Hungary 10 December 1996 Budapest Arbitration proceeding Vb 96074 (Caviar case) [English text]
[Cite as: http://cisgw3.law.pace.edu/cases/961210h1.html]
Primary source(s) for case presentation: Case text
DATE OF DECISION:
JURISDICTION:
TRIBUNAL:
JUDGE(S):
CASE NUMBER/DOCKET NUMBER: VB 96074
CASE NAME:
CASE HISTORY: Unavailable
SELLER'S COUNTRY: Yugoslavia (claimant)
BUYER'S COUNTRY: Hungary (respondent)
GOODS INVOLVED: Caviar
Case law on UNCITRAL texts (CLOUT) abstract no. 163
Reproduced with permission from UNCITRAL
A Yugoslav company sold and delivered caviar to a Hungarian company. According to their contract "the buyer has to pick up the fish eggs at the seller's address and take the goods to his facilities in Hungary". Payment was due two weeks after the delivery of the goods, at which time the UN embargo against Yugoslavia took effect in Hungary. The [seller] assigned the claim for the price of the goods to a company located in Cyprus. The [buyer] acknowledged the assignment, but could not pay on the basis that the UN embargo was a force majeure.
The arbitral court found that the damage caused by force majeure had to be borne by the party to whom the risk had passed, i.e., the [buyer]. In this connection, the arbitral court found it necessary to point out that the risk of freight had to be borne by the [buyer], unless the contract of the parties or the applicable law provided otherwise (article 67 CISG). The [buyer] could not be exculpated by proving that the damage was owing to an act or omission of the [seller] (article 66 CISG).
Accordingly, the arbitral court held that the [buyer] was obliged to pay the price of the delivered goods with interest.
APPLICATION OF CISG: Yes [Article 1(1)(a)]
APPLICABLE CISG PROVISIONS AND ISSUES
Key CISG provisions at issue: Articles
Classification of issues using UNCITRAL classification code
numbers:
79G [Force majeure occurring after delivery of goods]
Descriptors:
English: Unilex database [Clout abstract]
Polish: Hermanowski/Jastrzebski, Konwencja Narodow Zjednoczonych o umowach
miedzynarodowej sprzedazy towarow (Konwencja wiedenska) - Komentarz (1997) 293-294
CITATIONS TO TEXT OF DECISION
Original language (English): Text of case presented below
Translation: Unavailable
CITATIONS TO COMMENTS ON DECISION English: Thiele, 2 Vindobono Journal (1998) 3-35, citing this case [n.59] and 42 other interest rulings; Petrochilos, Arbitration Conflict of Laws Rules and the CISG (1999) nn.40, 70; Flambouras, Transfer of risk (1999) nn.18, 73, 276; [2004] S.A. Kruisinga, (Non-)conformity in the 1980 UN Convention on Contracts for the International Sale of Goods: a uniform concept?, Intersentia at 133; [2005] Schlechtriem & Schwenzer ed., Commentary on UN Convention on International Sale of Goods, 2d (English) ed., Oxford University Press, Art. 66 para. 4; Schwenzer & Fountoulakis ed., International Sales Law, Routledge-Cavendish (2007) at p. 474Classification of issues present
Editorial remarks
Citations to other abstracts, case texts and commentaries
CITATIONS TO OTHER ABSTRACTS OF DECISION
Reproduced with permission from the Arbitration Court of the Hungarian Chamber of Commerce and Industry
Választottbiróság
10 December 1996 VB/96074
In case of . . . Claimant . . . versus . . . Respondent [Buyer] . . . for payment of [a sum of money] with costs and interests the court of arbitration has brought today and delivers to the process parties . . . the following
Award
The Court of Arbitration obliges . . . [Buyer] to pay . . . (Claimant)
a) US $93,127 (ninety three thousand one hundred twenty seven US dollars), as well as
b) 8% interest on the amount of US $15,000 (fifteen thousand) from May 28, 1992 until payment,
c) 8% interest on the amount of US $78,127 (seventy eight thousand one hundred and twenty seven US dollars) from November 23, 1995 until payment,
d) US $5,309 (five thousand three hundred and nine US dollars) which this Court of Arbitration established as costs of arbitration, and
e) US $3,500 (three thousand five hundred US dollars) recognized by this Court of Arbitration as attorney's fee due to Claimant.
[Buyer] is obliged to pay all these amounts (indicated under a-e) within 30 days after the receipt of the present Award.
Further demands of the Claimant pertaining to interest are denied.
Reasons for the Award
[Seller] a Yugoslav company exported caviar to [Buyer]. Delivery took place on May 28, 1992, Hungarian customs clearance was affected on May 29, 1992. It was not contested by [Buyer] that delivery was according to the contract in every respect. The price agreed upon between [Seller] and [Buyer] was US $93,127 -- and it was never paid. . . . [Seller] asked [Buyer] to pay the outstanding amount to four beneficiaries. [Buyer] agreed to it. On July 21, and on July 28, 1992 [Buyer] attempted to pay and gave orders to its bank to effect payment to the Cyprus beneficiaries, but failed. [Buyer] informed [the] beneficiaries the payments were not effected due to the UN sanctions against Yugoslavia. During the . . . sanctions the parties made repeated endeavours to settle the outstanding debt of [Buyer]. The sanctions represented force majeure. In its letter of June 14, 1994 [Buyer] declare d that "the purchase of caviar stock has happened, but declare that fulfillment of payment is limited by force majeure." On December 26, 1994, a written agreement was reached . . . This agreement confirms that the new creditor is . . . the present Claimant in this arbitration case, since it paid to earlier creditors the amount of US $93,127. . . . [Buyer] accepted this change of creditors, it confirmed that its basic debt is US $93,127 and agreed to pay costs and interests on standard banking rates. [Buyer] answered to Claimant on May 26, 1995 that UN sanctions prevented the payment. After the UN sanction[s] were lifted, Claimant repeated its demands for payment on November 23, 1995, as well as on December 21, 1995. In its letter of January 29, 1996 [Buyer] stated that it does not contest the debt, but proposed arbitration which Claimant finally accepted.
Loss of or damage to the goods after the risk has passed to the Buyer does not discharge him from his obligation to pay the price, unless the loss or damage is due to an act or omission of the Seller (Art 66 of the Vienna Convention).
The Yugoslav material law has the same solution as the German, Austrian or Hungarian law when it says the title to ownership passes simultaneously when the goods are taken over by Buyer.
The Court of Arbitration came to the conclusion that the risk and the ownership has passed to Buyer . . . in accordance with the Contract at Kladovo. The [Buyer] could not exculpate itself proving the damage is due to an act or omission of Seller or he could not either prove Seller had known about the re-export intent of [Buyer]. In the opinion of the Court of Arbitration this means the damage caused by force majeure has to be borne by the party where the risk is at the moment the force majeure occurs. The Court of Arbitration finds it necessary [to] point out that the risk of the freight has to be borne by the Buyer unless the Contract of the parties or the applicable law otherwise provides (Art 67 of the Vienna Convention). Therefore, the Court of Arbitration stated that the claim of the Claimant is well founded and obliged [Buyer] to pay the Claimant the US $93,127 principal sum.
Claimant requested the payment of 8% interest on the principal sum of US $93,127 -- starting from May 1992 until payment. This position was reiterated by Claimant during the oral hearing. [Buyer] did not contest the rate of interest, but contested the principal claim, and -- by implication -- contested the justification for interest payment.
The Vienna Convention on the International Sale of Goods (chosen by the parties as applicable law) does not contain relevant provisions on interest for delay. Therefore, the arbitrators have to establish the applicable law by virtue of the relevant Hungarian conflict rules applicable on ground of Article 14(2) of the Rules of Proceedings of this Court of Arbitration. The relevant conflict rule is contained in §24 of the 1979 Hungarian Act on Private International Law. According to this provision, the applicable law is the substantive law of the Seller -- which is in this case Yugoslav law. In Yugoslavia, the relevant norms on interest on default are contained in the 1978 Act on Obligations (articles 277-279 in particular) as well as in the 1993 Act on the Amount of Interest on Default.
The Yugoslav rules referred to above have not made it perfectly clear whether interest on default is only due when delay in payment is attributable to the fault of the debtor, or whether such interest is a simple consequence of the objective fact that payment was not made in time. Article 277 of the Act on Obligations, and Article 1 of the Act on the Amount of Interest on Default simply state that interest on default is owed if the debtor is late with payment. In recent Yugoslav scholarly writings two justices of the Supreme Court of Serbia have taken a position that interest on default is due when the debtor is responsible for the delay. According to Justice Latinovic, "Interest on default is a consequence of breach of contract by the debtor . . ." (Z. Latinovic, Zatezna kamatazbog docnje u placanju novcane obaveze, Pravni zivot 9-10/1992, 1426, at p. 1428). In the words of Justice Maljkovic "Interest on default regarding pecuniary claims is due from the moment the debtor is in default." (B. Maljkovic, zatezna kamata na novcano potrazivanje nenovcane stete, Pravni zivot 9-10/1992, 1436, at p. 1438.) Under Yugoslav law, there is no default if lack of performance is not imputable to the debtor. At the same time, according to Article 262 (4) of the 1978 Act on Obligations, the debtor will be responsible even if his performance became impossible, if it became impossible after the debtor fell into default. We shall be guided by these rules.
The UN sanctions had created a rather peculiar situation regarding the distribution of liabilities for failure to perform. We have established in this award that [Buyer] is liable to pay the purchase price notwithstanding whether he was or was not able to make proper use of the goods. Respondent/Buyer became responsible for the goods before the UN sanctions became effective in Hungary (they became effective on June 3, 1992 by virtue of Government Order No. 91/1992.) As far as payment is concerned, according to the Purchase Agreement of May 21, 1992, Buyer was supposed to pay US $15,000 before delivery, while the balance was due "within two weeks after delivery". This means that with respect to US $15,000 -- Buyer was in default before the sanctions became effective, he could have and should have paid at a date when payment was possible and his status of being a defaulting party cannot be changed by a later force majeure under Article 262(4) of the Yugoslav Act on Obligations. This is not the case, however, with respect to the balance of US $78,127. With respect to this latter amount [Buyer] was not in default on June 3, 1992, the sanctions effectively thwarted payment. As a matter of fact, Claimant acknowledges in the statement of claim that in July 1992, [Buyer] made attempts to pay, but this was hindered by the UN sanctions. The payment of this amount became only possible when the UN sanctions were suspended. Suspension became effective on November 22, 1995 at 24:00 hours. (Resolution of the UN Security Council No. 1022/1995 -- Published in Hungary in Magyar Közlöny No. 102/1995.) Therefore, from November 23, 1995, [Buyer] was in default with the payment of the amount of US $78,127 -- short of convincing evidence to the contrary -- and no such evidence was presented.
On ground of these considerations the arbitrators have concluded that [Buyer] owes:
a) 8% interest on the amount of US $15,000 from May 28, 1992, until payment:
b) 8% interest on the amount of US $78,127 from November 23, 1995, until payment.
Dated this 10th December, 1996
Arbitrator |
Chairman |
|
Arbitrator |