ICC Arbitration Case No. 7660 of 23 August 1994 (Battery machinery case) [English text]
[Cite as: http://cisgw3.law.pace.edu/cases/947660i1.html]
Primary source(s) for case presentation: Text of case
DATE OF DECISION:
JURISDICTION:
TRIBUNAL:
JUDGE(S):
CASE NUMBER/DOCKET NUMBER: 7660 of 1994
CASE NAME:
CASE HISTORY: Unavailable
SELLER'S COUNTRY: Italy (defendant)
BUYER'S COUNTRY: Czechoslovakia (claimant)
GOODS INVOLVED: Machinery and other items: the production, delivery and installation of a complete automatic assembly line for batteries
Case abstract ARBITRATION: ICC International Court of Arbitration case no. 7660 of 1994 Case law on UNCITRAL texts (CLOUT) abstract no. 302 Reproduced with permission from UNCITRAL A Czech buyer, plaintiff, and an Italian seller, defendant, concluded a contract for the production,
delivery and installation of a complete automatic assembly line for batteries, which was to be delivered
to a Czech company X. The buyer sued the defendant requesting partial avoidance of the contract,
payment of damages arising out of undelivered spare parts and indemnification of a pending third-party
claim. The arbitral tribunal held that there was no dispute between the parties that their choice of law, Austrian
law, included the application of the CISG. Citing article 3(1) CISG, the arbitral tribunal determined that
the contract fell within the scope of the CISG. The arbitral tribunal allowed the buyer's claim regarding undelivered spare parts and granted the buyer
interest in the amount due under articles 78 and 84 CISG from the maturity of the first promissory
notes according to article 84(1) CISG. The arbitral tribunal stated that, as the CISG was silent on the
amount of interest (articles 78 CISG and 84 CISG), and, on the basis of article 7(2) CISG, Austrian law
had to be applied in order to determine this issue. Given that the contract price, though valued in Lira,
was due in DM at an exchange rate agreed by the parties, the arbitral tribunal held that any refund,
including interest, should also be due in DM at the same rate. The arbitral tribunal disallowed the buyer's claim for avoidance of part of the contract. The arbitral
tribunal noted that article 51(1) CISG provided for a partial avoidance of the contract as declared by the
buyer, and that under article 51(2) CISG such partial avoidance was the rule rather than the exception
in cases of partial non-performance amounting to a non-fundamental breach of the contract (article
49(1)(a) CISG). In view thereof, the arbitral tribunal determined that a partial avoidance under article
51(1) CISG was permissible where the defective piece of machinery formed an independent part of the
contracted goods as it was in the case at issue. However, the arbitral tribunal further determined that
the buyer's partial avoidance was barred by the 18-month time limit contained in the contract. It further
noted that according to article 6 CISG the parties by agreeing on an 18-month warranty period had also
reduced the two-year time limit provided for in article 39(2) CISG to a one and half year time limit. The
arbitral tribunal noted that the CISG was silent as to "prescription periods", and therefore Austrian law
had to govern such issue. The arbitral tribunal rejected the buyer's claim for indemnification of a pending claim filed by company
X in the Prague court against it, as the buyer had not suffered any damage yet as required by article 74
CISG.
APPLICATION OF CISG: Yes [Article 1(1)(b)]
APPLICABLE CISG PROVISIONS AND ISSUES
Key CISG provisions at issue: Articles
Classification of issues using UNCITRAL classification code
numbers:
4B [Scope of Convention (issues excluded): statute of limitations];
7C23 [Gap-filling: recourse to general principles on which Convention is
based];
39B3 [Requirement to notify seller of lack of conformity: cut-off period of
two years, effect of guarantee period];
49A1 [Buyer's right to avoid contract: grounds for avoidance, fundamental
breach of contract];
51A1 [Delivery or conformity of only part of goods: rules on avoidance apply
to part missing or non-conforming];
74C [Damages: loss suffered as consequence of breach];
78A ; 78B ; 84A [Interest on delay in receiving price or any other sum in
arrears; Seller bound to refund price must pay interest; Rate of interest]
EDITOR: Albert H. Kritzer
The contract was entered into by a seller from Italy
(a Contracting State) and a buyer from Czechoslovakia (not then a
Contracting State). The tribunal stated: "According to the contract,
Austrian law governs the merits of this dispute." The CISG was in effect in
Austria at the time of the conclusion of the contract. The tribunal ruled
that Austrian law governs the issues in dispute and that, pursuant to
Article 1(1)(b), this includes the CISG.
CISG issues ruled upon:
Interest (right to, accrual of, rate of). In assessing the claim for
non-delivered spare parts, the tribunal ruled that buyer is entitled to
"interest in the amount due under applicable law (Articles 78 and 84 CISG)":
"As to the starting date, interest for reimbursement of the
purchase price runs from the date of payment (see Article 84(1) CISG) . . . .
[Buyer] is entitled to interest from the maturity of the first promissory
notes."
"As to the amount of interest, Articles 78 and 84 CISG are silent
on the matter. . . . [U]nder applicable (see Article 7(2). CISG) Austrian law,
the statutory litigation interest applicable to commercial matters is 5%
(see Section 352 HGB). . . ."
Exchange rates. As a remedy against currency fluctuations, "the
contract price -- though valued in Lira -- was due in DM" calculated at a
specified exchange rate. The tribunal stated: "[A]ny refund, including
interest, should also be due in DM at the same rate. This is . . .
corroborated by Article 84(1) which shows that the Convention takes the
perspective of the date of payment rather than repayment."
Avoidance (avoidance of part of a contract). The tribunal stated
that avoidance of part of a contract is permissible:
"Article 51(1) CISG provides for a partial withdrawal as declared by
[buyer]. As Article 51(2) CISG shows, partial withdrawal is the rule rather than
the exception in cases of partial non-performance amounting to a
non-fundamental breach of the contract (see Article 49(1)(a) CISG). . .
.
"Therefore, a partial withdrawal under Article 51(1) of the
Convention is permissible where the defective piece of machinery forms an
independent part of the contracted goods. Independence of the b-machine is
suggested not only by the fact that the contract separately lists and values
it, but also because the b-machine was replaceable by a different
[manufacturer's] b-machine while continuing to use the remainder of the
contracted units together with the substitute.
However, the tribunal ruled that buyer's avoidance was not timely.
Statute of limitations/Prescription periods/Freedom of contract.
The contract contained a time-bar provision (an "18
month-latest" clause). Referring to this as a prescription period, the tribunal
remarked that, as permitted by Article 6,
this contract clause derogated from and varied the effect of the 24 month
latest-notice period recited in Article 39(2). Of particular
significance to this case, it served as a limitation or
prescription period for the bringing of the action.
Applying Austrian law to the prescription issue (because "[t]he Convention
is silent on the run of prescription periods"), the tribunal ruled that as
buyer's Request for Arbitration was filed after the 18-month-latest-period
ran out, relief under buyer's avoidance claim is barred.
Damages. The tribunal rejected buyer's claim for indemnification of a
pending third-party claim on other grounds, stating:
"Buyer's claim for damages is one for indemnification in view of XYZ's claim
now pending in the Prague court. As that court has not yet ruled on
[buyer's] liability to XYZ it is clear that -- as of now -- [buyer] has not
suffered any damage as required by Article 74 CISG. This is also true with
respect to [buyer's] further argument that the amount due to [buyer] but
withheld by XYZ should be treated as damages. Indeed, also the lawsuit
between [buyer] and XYZ is still pending so that . . . for that reason there
is -- as of now-- no damage that [buyer] has suffered. Accordingly, the
claim must be rejected. . . ."
The tribunal also took occasion to remark on the nature of a damages claim
under Article 74, stating: "Damages under Article 74 CISG do not include the
restitution of the contract price already paid by [buyer] to [seller].
English: Unilex database <http://www.unilex.info/case.cfm?pid=1&do=case&id=48&step=Abstract>
French: Bulletin de la Cour Internationale d'Arbitrage de la Chambre de
Commerce Internationale (November 1995) 68
Italian: Diritto del Commercio Internazionale (1995) 234, No. 54
CITATIONS TO TEXT OF DECISION
Original language (English): ICC International Court of
Arbitration Bulletin (November 1995) 69-72
Translation (French): Bulletin de la Cour Internationale
d'Arbitrage de la Chambre de Commerce Internationale (November 1995) 68-71
CITATIONS TO COMMENTS ON DECISION
English: Van Alstine, 146 University of Pennsylvania Law Review (1998) 767 n.336 [interest issues]; Ferrari, International Legal Forum (4/1998) 138-255 [188 n.429 (analysis of Art. 3(1)), 217 n.715 (choice of law of Contracting State), 226 n.794 (scope of CISG: statute of limitations), 242 n.964, n.917 (Art. 39(2) can be derogated from)]; Honnold, Uniform Law for International Sales (1999) 345 [Art. 51]; Lookofsky, Understanding the CISG in the USA [CISG/USA] (1995) 16 n.37, 71 n.46; Lookofsky, CISG/Scandinavia (1996) 21 n.64, 87 n.57; Bernstein/Lookofsky, CISG/Europe (1997) 8 n.42, 18 n.53, 90 n.56; Bonell/Liguori, Uniform Law Review (1996-1) 147 [150-151 n. 21, n. 23] [cited as 23 August 1993]; for analysis of the remedy of avoidance citing this and other cases, go to Kazimierska, Pace Review of the Convention on Contracts for the International Sale of Goods (1999-2000) n.n.84, 285, 418; Petrochilos, Arbitration Conflict of Laws Rules and the CISG (1999) n.56; Bernstein & Lookofsky, Understanding the CISG in Europe, 2d ed., Kluwer (2003) §: 1-4 n.46; §: 2-7 n.96; §: 6-8 n.72; CISG-AC advisory opinion on Examination of the Goods and Notice of Non-Conformity [7 June 2004] (this case and related cases cited in addendum to opinion); [2005] Schlechtriem & Schwenzer ed., Commentary on UN Convention on International Sale of Goods, 2d (English) ed., Oxford University Press, Art. 3 para. 6a Art. 4 para. 21 Art. 39 para. 26 Italian: Liguori, Foro italiano (1996-IV) 145 [154 n. 42, n. 44] [cited as 23 August 1993]
German: Schlechtriem, Internationales UN-Kaufrecht (1996) 18 n.34, 106 n.124; Will, UN-Kaufrecht und internationale Schiedsgerichtsbarkeit (1999) nn.9, 16
Spanish: Perales, Cuadernos Jurídicos 3 (1996) No. 43, 5 [7 n.
29] [commentary on Article 78: determination of rate of interest under the CISG (review of case law)]; Castellanos, Autonomia de la voluntad y derecho uniforme en la compraventa internacional, thesis, Carlos III de Madrid (1998) 154 n.332, 157-158 Classification of issues present
Editorial remarks
Scope of the CISG. The contract was for the production, delivery and
installation of a "complete automatic assembly line for batteries". Citing
Article 3, the tribunal ruled that the contract falls within the scope of
the CISG.
Citations to other abstracts, case texts and commentaries
CITATIONS TO OTHER ABSTRACTS OF DECISION
Pace Law School Institute of International
Commercial Law - Last updated February 15, 2007
Comments/Contributions
Go to Database Directory || Go to CISG Table of Contents
|| Go to Case Search Form || Go to Bibliography