France 14 June 2001 Appellate Court Paris (Aluminium and Light Industries Company v. Saint Bernard Miroiterie Vitrerie) [translation available]
[Cite as: http://cisgw3.law.pace.edu/cases/010614f1.html]
DATE OF DECISION:
JURISDICTION:
TRIBUNAL:
JUDGE(S):
CASE NUMBER/DOCKET NUMBER: RG No. 1998/38724; 2000/13970
CASE NAME:
CASE HISTORY: 1st instance Tribunal de commerce de Paris 10 May 2000; 3d instance Cour de Cassation 24 September 2003
SELLER'S COUNTRY: France (defendant)
BUYER'S COUNTRY: United Arab Emirates (plaintiff)
GOODS INVOLVED: Decorated laminated glass panels
FRANCE: Cour d'appel de Paris 14 June 2001
Case law on UNCITRAL texts (CLOUT) abstract no. 481
Reproduced with permission of UNCITRAL
The buyer, a company with its headquarters in the United Arab Emirates placed an order with the seller, a French company, for 128 decorated laminated glass panels for the construction of a dome in an Egyptian hotel. The buyer noted when the goods arrived at the port of Dubai in February 1997 that 35 of the panels were unusable because the decorative films had come unstuck and were creased. On 26 February 1997 the buyer sent a fax to the seller stating that "the product does not meet the required standards". The buyer had a number of amicable expert evaluations carried out with a view to finding out whether the lack of conformity of the goods was due to a manufacturing fault or a transport fault, but the reports produced conflicting results. On 6 May 1998 the buyer brought an action against the seller and claimed avoidance of the contract as well as restitution of the price with interest and payment of damages.
The Commercial Court of Paris dismissed the buyer's claims on the grounds that the buyer did not prove with certainty the origin of the defect in the glass panels.
The Court of Appeal of Paris disagreed with the reasoning of the Commercial Court, but nonetheless ruled the buyer's claim inadmissible. The Court stated first of all that CISG was applicable to the present contract, which it characterized as a sales contract rather than a contract for services. The Court observed that "the work required for the manufacture of decorated laminated glass cannot be regarded as the supply of labour or services under article 3(2) CISG".
However, the Court determined that the claim for avoidance of the contract and the secondary claims for restitution of the price and payment of damages were inadmissible because avoidance had not been declared within a reasonable time, as required by article 49(2) CISG. The claim for damages was also found to be inadmissible. In determining whether avoidance had been declared within a reasonable time, pursuant to article 49(2), the Court referred to the date on which the court action was brought -- 6 May 1998 -- whereas notice of non-conformity of the goods was given on 26 February 1997. With regard to the point at which the period of time commenced, the Court expressed hesitation. Initially, the Court cited the date on which notice of the defects was given; subsequently, in view of the amicable expert evaluations carried out to determine precisely the origin of the defects, it cited the submission of the last evaluation report on 22 August 1997 and concluded that "the claim for avoidance of the contract, made more than eight months after the event, could not be regarded as having been made within a reasonable time".
In the last part of the ruling, the Court noted in addition that the buyer's claims were inadmissible on the merits, in view of the impossibility of determining with certainty the origins of the defects in the goods, since the defects could have been caused wholly or partly by the transport or storage conditions, which were the responsibility of the buyer.
APPLICATION OF CISG: Yes
APPLICABLE CISG PROVISIONS AND ISSUES
Key CISG provisions at issue:
Classification of issues using UNCITRAL classification code numbers:
Descriptors:
CITATIONS TO OTHER ABSTRACTS OF DECISION
English: Unilex database <http://www.unilex.info/case.cfm?pid=1&do=case&id=761&step=Abstract>
CITATIONS TO TEXT OF DECISION
Original language (French): CISG-France website <http://Witz.jura.uni-sb.de/CISG/decisions/140601v.htm>; see also Unilex database <http://www.unilex.info/case.cfm?pid=1&do=case&id=761&step=FullText>
Translation (English): Text presented below
CITATIONS TO COMMENTS ON DECISION
English: [2005] Schlechtriem & Schwenzer ed., Commentary on UN Convention on International Sale of Goods, 2d (English) ed., Oxford University Press, Art. 49 para. 32; Henschel, The Conformity of Goods in International Sales, Forlaget Thomson (2005) 275
French: Witz, [2002] Journal du Droit International 488-497, Obs.
Go to Case Table of ContentsQueen Mary Case Translation Programme
Société Aluminium and Light Industries Company v. SARL Saint Bernard Miroiterie Vitrerie
Translation by [*] Audrey Turquois [**]
Translation edited by Camilla Baasch Andersen [***] RG No, 1998/38724
REPUBLIC OF FRANCE
PARTIES. Appellant: Société A and L … Industries Co. of Sharjah, United Arab Emirates, [buyer];
Appellee: SARL S … B … Miroiterie Vitrerie of Paris, France [seller]. COMPOSITION OF COURT.
During the arguments and the deliberation: Président: Mr. Main; conseillers: Mr Fauchere and Mrs.
Briottet; greffier [Clerk of the Court] during arguments and entry of the ruling: Mrs. Laissac. Ruling
rendered by Mr. Main, président, signed transcript of ruling with Mrs. Laissac, greffier.
I. FACTS AND PLEADINGS
Société A and L … Industries Co. [buyer] ordered 128 decorated glass panels from SARL S … B …
Miroiterie Vitrerie [seller], which subcontracted the manufacture to company C, which itself
subcontracted the assembly of the goods to company IVB CH, while the packaging was subcontracted by
[seller] to SNEM.
Asserting that the goods did not conform to the contract, the [buyer] sued the [seller] in order to obtain the
avoidance of the contract, restitution of the price and damages. By judgment of 10 May 2000, the French
Court of First Instance rejected these claims considering that the [buyer] did not prove the origin of the
defects observed.
The [buyer] seeks the reversal of that ruling.
1. [Buyer's position]
The [buyer] requests that the Appellate Court:
2. [Seller's position]
The [seller] requests that the Appellate Court:
[…]
[II. REASONING OF THE APPELLATE COURT]
[1.] Applicability of the CISG
The CISG is applicable to the contract concerned, which is not a contract of supply of services but a
contract of sale of goods since the [seller] has no obligation to furnish labor or other services which, in the
case of preponderance, would prevent the application of the CISG by virtue of Article 3(2) CISG. Indeed,
even if the work required to manufacture the decorated glass panels ordered by the buyer were
preponderant in comparison with the obligation to furnish the raw materials, it could not characterize the
contract as one for supply of labor and other services as understood by Article 3(2) CISG.
[2.] Evaluation of the buyer's claims
By virtue of Article 49(2) CISG, in cases where the seller has delivered the goods, the
buyer loses the right to declare the contract avoided if the buyer does not declare this
(in respect of any breach other than late delivery) within a reasonable time after the buyer
knew or ought to have known of the breach, or after the expiration of any additional
period of time fixed by the buyer in accordance with Article 47(1) CISG, or after the
expiration of any additional period of time indicated by the seller.
Being a "vente à l'usine", the delivery occurred on 7 January 1997, when the goods were taken in
Montreuil under the responsibility of and with the risk passed to [buyer], before their carriage by sea to
Dubai.
According to [buyer]'s own declarations, the [buyer] noticed, as soon as the goods arrived in Dubai, that
some panels had apparent defects making them, along with the rest of the goods, unusable. On 26
February 1997, the [buyer] informed the [seller] of these defects and of [buyer]'s opinion that "we noticed
that the goods do not comply with the required norms". Nevertheless, [buyer] did not sue the [seller] for
avoidance of the contract before 6 May 1998.
According to the [buyer], the avoidance of the contract could not be sought before the results of the
amicably agreed expert examination since, until then, the liability of the [seller] could not be established
with certainty.
Nevertheless, the observation of the non-conformity of the goods with the order, obliged the [buyer] to sue
for the avoidance of the contract without waiting for the results of the amicably agreed expert's report; the
[seller] admitting only the reality of the defaults but denying his liability - only a contradictory judicial
expert examination would have established with certainty the cause of the defects and the subsequent
liability.
Even if the last report of the amicably agreed expert was considered as the starting point of the reasonable
time period in which to sue, provided by Article 49(2) CISG, the claim for the avoidance of the contract,
arising eight months later, does not comply with this provision.
Therefore, the claim for the avoidance of the contract and the subsequent claims of restitution of the price
and payment of damages by the [buyer], who lost his right to declare the contract avoided, are not
recoverable.
Considerant a titre surabondant [In addition to the fact that the present claim is unsuccessful for the
above reasons, the Court adds that] the claim would have failed, since no contradictory judicial expert
examination was carried out or can be carried out because of [1] the long period of time since the delivery
[of the goods] and [2] the parties' lack of knowledge concerning the conditions of storage of the panels.
The reports presented by the [buyer] on the basis of unilateral examinations and analysis cannot establish
with certainty that the defect is due to the manufacture or the packaging by the [seller], which would
characterise a fundamental breach of the contract. Indeed, according to report M, criticized by the [buyer],
the cause of the defect is in the transportation; according to report L, which the [buyer] argues comes from
an independent expert, the source of the default is "probably" due to the cleaning of the triple layer of
glass using a solvent of hydrocarbon with chlorine; but the report of the "Centre experimental de
recherches et d'études du batiment et des travaux publics", whose independence is not criticized by either
party, gives no opinion about the origin of the defects. The report merely states that they are signs of too
much humidity in the PVB, which can result from a manufacturing atmosphere with a humidity ratio of at
least 25%, but that the conditions of carriage by sea can reveal the same phenomenon of bubbles and
peeling without being the reason for it; the storage of the products at various temperatures can also be the
cause of the superficial condensation.
Thus, considering this divergent technical information, it is not possible to determine with certainty the
cause or the causes of the defects which appeared on the goods as soon as they arrived in Dubai, and thus
to assert that they are accountable to the [seller], since they were not noticed at the moment of the delivery
and transfer of the risks to the [buyer], and could be totally or partially due to the condition of
transportation or of storage, which were under the responsibility and at the risk of the [buyer].
[…]
The Appellate Court:
[…]
Reverses the judgment of the Court of First Instance, except when it applied the CISG,
[and the opinion] stated regarding the expenses and Article 700 of the new Code of Civil
Procedure;
Declares that the claim of the [buyer] for the avoidance of the contract with the
[seller] and the subsequent claims (restitution of the price and damages) are unfounded;
Holds that the [buyer] will bear the expenses of the appeal (f 12,000) and will guarantee the
[seller] against his condemnation pronounced by the Court of First instance and by this
Court towards the guarantees in accordance with Article 700 of the new Code of Civil
Procedure;
[…]
FOOTNOTES
* All translations should be verified by cross-checking against the original text. For purposes of this translation, the Plaintiff/Appellant Société T…diffusion of the United
Arab Emirates is referred to as [buyer]; the Defendant/Appellee Société M…SL of France is
referred to as [seller]. Monetary amounts in the currency of France [French francs] are
indicated by [f].
** Audrey Turquois, has a DJCE Masters Degree in Commercial & Tax Law from University of
Poitiers in France, and is currently taking her LL.M. degree at Queen Mary, University of
London. The second-iteration redaction of this translation was by Dr. John Felemegas of
Australia.
Go to Case Table of Contents
Case text (English translation)
Court of Appeal (Cour d'appel ) of Paris, 14 June 2001
In the name of the French People
-
Declare that the CISG is applicable to the contract concerned;
-
Declare the non-conformity of the panels with the order, the default of manufacture and the improper packaging of the goods;
-
Declare that the [seller] failed to perform his obligation under Article 35 CISG;
-
Declare, by virtue of Article 49 CISG, the avoidance of the contract;
-
Consequently, order the restitution of the price (f [French francs] 1,467,000), the payment of interest at a rate of 8.5% per annum, damages (f 500,000) and a sum of f 50,000 pursuant to Article 700 of the new Code of Civil Procedure.
-
Affirm the judgment of the Court of First Instance which rejected the claim of the [buyer] and order the payment of f 5,000 by the [buyer] to the [seller] pursuant to Article 700 of the new Code of Civil Procedure;
-
Reverse the judgment when it declares that the CISG is applicable, ruling that the contract concerned is a contract of supply of services and reject the [buyer]'s claims;
-
Declare, if the Convention [CISG] is held to be applicable, that the [buyer] lost the right to sue for the avoidance of the contract by virtue of Article 49(2) CISG;
-
Order, as subsidiary claim, that company C, manufacturer, and/or company SNEM, which packed the goods, to pay instead of [seller] or to provide a guarantee for the sums that [seller] could be ordered to pay.
Pace Law School
Institute of International Commercial Law - Last updated December 2, 2005
Comments/Contributions
Go to Database Directory ||
Go to CISG Table of Contents
|| Go to Case Search Form || Go to Bibliography