf. Karollus, op. cit., 127). In such a case, the buyer loses
all claims for damages derived from the non-conformity of the goods, if it does
not have a reasonable excuse for its failure to give the required notice
(Karollus, op. cit.). On the basis of the facts established by the Court of
First Instance the Supreme Court cannot determine whether the goods delivered
by the [seller] were defective, whether the notice of non-conformity was given
in time and whether and which damage the [buyer] suffered as a result of the
defective goods. Therefore, the Court had to set aside the judgments of the
lower instances. The Court of First Instance is directed to supplement the
proceeding in the manner discussed.
The ruling on the costs is based on § 52(1) ZPO [Austrian Code on Civil
Procedure].
FOOTNOTES
* All translations should be verified by cross-checking against the original text. For purposes of this translation, the Czech Plaintiff-Respondent is referred to as [seller], the Austrian Defendant-Appellant as [buyer]. Monetary amounts in German currency (Deutsche Mark) are indicated as [DM].
Translator's note on other abbreviations: SZ = Entscheidungen des österreichischen Obersten Gerichtshofes in Zivilsachen [Official Reporter on the decisions of the Austrian Supreme Court in Civil Matters]
** Peter Feuerstein is an International Legal Consultant. He conducted his post graduate studies at Cambridge University, England, where he researched at Clare College in preparation of his Doctoral Dissertation. He received his Dr. jur. from Philipps-University of Marburg, Hessia, Germany, in 1977.
*** Ruth M. Janal, LL.M. (UNSW) is a Phd candidate at Albert-Ludwig-Universität Freiburg.
Case text (English translation)
Austrian Supreme Court (Oberster Gerichtshof )
Pace Law School
Institute of International Commercial Law - Last updated February 7, 2007
Comments/Contributions
Go to Database Directory || Go to CISG Table of Contents
|| Go to Case Search Form || Go to Bibliography